Deadline calendar: German energy transition
27 dates are coming up in the next 90 days. Search for a keyword or pick a market role.
- As of: 14 October 2026
- 58 upcoming
- Where it gets tight ↓
Book an implementation check →
30 minutes on the project that's pressing for you right now. No sales loop.
Deadlines
Upcoming deadlines
58 upcoming deadlinesSubscribe to the calendaror download the file (ICS)only for the selected role
A classification for typical market roles, not a review of your individual case and not legal advice. Whether an obligation applies to your company (thresholds, exemptions) is for your legal department or counsel to confirm. The calendar doesn't replace your own deadline review.
What the labels mean
Each deadline shows what kind of date it is (applies from, due by, comments by, decision) and how binding it is. Without a label in the row, the date is adopted: the law, ruling or technical rule is final, and the details name its basis. "Not yet adopted" is a draft, and its date can still move. Consultations and targets oblige no one. A filled dot marks an adopted date, a ring an open or non-binding one. The "Level" filter refers to the selected market role; without a role it shows every deadline where any role has that level.
No deadline matches . Try a shorter term or all roles.
Q4 2026
20 deadlinesComments by16 October 2026aFRR at the Czech border: consultation on the capacity method closes
Ruling Chamber 6 is consulting on the proposal by the German, Austrian and Czech TSOs to amend the probabilistic method for cross-zonal capacity available for exchanging aFRR. Comments are due by 16 October 2026.
If the deadline is missed: No direct legal consequence Commenting is voluntary. Parties that do not comment by 16 October 2026 do not bring their objections into this procedure; only the method approved by the Federal Network Agency becomes binding. Legal basis ↗
Applicability: Concerns the control areas bordering the Czech Republic; the German-Austrian aFRR cooperation is not affected.
- Transmission system operatorcheck applicabilityCan comment on the amendment proposal until 16 October and checks whether cross-border aFRR procurement at the Czech border changes.Typically affected: Grid control system / SCADA, Trading and procurement system (ETRM)
Read the article → Source ↗ Procurement, trading & market design Information as of: 14 October 2026 Discuss the implementation →
Comments by21 October 2026Redispatch without balancing: consultation on cost reimbursement closes
Ruling Chamber 8 is consulting on how DSOs reimburse costs when redispatch measures are not specifically balanced. Comments are due by 21 October 2026, with the final ruling targeted by year end.
If the deadline is missed: No direct legal consequence Comments are voluntary. Anyone who submits nothing by 21 October 2026 can no longer bring objections into this consultation; Ruling Chamber 8 then publishes the final ruling. Legal basis ↗
- Electricity grid operatoraffectedCan comment until 21 October and models which reimbursements arise without targeted balancing.Typically affected: Regulatory management, controlling, Grid usage and customer billing
- Balance responsible partycheck applicabilityAssesses how the reimbursement affects balancing groups.Typically affected: Trading and procurement system (ETRM)
- Plant operator (generation)check applicabilityAssesses whether reimbursement for curtailed plants is calculated differently.Typically affected: Plant master data and MaStR
Linked to: Redispatch 2.0: choice of settlement method for 2027
Read the article → Source ↗ Flexibility, storage & grid charges Information as of: 14 October 2026 Discuss the implementation →
Due by25 October 20262027 levies: publication by the transmission system operators
The transmission system operators publish the 2027 CHP levy and offshore grid levy by 25 October. Suppliers and grid operators carry the values into price sheets and grid fee billing.
Law · adopted
If the deadline is missed: Regulator can enforce The Federal Network Agency monitors publication under Section 62(1) no. 1(a) EnFG and can order it using its EnWG powers. Breaching an enforceable order is an administrative offence under Section 63(1) no. 2 EnFG, with fines of up to EUR 200,000. Legal basis ↗
Applicability: Transmission system operators; indirectly all electricity suppliers and electricity DSOs.
- Electricity grid operatoraffectedElectricity DSOs apply the levies as a surcharge on grid withdrawal in their 2027 price sheets.Typically affected: Grid usage and customer billing, Regulatory management, controlling
- Transmission system operatorrole obligationTransmission system operators publish the 2027 levies on time on their joint website.Typically affected: Regulatory management, controlling, Customer and grid connection portal
- SupplieraffectedSuppliers carry the levies into 2027 pricing and price change letters.Typically affected: Grid usage and customer billing, SAP IS-U / S/4HANA Utilities
Source ↗ Procurement, trading & market design Information as of: 14 October 2026 Discuss the implementation →
Comments by26 October 2026Electricity efficiency benchmarking: data collection consultation closes
Ruling Chamber 8 is consulting on which data electricity DSOs must supply for the efficiency benchmarking of the fifth regulatory period. Comments are due by 26 October 2026; the data collection follows afterwards.
If the deadline is missed: No direct legal consequence Commenting is voluntary. Operators that do not comment by 26 October 2026 do not bring their objections into this procedure; which data must be supplied only becomes binding with the final decision. Legal basis ↗
Applicability: Electricity DSOs in the standard incentive regulation procedure; the simplified procedure may differ.
- Electricity grid operatoraffectedCan comment on the data catalogue until 26 October and checks which systems the data come from.Typically affected: Regulatory management, controlling, Grid planning, GIS, load flow, SAP IS-U / S/4HANA Utilities
Linked to: NEST: fifth regulatory period, electricity
Part of the bundle: Grid regulation and planning
Source ↗ Grid & low voltage Information as of: 14 October 2026 Discuss the implementation →
Due by31 October 2026Grid expansion plan under section 14d EnWG: first filing
Distribution system operators with 100,000 or more customers submit their first grid expansion plan to the Federal Network Agency, then every two years by 31 October. Smaller operators are covered only if they curtailed more than 3 percent of wind or solar output in each of the two previous years.
Law · adopted
If the deadline is missed: Regulator can enforce Section 14d EnWG sets no penalty of its own. The regulator can order the filing under Section 65(2) EnWG and enforce it with coercive fines under Section 94 EnWG; breaching the enforceable order is an administrative offence under Section 95(1) no. 3(a) EnWG (up to EUR 100,000). Legal basis ↗
Applicability: Only for distribution system operators with 100,000 or more customers. Smaller operators only if more than 3 percent of possible wind or solar output was curtailed in each of the two previous years.
- Electricity grid operatorcheck applicabilityChecks customer count and curtailment share; if covered, submits the plan with congestion analysis and measures to the BNetzA.Typically affected: Grid planning, GIS, load flow, Regulatory management, controlling
Part of the bundle: Grid regulation and planning
Read the article → Source ↗ Grid & low voltage Information as of: 11 October 2026 Discuss the implementation →
Due by31 October 2026Congestion income 2027: report the planned use to the Federal Network Agency
Transmission system operators tell the Federal Network Agency by 31 October how they plan to use the 2027 congestion income from allocating cross-zonal capacity. The basis is Article 4 of the ACER methodology on the use of congestion income under Article 19 of Regulation (EU) 2019/943.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce The ACER methodology sets no sanction of its own. The Federal Network Agency decides on the use by 31 December and can require changes; it can enforce the reporting duty under Section 56(1) sentence 2 and Section 94 EnWG with coercive fines of EUR 1,000 to EUR 10 million. Legal basis ↗
Applicability: Only transmission system operators that earn congestion income from allocating cross-zonal transmission capacity.
- Transmission system operatorrole obligationSubmits the planned use of the 2027 congestion income to the Federal Network Agency by 31 October.Typically affected: Regulatory management, controlling
Source ↗ Procurement, trading & market design Information as of: 13 October 2026 Discuss the implementation →
Due by1 November 2026EEG onshore wind tender: bid deadline 1 November 2026
Bids for onshore wind turbines must reach the Federal Network Agency by the bid deadline. According to the agency, the volume is about 2,495 MW and the 2026 ceiling price is 7.25 cents per kilowatt hour.
Law · adopted
If the deadline is missed: Exclusion or loss of role Bids must reach the Federal Network Agency by the bid date (Section 30a(2) EEG); only bids received in time are opened (Section 32(1) sentence 2 EEG), so a late bid gets no award in this round. A bid is also excluded if the fee or security has not been paid in full by then (Section 33(1) no. 3 EEG). Legal basis ↗
Applicability: Developers and operators of onshore wind turbines holding a federal immission control permit.
- Direct marketercheck applicabilityDirect marketers prepare marketing offers for awarded projects.Typically affected: Direct marketing and remote control
- Plant operator (generation)check applicabilityPlant operators with permitted wind projects assess participation, bid value and security deposit.Typically affected: Plant master data and MaStR, Regulatory management, controlling
Source ↗ Generation & direct marketing Information as of: 11 October 2026 Discuss the implementation →
Due by20 November 2026Price change on 1 January 2027: notice deadline in default supply
Default suppliers changing their general prices on 1 January 2027 must publish the change at least six weeks in advance, notify customers by letter and post it online. For household customers on special contracts, Section 41(5) EnWG sets a one month notice period.
Law · adopted
If the deadline is missed: Civil-law consequence Under Section 5(2) StromGVV and GasGVV a change to general prices only takes effect after public notice at least six weeks in advance; with later notice the new price does not apply from 1 January 2027. For household customers on special contracts Section 41(5) EnWG requires one month's notice but states no express consequence. Legal basis ↗
Applicability: Default suppliers of electricity and gas changing prices on 1 January 2027; special contract suppliers with household customers (one month notice).
- Supplierrole obligationDefault suppliers finish 2027 pricing early enough that publication, customer letters and online notice go out by 20 November 2026 at the latest.Typically affected: Grid usage and customer billing, SAP IS-U / S/4HANA Utilities, Customer and grid connection portal
Linked to: 2027 levies: publication by the transmission system operators, 2027 network charges: publication by 15 October
Source ↗ Market communication & market processes Information as of: 11 October 2026 Discuss the implementation →
Due by30 November 2026Redispatch 2.0: choice of settlement method for 2027
Under ruling BK6-23-241, the plant operator sets the settlement method for each technical resource by 30 November for the following year. Without a decision the simplified peak settlement applies; the flat-rate settlement ends for existing resources at the end of 2028.
Regulatory ruling · adopted
If the deadline is missed: No direct legal consequence Without an assignment decision by 30 November, the simplified peak settlement applies to resources with fluctuating generation (BilAReM chapter 3.2.1); resources already on flat-rate settlement stay there until 31 December 2028 at the latest. The assignment holds for the whole following year. Legal basis ↗
Applicability: Operators of plants from 100 kW and controllable plants within Redispatch 2.0.
- Electricity grid operatoraffectedElectricity DSOs take the assignment into the calculation of curtailed energy.Typically affected: EDM / MDM, Market communication gateway (EDIFACT, AS4, API)
- Balance responsible partyaffectedBalance responsible parties check how the chosen method affects imbalance costs.Typically affected: Trading and procurement system (ETRM)
- Direct marketeraffectedDirect marketers agree with plant operators which method best reflects the balancing compensation in the balance group.Typically affected: Direct marketing and remote control
- Plant operator (generation)affectedPlant operators decide per technical resource between peak, simplified peak or flat-rate settlement and report the choice to the connecting grid operator.Typically affected: Plant master data and MaStR, Market communication gateway (EDIFACT, AS4, API)
Source ↗ Flexibility, storage & grid charges Information as of: 11 October 2026 Discuss the implementation →
Due by1 December 2026EEG ground-mounted solar tender: bid deadline 1 December 2026
Bids for ground-mounted solar plants (first segment) must reach the Federal Network Agency by the bid deadline. According to the agency, the actual volume is about 2,079 MW.
Law · adopted
If the deadline is missed: Exclusion or loss of role Bids must reach the Federal Network Agency by the bid date (Section 30a(2) EEG); only bids received in time are opened (Section 32(1) sentence 2 EEG), so a late bid gets no award in this round. A bid is also excluded if the fee or security has not been paid in full by then (Section 33(1) no. 3 EEG). Legal basis ↗
Applicability: Developers and operators of ground-mounted solar plants above 1 MW.
- Direct marketercheck applicabilityDirect marketers prepare marketing and profile valuation for awarded solar parks.Typically affected: Direct marketing and remote control, Trading and procurement system (ETRM)
- Plant operator (generation)check applicabilityPlant operators with sites and a grid connection commitment assess participation and bid value.Typically affected: Plant master data and MaStR, Regulatory management, controlling
Source ↗ Generation & direct marketing Information as of: 11 October 2026 Discuss the implementation →
Applies from2 December 2026EU AI Act: labelling duty extends to AI already in use
The four-month transition period ends. Generative AI systems placed on the market before 2 August 2026 must mark their output in machine-readable form.
Law · adopted
If the deadline is missed: Fine possible If a provider of generative AI placed on the market before 2 August 2026 does not mark its output in machine-readable form by 2 December 2026 (Art. 50(2) and Art. 111(4) AI Act), the breach can be fined under Art. 99(4)(g) up to EUR 15 million or 3% of worldwide turnover, with the lower amount for SMEs. The same range applies to deployers for disclosing deepfakes (Art. 50(4)). Legal basis ↗
Applicability: Art. 50(2) of the AI Act addresses providers of generative AI systems. Companies that only use bought-in systems are deployers and mainly face disclosure duties under Art. 50(4).
- Company-wide, several rolescheck applicabilityDetermines for each generative AI system whether the company acts as provider and, if so, marks outputs in machine-readable form.Typically affected: AI systems and chatbots, Customer and grid connection portal
Linked to: EU AI Act: classification and transparency obligations
Read the article → Source ↗ IT architecture, data & AI Information as of: 11 October 2026 Discuss the implementation →
Due by29 December 2026Power plant strategy (StromVKG): second auction for long-duration capacity
On 29 December 2026 the Federal Network Agency auctions another 4.5 gigawatts of long-duration capacity. Eligible are generation plants able to feed in 80 percent of their capacity for at least ten consecutive hours, with a 15-year commitment.
Law · adopted
If the deadline is missed: Exclusion or loss of role A bid must reach the Federal Network Agency by the bid date, with no reinstatement (Section 37(1) StromVKG). Bids without the fee or security paid by then are excluded under Section 49(1) no. 1 StromVKG. Legal basis ↗
Applicability: Only generation plants at sites without generation on 30 June 2026 or covered by the exceptions in section 12(3) StromVKG.
- Plant operator (generation)check applicabilityPlant operators assess whether a new build or site meets the conditions and a bid is worthwhile.Typically affected: Plant master data and MaStR, Regulatory management, controlling
Source ↗ Procurement, trading & market design Information as of: 11 October 2026 Discuss the implementation →
DecisionEnd of 2026AgNes: framework ruling on electricity grid charges
Under the draft of 6 August 2026, low-voltage connections up to 100,000 kWh keep a standing charge and an energy charge; those generating behind the connection pay a prosumer surcharge of 70 to 90 percent of the standing charge, plug-in solar devices excepted. Above that, and above low voltage, a capacity price applies, and generation plants above 30 kW pay a feed-in charge. The draft provides dynamic grid charges only for storage (2030 at the earliest, 2033 at the latest) and generation (2032 to 2035), not for final customers for now. Follow-up rulings in 2027, effect from 2029.
If the deadline is missed: No direct legal consequence The date is the Federal Network Agency's. Its notification, set for 1 January 2027 in the draft (operative point 20), starts other cut-offs, such as grandfathering for storage and generation plants with an investment decision before notification, to be proven to the network operator by 31 March 2027. Legal basis ↗
- Electricity grid operatoraffectedPlans billing and tariff systems for the prosumer surcharge, capacity prices and feed-in charges from 2029; under the draft, prosumers are to be identified and reported to suppliers by 1 April 2028.Typically affected: Grid usage and customer billing, Regulatory management, controlling, SAP IS-U / S/4HANA Utilities
- SupplieraffectedPrepares products and billing to pass new network charge components on to customers; under the draft, prosumer status appears on the bill from 1 April 2028.Typically affected: Grid usage and customer billing
Linked to: AgNes: consultation on the grid charge reform closes, MiSpeL: ruling on market integration of storage and charging points
Part of the bundle: Grid regulation and planning
Read the article → Explained in the handbook: chapter 6 → Source ↗ Flexibility, storage & grid charges Information as of: 14 October 2026 Discuss the implementation →
Due by31 December 2026Heating costs ordinance: retrofit remote reading
Heat suppliers retrofit or replace meters installed before 5 October 2021 that cannot be read remotely (FFVAV). Building owners do the same for heat and hot water meters and heat cost allocators (Heating Costs Ordinance).
Law · adopted
If the deadline is missed: Money is lost Where remotely readable equipment is missing contrary to Section 5(3) HeizkostenV, occupants may cut their share of the costs by 3 percent under Section 12(1) sentence 2 HeizkostenV. The FFVAV sets no penalty of its own for heat suppliers; their retrofit duty applies within the supply contract with the customer (Section 1(1) and Section 3(3) FFVAV). Legal basis ↗
Applicability: The FFVAV applies to heat suppliers, the Heating Costs Ordinance to building owners. Metering operators under the MsbG are not addressed.
- Heat network operatorrole obligationRetrofits or replaces heat meters installed before 5 October 2021 that cannot be read remotely, by year end.Typically affected: Field service and work orders, EDM / MDM
- Company-wide, several rolescheck applicabilityChecks for its own buildings and contracting models who carries the retrofit under the Heating Costs Ordinance as building owner.Typically affected: Field service and work orders
Part of the bundle: Metering at year end
Read the article → Explained in the handbook: chapter 2 → Source ↗ Smart metering, SMGW & §14a Information as of: 11 October 2026 Discuss the implementation →
Due by31 December 2026Smart meter rollout: 90 percent of the installation cases since February 2025
By the end of 2026 default metering point operators must have completed at least 90 percent of the metering points that have fallen due since 25 February 2025. According to its press release, the Bundesnetzagentur collects progress twice a year, and it has been running supervisory proceedings against laggards since March 2026.
Law · adopted
If the deadline is missed: Regulator can enforce If the default metering point operator misses the quota, the Federal Network Agency can order measures under Sections 45(2) and 76 MsbG and enforce them with coercive fines of EUR 1,000 to EUR 10 million (Section 76(4) MsbG, Section 94 EnWG). If the rollout of control units falls short by at least 25 percent and this contributes significantly to a possible threat to system security, it can withdraw the default responsibility under Section 12(2g) EnWG. Legal basis ↗
- Default metering point operatorrole obligationFits at least 90 percent of metering points due since 25 February 2025 with smart metering systems by year end.Typically affected: Gateway administration and CLS management, Field service and work orders, SAP IS-U / S/4HANA Utilities
Part of the bundle: Metering at year end
Read the article → Explained in the handbook: chapter 8 → Source ↗ Smart metering, SMGW & §14a Information as of: 14 October 2026 Discuss the implementation →
Due by31 December 2026WPG §32: decarbonisation roadmap for heat networks
Operators of existing heat networks submit the roadmap: 30 percent renewable by 2030, 80 percent by 2040.
Law · adopted
If the deadline is missed: Regulator can enforce The Heat Planning Act sets neither a fine nor a specific power to issue orders for a missing or late roadmap. Compliance is monitored by the authority each federal state designates under Section 33(5) WPG. Legal basis ↗
Applicability: Heat networks already fed entirely by renewable heat, unavoidable waste heat or a combination of both are outside the duty, as are networks under 1 km and networks with an approved BEW transformation plan. The pending WPG amendment would give only operators of industrial heat networks until the end of 2030.
- Heat network operatorrole obligationDraws up the expansion and decarbonisation roadmap for each heat network and submits it to the competent authority.Typically affected: Grid planning, GIS, load flow, Regulatory management, controlling
Read the article → Source ↗ Heat, gas & hydrogen Information as of: 11 October 2026 Discuss the implementation →
Due by31 December 2026Smart meter rollout: 90 percent of new generation capacity up to 100 kilowatts
By the end of 2026 default metering point operators must have equipped at least 90 percent of the generation capacity up to 100 kilowatts that came online between 25 February 2025 and 30 September 2026. The yardstick is installed capacity, not the number of metering points.
Law · adopted
If the deadline is missed: Regulator can enforce If the default metering point operator misses the quota, the Federal Network Agency can order measures under Sections 45(2) and 76 MsbG and enforce them with coercive fines of EUR 1,000 to EUR 10 million (Section 76(4) MsbG, Section 94 EnWG). If the equipping of installations with control units falls short by at least 25 percent and this contributes significantly to a possible threat to system security, it can withdraw the default responsibility under Section 12(2g) EnWG. Legal basis ↗
Applicability: Under the government draft for EEG 2027, the installation quotas in Section 45 MsbG would count metering points to be equipped instead of kilowatts, with the default metering point operator free to choose for this quota at 31 December 2026. Nothing has been adopted.
- Electricity grid operatoraffectedSupplies plant master data from grid connection and the market master data register so the metering operator knows the cases.Typically affected: SAP IS-U / S/4HANA Utilities
- Default metering point operatorrole obligationEquips generation up to 100 kW so that 90 percent of capacity commissioned from February 2025 to September 2026 is covered.Typically affected: Gateway administration and CLS management, Field service and work orders
Part of the bundle: Metering at year end
Read the article → Explained in the handbook: chapter 8 → Source ↗ Smart metering, SMGW & §14a Information as of: 14 October 2026 Discuss the implementation →
DecisionEnd of 2026Gas WACC: the rate of return decision is issued
The Bundesnetzagentur intends to set the flat-rate return on capital for gas grid operators by the end of 2026. Gas distribution operators then calculate the revenue caps of the fifth regulatory period from 2028 with the adopted rate.
If the deadline is missed: No direct legal consequence Issuing the decision by the end of 2026 is the Federal Network Agency's own target. The ruling fixes the rate for gas revenue caps from 2028; it can only be challenged by an appeal within one month of service (Section 78(1) EnWG). Legal basis ↗
- Gas grid operatoraffectedCalculates revenue caps for the fifth gas regulatory period from 2028 with the rate that is set.Typically affected: Regulatory management, controlling
Linked to: Gas WACC: end of the consultation on the rate of return
Part of the bundle: Grid regulation and planning
Read the article → Source ↗ Grid & low voltage Information as of: 11 October 2026 Discuss the implementation →
Due by31 December 2026CHP Act: cut-off for commercial operation or permit of CHP plants, heat networks and heat storage
CHP Act support requires that CHP plants start commercial operation by 31 December 2026, or hold a federal immission control permit or binding order by then and start commercial operation within four years. Support for heat networks and heat storage is also tied to 31 December 2026 (commissioning or all permits under state law in place).
Law · adopted
If the deadline is missed: Money is lost The CHP premium under Section 6(1) sentence 1 no. 1 KWKG is only paid if the plant enters commercial operation by 31 December 2026, or holds an immission control permit or binding order by then and starts commercial operation within four years; awards from CHP tenders are exempt. Similar cut-offs apply to new heat networks and heat storage (Section 18(1) no. 1 and Section 22(1) no. 1 KWKG). Legal basis ↗
Applicability: New, modernised or retrofitted CHP plants and new or extended heat networks and heat storage seeking CHP Act support.
- Plant operator (generation)affectedPlant operators secure commercial operation, permit or binding order for CHP projects by year end.Typically affected: Plant master data and MaStR, Regulatory management, controlling
- Heat network operatoraffectedHeat network operators check whether network and storage projects go live or hold all permits by year end.Typically affected: Plant master data and MaStR, Regulatory management, controlling
Source ↗ Generation & direct marketing Information as of: 11 October 2026 Discuss the implementation →
Due by31 December 2026Regulatory account: application for 2025
Electricity network operators apply for the 2025 regulatory account balance with the regulator by 31 December 2026.
Law · adopted
If the deadline is missed: Regulator can enforce The ARegV sets no penalty of its own, but the application is mandatory under Section 4(4) sentence 3 ARegV; the regulator can order it under Section 65(2) EnWG and enforce it with coercive fines. Under Section 5(3) sentence 3 ARegV the balance is only spread from the second year after the application. Legal basis ↗
Applicability: Operators in the standard procedure; different rules may apply in the simplified procedure or under state regulators.
- Electricity grid operatorrole obligationFiles the 2025 regulatory account application with the competent regulator.Typically affected: Regulatory management, controlling, Grid usage and customer billing
- Transmission system operatorrole obligationFiles the 2025 regulatory account application with the Federal Network Agency.Typically affected: Regulatory management, controlling
Part of the bundle: Grid regulation and planning
Source ↗ Grid & low voltage Information as of: 11 October 2026 Discuss the implementation →
Q1 2027
8 deadlinesApplies from1 January 2027AFIR: ISO 15118-20 for new charging points
From 2027, newly built or renovated publicly accessible charging points and private charging points in modes 3 and 4 must support at least ISO 15118-20. Bidirectional charging and Plug and Charge stay optional; anyone offering Plug and Charge needs both ISO 15118-2 and ISO 15118-20.
Law · adopted
If the deadline is missed: Regulator can enforce For publicly accessible charging points, the Federal Network Agency can require retrofitting and prohibit operation under Section 5(2) and (3) of the Charging Station Ordinance if Annex II to AFIR (Regulation (EU) 2023/1804) is not met. ISO 15118-20 sits in that annex since Delegated Regulation (EU) 2025/656. Legal basis ↗
Applicability: Applies to newly built or renovated charging points; existing ones are exempt. Private charging points only in modes 3 and 4.
- Charge point operatorrole obligationFrom 2027 procures only charging points with ISO 15118-20 and upgrades backend and PKI if Plug and Charge is offered.Typically affected: Charging backend (OCPP, PKI)
Read the article → Source ↗ Sales, portals & e-mobility Information as of: 11 October 2026 Discuss the implementation →
Applies from1 January 2027Grid package: system-serving connection capacity instead of maximum output
The right to a grid connection no longer covers the maximum generation output: for plants connected from 1 January 2027, the draft caps feed-in from new first-segment solar plants at 70 percent of installed capacity and from onshore wind at 280 watts per square metre of rotor area (Section 8 of the draft EEG). By then the transmission system operators submit procedure rules with prioritisation criteria to the Federal Network Agency, and distribution system operators may adopt them. Grid operators show available capacity on grid maps every month; the electronic enquiry procedure from 135 kilowatts only arrives in 2028 under the draft.
If the deadline is missed: Regulator can enforce Under the government bill (Bundestag printed paper 21/7866) the new duties carry no fine of their own. Duties such as the transmission system operators' submission of procedure rules or the monthly capacity map (Sections 17a and 17c of the draft EnWG) could be enforced by the regulator under Section 65 EnWG. Legal basis ↗
- Electricity grid operatorcheck applicabilityMay adopt the transmission operators' prioritisation principles for connection requests and publishes available connection capacity on a map; the bill may still change in parliament.Typically affected: Customer and grid connection portal, Grid planning, GIS, load flow
- Transmission system operatorcheck applicabilitySubmits joint procedure rules with prioritisation criteria for transmission grid connections to the Federal Network Agency by 1 January 2027; the bill may still change.Typically affected: Customer and grid connection portal
Part of the bundle: Grid regulation and planning
Read the article → Source ↗ Grid & low voltage Information as of: 13 October 2026 Discuss the implementation →
Applies from1 January 2027EEG 2027 (government draft): no fixed tariff for new PV below 25 kW
Under the government draft, subject to the Bundestag's decision and EU state aid approval: new PV systems below 25 kW receive a temporary transition payment from the grid operator for at most 36 months instead of the feed-in tariff, then direct marketing with a 1.5 ct/kWh bonus for up to 48 months. Rooftop systems below 100 kW cap feed-in at 50 percent permanently. Systems commissioned by 31 December 2026 stay under the old rules. In the MsbG, mandatory smart meters and control devices for generation start above 2 kW, and the installation quotas in Section 45 count metering points instead of kilowatts. The Bundesrat wants to drop the 2 kW threshold; the federal government rejects that.
If the deadline is missed: No direct legal consequence Under the draft (Bundestag printed paper 21/7867), payment obligations for breaches under Section 52 EEG fall on plant operators; it sets no separate sanction for network operators, metering point operators or suppliers. According to the explanatory memorandum, network operators need software to administer the temporary transition payment. Legal basis ↗
Applicability: Under the draft this only affects new systems commissioned from 1 January 2027. Existing systems stay under the old rules; plug-in solar devices up to 2 kW are exempt.
- Electricity grid operatorcheck applicabilityPrepares EEG settlement for grid operator offtake, transition payment and bonus and checks the 50 percent cap at commissioning; the bill may still change in parliament.Typically affected: Grid usage and customer billing, SAP IS-U / S/4HANA Utilities, Market communication gateway (EDIFACT, AS4, API)
- Default metering point operatorcheck applicabilityPlans the 2 to 7 kW segment into the mandatory rollout with control devices, plus early installations for direct marketing; status government draft.Typically affected: Gateway administration and CLS management, Field service and work orders
- Suppliercheck applicabilityConsiders offering direct marketing for small systems in its own area; status government draft.Typically affected: Market communication gateway (EDIFACT, AS4, API), Grid usage and customer billing
Read the article → Source ↗ Market communication & market processes Information as of: 14 October 2026 Discuss the implementation →
Applies from1 January 2027BSI TR-03109-6 v2.0 for gateway administrators
Gateway administrators have their GWA system assessed against version 2.0 at the next certification or recertification from 1 January 2027. Version 2.0 covers remote workplaces, cloud service providers, zero trust, time servers and penetration tests, among other things. Version 1.0 stays valid until 31 December 2028.
Regulatory ruling · adopted
If the deadline is missed: Exclusion or loss of role Conformity with TR-03109-6 is proven by certification. If the default metering point operator lacks the certificates required under Section 25 MsbG, the fallback metering operator takes over in emergency operation (Section 11(2) no. 2 MsbG) and, six months later, the default responsibility (Section 11(4) MsbG). Legal basis ↗
Applicability: Applies to metering operators that run gateway administration themselves; otherwise the contracted service provider is affected. Version 1.0 stays valid until the end of 2028.
- Default metering point operatorrole obligationMoves gateway administration to version 2.0 at its next certification or recertification from 2027.Typically affected: Gateway administration and CLS management, ISMS and security operations
Part of the bundle: Metering at year end
Read the article → Explained in the handbook: chapter 3 → Source ↗ Smart metering, SMGW & §14a Information as of: 14 October 2026 Discuss the implementation →
Applies from1 January 2027BSI TR-03109-1 v2.0: gateway certificates only with MUSS+
Anyone certifying a smart meter gateway against version 2.0 of the protection profile and TR-03109-1 must also prove the MUSS+ requirements from 1 January 2027. According to the BSI these include a WAN API, registering power metering over the local metrological network and factory reset by the service technician, plus TAF 8 in its new form and TAF 15. By mid-October 2026 no gateway had been certified under version 2.0.
Regulatory ruling · adopted
If the deadline is missed: Exclusion or loss of role Without MUSS+ proof there is no version 2.0 certificate from that date. Without a valid certificate, a smart meter gateway may not be used as part of a smart metering system under Section 24(4) MsbG, and under Section 25(1) MsbG the gateway administrator may only use gateways with valid certificates. Legal basis ↗
Applicability: Addressed to manufacturers that have gateways certified. Metering point operators are affected through procurement and rollout of new devices.
- Default metering point operatoraffectedAsks gateway vendors when devices certified under version 2.0 with MUSS+ will be available and plans procurement and rollout for 2027 and 2028 around those dates.Typically affected: Gateway administration and CLS management, Field service and work orders
- Competitive metering point operatoraffectedAsks gateway vendors when version 2.0 devices can be delivered and plans procurement accordingly.Typically affected: Gateway administration and CLS management, Field service and work orders
Part of the bundle: Metering at year end
Explained in the handbook: chapter 3 → Source ↗ Smart metering, SMGW & §14a Information as of: 14 October 2026 Discuss the implementation →
Due by1 January 2027Fallback metering operator: publication for 2027
At the start of the calendar year the Bundesnetzagentur publishes the name, address and website of the fallback metering operator responsible for each federal state, together with the operators that declared readiness. The basis is the monitoring data under section 35 EnWG.
Law · adopted
If the deadline is missed: No direct legal consequence Publication under Section 11(3) sentence 2 MsbG is a duty of the Federal Network Agency. It shows who takes over emergency operation if a default metering point operator drops out, loses its certificates or lacks approval (Section 11(2) MsbG). Legal basis ↗
Applicability: The duty to publish lies with the Federal Network Agency. For municipal utilities the entry is information, not a deadline of their own.
- Default metering point operatoraffectedChecks the Federal Network Agency's list when handing over metering points or after declaring readiness as fallback operator.Typically affected: Regulatory management, controlling
Part of the bundle: Metering at year end
Read the article → Source ↗ Smart metering, SMGW & §14a Information as of: 11 October 2026 Discuss the implementation →
Applies from1 January 2027AFIR: card payment at existing fast chargers from 50 kW
From 1 January 2027, publicly accessible charging points from 50 kW along the TEN-T road network or at safe and secure truck parking areas must accept ad hoc charging via a card reader or contactless card device, including points built before 13 April 2024.
Law · adopted
If the deadline is missed: Regulator can enforce If a charging point does not meet Article 5(1) AFIR (Regulation (EU) 2023/1804), the Federal Network Agency can require retrofitting under Section 5(2) of the Charging Station Ordinance and prohibit operation under Section 5(3). Legal basis ↗
Applicability: Publicly accessible charging points from 50 kW on the TEN-T road network or at safe and secure parking areas, where charging is paid.
- Charge point operatorrole obligationCharge point operators retrofit affected existing charging points with card readers or NFC terminals and connect payment to backend and billing.Typically affected: Charging backend (OCPP, PKI), Grid usage and customer billing
Source ↗ Market communication & market processes Information as of: 11 October 2026 Discuss the implementation →
Applies from1 March 2027VDE-AR-N 4105:2026-03: end of the transition period
From this date only the 2026-03 edition applies to connecting generation plants to the low-voltage grid. Technical connection conditions, notification forms (F.1.1, F.1.2) and the connection assessment up to 500 kW have to be switched over by then.
Technical rule · adopted
If the deadline is missed: Civil-law consequence The application rule is not a statute and carries no penalty of its own. It sets general minimum technical requirements; conflicting requirements in technical connection conditions are void under Section 19(1a) EnWG, and the regulator can have them removed under Section 65 EnWG. Legal basis ↗
Applicability: Applies to grid operators, installers and plant operators connecting generation plants and storage to the low-voltage grid. Unchanged existing installations are not covered as long as safe and trouble-free operation is assured.
- Electricity grid operatorrole obligationSwitches technical connection conditions, notification forms and the assessment process to the 2026-03 edition and records the applicable edition for every case until then.Typically affected: Customer and grid connection portal, Grid planning, GIS, load flow, Plant master data and MaStR
- Competitive metering point operatoraffectedRegisters generation plants and storage using the new forms and aligns metering concepts with feed-back capable charging equipment treated as storage.Typically affected: Customer and grid connection portal, Grid usage and customer billing
Read the article → Source ↗ Grid & low voltage Information as of: 30 September 2026 Discuss the implementation →
Q2 2027
5 deadlinesApplies from2027, date openEnergy sharing: practical start with the BNetzA platform
Network operators jointly build a nationwide web platform under Section 20b EnWG that also registers energy sharing agreements. The Federal Network Agency sets the date; until then energy sharing runs through the service model.
Law · adopted, date open
If the deadline is missed: Regulator can enforce There is no specific fine. The regulator can enforce the duty under Section 20b(1) EnWG to build the platform jointly through Section 65 EnWG; a binding date only exists once the Federal Network Agency sets one under Section 20b(3) EnWG. Legal basis ↗
- Electricity grid operatorrole obligationTakes part in building and running the joint platform under Section 20b EnWG; the Federal Network Agency sets the date.Typically affected: Customer and grid connection portal, Market communication gateway (EDIFACT, AS4, API)
- Suppliercheck applicabilityChecks whether energy sharing offers have to be registered on the platform once it is live.Typically affected: Customer and grid connection portal
Linked to: Energy sharing under §42c EnWG
Part of the bundle: Market communication and EDM wave
Read the article → Source ↗ Flexibility, storage & grid charges Information as of: 11 October 2026 Discuss the implementation →
Applies from1 April 2027MaKo format release, notice no. 58
On 1 April 2027 ActivationDocument AWT version 1.1g and transport rules version 1.11, including the changes to certificate use with mTLS, become binding. The previously consulted replacement of UTILTS by API web services is off the table.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce The versions are binding under the market communication rulings. The Federal Network Agency can have breaches remedied under Section 65 EnWG, or Section 76 MsbG for metering point operators, and enforce this with coercive fines of up to EUR 10 million (Section 94 EnWG). If a secure connection fails because certificates are missing or invalid, the party that did not provide them or used them incorrectly bears the consequences (transport rules, chapter 12). Legal basis ↗
Applicability: ActivationDocument AWT concerns only market partners involved in redispatch. Transport rules 1.11 apply to exchange via AS2, email (SMTP), SFTP and REST; AS4 has its own rules.
- Electricity grid operatorrole obligationMoves redispatch messages to ActivationDocument AWT 1.1g and updates the transport path to version 1.11.Typically affected: Market communication gateway (EDIFACT, AS4, API), EDM / MDM
- Transmission system operatorrole obligationReceives redispatch calls in ActivationDocument AWT 1.1g format and adjusts certificate use for mTLS.Typically affected: Market communication gateway (EDIFACT, AS4, API), Direct marketing and remote control
- Default metering point operatorrole obligationUpdates the transport path to version 1.11; the planned API replacement of UTILTS is dropped, so UTILTS traffic stays.Typically affected: Market communication gateway (EDIFACT, AS4, API), EDM / MDM
- Supplierrole obligationKeeps UTILTS processing for metering times and calculation formulas and adapts the transport path to version 1.11.Typically affected: Market communication gateway (EDIFACT, AS4, API)
Linked to: MaKo format release, notice no. 56
Part of the bundle: Market communication and EDM wave
Read the article → Explained in the handbook: chapter 7 → Source ↗ Market communication & market processes Information as of: 13 October 2026 Discuss the implementation →
Applies from1 April 2027VDE-AR-N 4100:2026-04: end of the transition period
Projects already in planning or under construction on the cut-off date may be completed under the old edition until this day. After that, only the 2026-04 edition applies to customer installations on the low-voltage grid, including instrument transformer installations with semi-indirect metering up to 1,000 A and the meter-position field for communication modules and control units.
Technical rule · adopted
If the deadline is missed: Regulator can enforce The application rule is not a statute and carries no penalty of its own. Under Section 20 sentence 2 NAV, technical connection conditions must reflect generally accepted engineering standards; the regulator can have breaches of the NAV stopped under Section 65 EnWG. Legal basis ↗
Applicability: Applies to customer installations on the low-voltage grid. Unchanged existing installations are not covered; triggers for an upgrade include a capacity increase, feed-in, controllable consumption devices under Section 14a EnWG and additional grid connections.
- Electricity grid operatorrole obligationUpdates the technical connection conditions to the 2026-04 edition and checks meter position, instrument transformer installations and short-circuit ratings against the new requirements.Typically affected: Customer and grid connection portal, Plant master data and MaStR
- Default metering point operatoraffectedTakes the new meter-position field for communication modules and control units into account in rollout planning and installation specifications.Typically affected: Gateway administration and CLS management, Field service and work orders
Linked to: VDE-AR-N 4105:2026-03: end of the transition period
Read the article → Explained in the handbook: chapter 5 → Source ↗ Grid & low voltage Information as of: 11 October 2026 Discuss the implementation →
Applies from1 April 2027Schedule nomination process description v4.7 becomes binding
From 1 April 2027 version 4.7 of the schedule nomination process description applies to all market participants required to implement it. The changes relate to European market coupling.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce Through Annex 3 the process description is part of the approved balance group contract; the Federal Network Agency can have breaches remedied under Section 65 EnWG. The approved balance group contract (BK6-18-061) provides in clause 20 for a formal warning in case of breaches and extraordinary termination if they recur. Legal basis ↗
- Transmission system operatorrole obligationApplies version 4.7 of the process description in scheduling.Typically affected: Trading and procurement system (ETRM), Market communication gateway (EDIFACT, AS4, API)
- Balance responsible partyaffectedChecks whether the scheduling system supports version 4.7.Typically affected: Trading and procurement system (ETRM)
Part of the bundle: Market communication and EDM wave
Source ↗ Market communication & market processes Information as of: 11 October 2026 Discuss the implementation →
Due by18 May 2027Power plant strategy (StromVKG): auction for generation capacity
On 18 May 2027 the Federal Network Agency auctions 2 gigawatts of generation capacity. Only generation plants are eligible, with a 15-year commitment.
Law · adopted
If the deadline is missed: Exclusion or loss of role A bid must reach the Federal Network Agency by the bid date, with no reinstatement (Section 37(1) StromVKG). Bids without the fee or security paid by then are excluded under Section 49(1) no. 1 StromVKG. Legal basis ↗
Applicability: Only generation plants at sites without generation on 30 June 2026 or covered by the exceptions in section 12(3) StromVKG.
- Plant operator (generation)check applicabilityPlant operators assess whether a new build or site meets the conditions and a bid is worthwhile.Typically affected: Plant master data and MaStR, Regulatory management, controlling
Linked to: Power plant strategy (StromVKG): second auction for long-duration capacity
Source ↗ Procurement, trading & market design Information as of: 11 October 2026 Discuss the implementation →
Q3 2027
1 deadlineApplies fromEnd of September 2027MiSpeL: end of the transition period
Until the end of September 2027 the demarcation option and the flat-rate option can be used only with the consent of the grid operator and the metering operator. Both use that period to set up metering, data delivery and billing for the two options.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce From 1 October 2027 grid and metering operators must enable the demarcation and flat-rate options even without their consent (MiSpeL, operative point 7). If they do not, the Federal Network Agency can order remedies under Section 85(3) EEG with Section 65 EnWG; breaching the enforceable order is an administrative offence under Section 86(1) no. 3 EEG (up to EUR 200,000). Legal basis ↗
Applicability: Concerns sites with storage or charging points in mixed use. The individual steps follow from the operative part and the annexes of the ruling.
- Electricity grid operatoraffectedSets up the processes that let both MiSpeL options run without case-by-case consent by the end of the transition period.Typically affected: EDM / MDM, Grid usage and customer billing
- Default metering point operatoraffectedProvides the metering and data delivery the demarcation option needs at storage and charging sites.Typically affected: EDM / MDM, Field service and work orders
- Storage operatorcheck applicabilityClarifies whether moving to one of the two options pays off during the transition period or only afterwards.Typically affected: Plant master data and MaStR
Linked to: MiSpeL: ruling on market integration of storage and charging points
Part of the bundle: Market communication and EDM wave
Explained in the handbook: chapter 6 → Source ↗ Flexibility, storage & grid charges Information as of: 11 October 2026 Discuss the implementation →
Q4 2027
6 deadlinesApplies from1 October 2027Secure exchange rules for scheduling v2.4 become binding
From 1 October 2027 version 2.4 of the rules for secure exchange in scheduling applies to all market participants required to implement it. It covers transmission channels and certificates for schedule exchange.
Regulatory ruling · adopted
If the deadline is missed: Civil-law consequence The recipient may leave schedule messages that are not properly signed or encrypted unprocessed, and the sender bears the consequences (chapter 7 of the rules). The approved balance group contract (BK6-18-061) provides in clause 20 for a formal warning in case of breaches and extraordinary termination if they recur. Legal basis ↗
- Transmission system operatorrole obligationMoves schedule intake to the version 2.4 security rules.Typically affected: Trading and procurement system (ETRM), ISMS and security operations
- Balance responsible partyrole obligationMoves schedule exchange with the TSO to the version 2.4 security rules.Typically affected: Trading and procurement system (ETRM), ISMS and security operations
Linked to: Schedule nomination process description v4.7 becomes binding
Source ↗ Market communication & market processes Information as of: 11 October 2026 Discuss the implementation →
Applies from29 October 2027REMIT II: new reporting formats and first exposure report
From 29 October 2027 the new data fields apply to continuous transaction reporting to ACER. Market participants with positions of 600 GWh per year or more report exposures quarterly, first in October 2027; balancing service transactions must be reported monthly from 29 April 2028.
Law · adopted
If the deadline is missed: Fine possible Failing, intentionally or recklessly, to report transaction data to ACER under Article 8(1) REMIT, or reporting it incorrectly, incompletely or late, is an administrative offence under Section 95(1c) no. 7 EnWG, with fines of up to EUR 10,000. The Federal Network Agency can also take supervisory measures under Section 65(6) EnWG. Legal basis ↗
Applicability: REMIT market participants with transactions in wholesale electricity and gas products; exposure reporting only from 600 GWh per year, assessed separately for electricity and gas.
- Supplierrole obligationSuppliers trading wholesale switch reporting channels and data fields to the new format and check the 600 GWh threshold for exposure reporting.Typically affected: Trading and procurement system (ETRM), Regulatory management, controlling
- Balance responsible partyaffectedBalance responsible parties supply trade data for the new reporting fields.Typically affected: Trading and procurement system (ETRM)
- Direct marketerrole obligationDirect marketers adapt transaction reports and prepare monthly reporting of balancing service transactions.Typically affected: Trading and procurement system (ETRM), Direct marketing and remote control
- Plant operator (generation)check applicabilityPlant operators trading themselves or offering balancing services check whether they report as market participants.Typically affected: Regulatory management, controlling
- Storage operatoraffectedStorage operators with wholesale or balancing transactions check their reporting duties under the new catalogue.Typically affected: Trading and procurement system (ETRM), Regulatory management, controlling
Source ↗ Procurement, trading & market design Information as of: 11 October 2026 Discuss the implementation →
Due by1 December 2027Capacity market (StromVKG): first technology-open capacity auction
The first capacity auction takes place on 1 December 2027, open to generation plants, electricity storage, controllable loads and plant pools. Prequalification with the responsible transmission system operator is required first; applications are only possible from the seventh to the fifth month before the bid date.
Law · adopted
If the deadline is missed: Exclusion or loss of role Without prequalification the Federal Network Agency excludes a bid under Section 49(2) StromVKG, and prequalification can only be applied for within the window in Section 26(2). A late bid does not count, and there is no reinstatement (Section 37(1) StromVKG). Legal basis ↗
Applicability: Operators of generation plants, electricity storage and controllable loads, and aggregators wishing to bid.
- Transmission system operatorrole obligationTransmission system operators run prequalification on the joint online platform and publish volumes and ceiling prices.Typically affected: Customer and grid connection portal, Regulatory management, controlling
- Direct marketercheck applicabilityDirect marketers and aggregators assess bids for plant pools and small plant pools.Typically affected: Direct marketing and remote control
- Plant operator (generation)check applicabilityPlant operators assess which power or CHP plants to prequalify and offer.Typically affected: Plant master data and MaStR, Regulatory management, controlling
- Storage operatorcheck applicabilityStorage operators assess participation; eligible capacity depends on the maximum delivery duration.Typically affected: Plant master data and MaStR, Regulatory management, controlling
- Company-wide, several rolescheck applicabilityCompanies with controllable loads assess offering load reduction as capacity.Typically affected: Plant master data and MaStR
Source ↗ Procurement, trading & market design Information as of: 11 October 2026 Discuss the implementation →
Applies from2 December 2027EU AI Act: high-risk requirements, Annex III
AI in critical infrastructure and grid operations falls under Annex III; the BNetzA becomes market surveillance authority.
Law · adopted
If the deadline is missed: Fine possible Breaches of the duties of providers (Art. 16) and deployers (Art. 26) of high-risk AI can be fined under Art. 99(4)(a) and (e) of the AI Act up to EUR 15 million or 3% of worldwide turnover, with the lower amount for SMEs. Under Art. 111(2), systems placed on the market or put into service before 2 December 2027 are only covered after a significant change. Legal basis ↗
- Electricity grid operatorcheck applicabilityChecks AI in grid control and control systems for high-risk classification under Annex III.Typically affected: Grid control system / SCADA, AI systems and chatbots
- Company-wide, several rolescheck applicabilityChecks whether AI systems act as safety components in grid operation or in HR and prepares the high-risk obligations.Typically affected: AI systems and chatbots, ISMS and security operations
Linked to: EU AI Act: classification and transparency obligations, KI-MIG: the Bundesnetzagentur becomes market surveillance authority
Read the article → Source ↗ IT architecture, data & AI Information as of: 11 October 2026 Discuss the implementation →
Decision2027AgNes: follow-up rulings that fill in the detail
After the framework ruling at the end of 2026, the Bundesnetzagentur plans to fill in the new system in follow-up rulings during 2027. Distribution system operators plan billing and systems against this detail.
If the deadline is missed: No direct legal consequence The Federal Network Agency issues the follow-up rulings. If they slip, less time remains to convert price sheets, billing and systems before the new system applies from 2029. Legal basis ↗
- Electricity grid operatoraffectedAligns billing and systems with the follow-up rulings once they are published.Typically affected: Grid usage and customer billing, SAP IS-U / S/4HANA Utilities
- Suppliercheck applicabilityChecks which new charge components change tariffs and customer billing.Typically affected: Grid usage and customer billing
Linked to: AgNes: framework ruling on electricity grid charges
Read the article → Explained in the handbook: chapter 6 → Source ↗ Flexibility, storage & grid charges Information as of: 14 October 2026 Discuss the implementation →
Due by31 December 2027SAP ECC and IS-U: end of mainstream maintenance
Extended maintenance until 2030 at a surcharge. Migrations to S/4HANA Utilities take 18 to 36 months.
If the deadline is missed: No direct legal consequence The date is set by SAP, not by law. From 2028 SAP only covers legal changes in extended maintenance, at a premium and until the end of 2030 at the latest; without it the system is no longer adapted to new legal requirements. Legal basis ↗
Applicability: Only affects companies running SAP ECC or IS-U. The date follows from SAP's maintenance strategy, not from law.
- Company-wide, several rolesaffectedPlans the move from SAP IS-U to S/4HANA Utilities or contracts extended maintenance until 2030.Typically affected: SAP IS-U / S/4HANA Utilities
Read the article → Source ↗ IT architecture, data & AI Information as of: 11 October 2026 Discuss the implementation →
Q1 2028
4 deadlinesApplies from1 January 2028NEST: fifth regulatory period, gas
New incentive regulation under the NEST rulings of December 2025. The fifth period lasts five years, to the end of 2032 (RAMEN Gas, operative item 3.1), followed by three-year periods.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce The start of the period triggers no penalty itself; the regulator sets the revenue caps ex officio (RAMEN Gas, operative item 4.1). It can enforce duties under the NEST rulings, such as notifying the capital cost markup by 30 June of the previous year, under Section 65 EnWG. Legal basis ↗
- Gas grid operatorrole obligationEnters the fifth gas regulatory period, which runs for five years; three-year periods follow.Typically affected: Regulatory management, controlling
Linked to: Gas WACC: the rate of return decision is issued
Read the article → Source ↗ Grid & low voltage Information as of: 13 October 2026 Discuss the implementation →
Applies from1 January 2028EU ETS 2 starts: emissions trading for buildings and transport replaces the national BEHG
The regular phase of EU ETS 2 starts on 1 January 2028; the first surrender of allowances for 2028 emissions is due by 31 May 2029. Reporting and surrender duties under the national BEHG continue through 2027.
Law · adopted
If the deadline is missed: Fine possible If an obligated entity does not surrender enough allowances by 31 May, the authority sets a payment of EUR 100 per missing tonne of CO2 equivalent under Section 46(1) TEHG, indexed to inflation since 2012. The allowances must still be surrendered, and the name is published in the Federal Gazette (Section 46(3) and (4) TEHG). Legal basis ↗
Applicability: Obligated entities under BEHG and TEHG placing fuels for buildings, road transport and additional sectors on the market; indirectly all customers.
- Supplierrole obligationGas suppliers placing fuels on the market as obligated entities move monitoring, allowance procurement and price pass-through to EU ETS 2.Typically affected: Trading and procurement system (ETRM), Grid usage and customer billing, Regulatory management, controlling
- Heat network operatoraffectedHeat network operators whose fuels are outside EU ETS 1 factor the EU ETS 2 carbon price into heat prices and indexation clauses.Typically affected: Grid usage and customer billing
- Company-wide, several rolescheck applicabilityCompanies assess carbon costs for fleet and building heat from 2028.Typically affected: Regulatory management, controlling
Source ↗ Procurement, trading & market design Information as of: 13 October 2026 Discuss the implementation →
Applies from1 January 2028BRÜCKEN ruling: provisions for decommissioning and dismantling gas grids
From the fifth regulatory period, allocations to and releases of provisions for decommissioning and unavoidable dismantling of gas grids count as cost shares outside the efficiency benchmark. Operators and lessors of gas grids need a traceable derivation of those provisions in the cost review.
Regulatory ruling · adopted
If the deadline is missed: Money is lost The BRÜCKEN ruling (BK9-25/618) only recognises provisions for necessary decommissioning and unavoidable dismantling. Amounts without a traceable derivation are not recognised as cost shares outside the efficiency benchmark. Legal basis ↗
Applicability: Concerns operators and lessors of gas distribution grids under incentive regulation. The classification takes effect with the fifth regulatory period for gas; how far provisions from the base year count is set out in the ruling.
- Gas grid operatoraffectedDerives the provisions for decommissioning and unavoidable dismantling in a traceable way and submits them in the cost review for the fifth regulatory period.Typically affected: Regulatory management, controlling
Linked to: NEST: fifth regulatory period, gas
Source ↗ Grid & low voltage Information as of: 11 October 2026 Discuss the implementation →
Applies from1 January 2028Smart meter gateways: installation only to version 2.0 of protection profile and TR-03109-1
Under the BSI transition rules, gateways certified to protection profile PP-0073 version 1.3 and TR-03109-1 version 1.1 may only be installed until 31 December 2027, and recertification to that standard can be requested until that date at the latest. After that, version 2.0 applies to newly installed gateways. Devices already in the field can move to the new standard by software update.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce Under Section 19(2) MsbG, only systems that meet Sections 21 and 22 may be used for billing, balancing and grid-related metering and control; the yardstick is the protection profiles and technical guidelines in the version in force, which the BSI publishes under Section 22(2). The Federal Network Agency can act against breaches under Section 76 MsbG. Legal basis ↗
Applicability: Applies to installation. For gateways already in the field, the transition rules point to migration by software update.
- Default metering point operatoraffectedSwitches procurement so that only version 2.0 gateways are installed from 2028 and agrees the software migration of installed devices with vendors and gateway administration.Typically affected: Gateway administration and CLS management, Field service and work orders
- Competitive metering point operatoraffectedUses up old-standard stock by the end of 2027 and installs only version 2.0 gateways from 2028.Typically affected: Gateway administration and CLS management, Field service and work orders
Linked to: BSI TR-03109-1 v2.0: gateway certificates only with MUSS+
Explained in the handbook: chapter 3 → Source ↗ Smart metering, SMGW & §14a Information as of: 14 October 2026 Discuss the implementation →
Q2 2028
2 deadlinesApplies from1 June 2028Energy sharing across the grid boundary
From 1 June 2028 energy sharing must also work across adjacent balancing areas. According to the Federal Network Agency's Notice No. 73, the supplier based service model covers this too, with no further implementation by network operators.
Law · adopted
If the deadline is missed: Regulator can enforce There is no specific fine. If a distribution system operator does not enable shared use with the adjacent balancing area (Section 42c(4) sentence 1 no. 2 EnWG), the regulator can order remedies under Section 65 EnWG. According to the Federal Network Agency's Notice No. 73, the supplier-based service model covers this stage too. Legal basis ↗
- Electricity grid operatorcheck applicabilityChecks coordination needs with the adjacent network operator; per the Federal Network Agency the service model suffices here too.Typically affected: Market communication gateway (EDIFACT, AS4, API)
- Suppliercheck applicabilityChecks whether to offer energy sharing across adjacent balancing areas as a service.Typically affected: Grid usage and customer billing
Linked to: Energy sharing under §42c EnWG
Read the article → Source ↗ Flexibility, storage & grid charges Information as of: 11 October 2026 Discuss the implementation →
Due by30 June 2028WPG: heat plans for all municipalities under 100,000 inhabitants
After the large cities, all remaining municipalities must submit their heat planning; utilities provide the data basis.
Law · adopted
If the deadline is missed: No direct legal consequence The deadline binds the planning bodies, usually municipalities, not the network operators. If grid or heat network operators withhold the information owed under Section 11(1) no. 2 WPG, the planning body can order it with a deadline under Section 11(6) WPG. Legal basis ↗
Applicability: The planning duty lies with municipalities of 100,000 inhabitants or fewer; network operators contribute data.
- Gas grid operatoraffectedAligns gas network areas and conversion paths with municipal heat planning.Typically affected: Grid planning, GIS, load flow
- Heat network operatoraffectedProvides the municipality with data on network, generation and expansion plans for heat planning.Typically affected: Grid planning, GIS, load flow
Read the article → Source ↗ Heat, gas & hydrogen Information as of: 11 October 2026 Discuss the implementation →
Q3 2028
2 deadlinesDue by1 July 2028MaBiS hub: test systems of all market partners ready (BDEW scenario)
Under the BDEW introduction scenario, the test systems of all market partners and of the MaBiS hub are available from 1 July 2028. Every interface to the hub has to pass at least one test by 30 September 2028. Parallel operation starts on 1 January 2029.
If the deadline is missed: No direct legal consequence There is no decision yet in proceeding BK6-24-210, and the date comes from the industry's introduction scenario. It only becomes binding and enforceable under Section 65 EnWG once a ruling sets it. Legal basis ↗
Applicability: The dates are a BDEW proposal that the Federal Network Agency put out for consultation unchanged in procedure BK6-24-210-1. They are not binding: notice no. 58 of 1 October 2026 lists the MaBiS hub ruling as pending.
- Electricity grid operatoraffectedAdapts balancing and data exchange systems to the MaBiS hub interfaces.Typically affected: EDM / MDM, Market communication gateway (EDIFACT, AS4, API)
- SupplieraffectedMoves balancing group processes and data reconciliation to the central MaBiS hub.Typically affected: EDM / MDM, Market communication gateway (EDIFACT, AS4, API)
Read the article → Explained in the handbook: chapter 7 → Source ↗ Market communication & market processes Information as of: 14 October 2026 Discuss the implementation →
Applies from1 July 2028Metering Act Section 40: new gas meters with load profile metering on the smart meter gateway
New gas meters with interval (load profile) metering must be connected to existing smart meter gateways from 1 July 2028 at the latest. Other new gas meters follow once connection is technically possible and causes no extra cost.
Law · adopted
If the deadline is missed: Regulator can enforce Section 40 MsbG sets no penalty of its own. The Federal Network Agency can order compliance under Section 76(2) MsbG and enforce it with coercive fines of EUR 1,000 to EUR 10 million (Section 76(4) MsbG, Section 94 EnWG). Legal basis ↗
Applicability: Newly installed gas meters with interval metering at metering points with an existing smart meter gateway.
- Gas grid operatoraffectedGas DSOs ensure receipt and processing of meter data via the gateway infrastructure.Typically affected: EDM / MDM, Market communication gateway (EDIFACT, AS4, API), SAP IS-U / S/4HANA Utilities
- Default metering point operatorrole obligationDefault gas metering operators plan meter types, interfaces and gateway connection for new interval gas meters.Typically affected: Gateway administration and CLS management, EDM / MDM, Field service and work orders
- Competitive metering point operatoraffectedCompetitive metering operators handling interval gas meters also set up gateway connection.Typically affected: Gateway administration and CLS management, EDM / MDM
Explained in the handbook: chapter 2 → Source ↗ Smart metering, SMGW & §14a Information as of: 11 October 2026 Discuss the implementation →
Q4 2028
2 deadlinesDue byDecember 2028 at the earliest, date openBSIG §39: first evidence for critical installations
Operators of critical installations must prove their security measures through an audit, review or certification, then every three years. The BSI sets the date, at the earliest three years after the installation counts as critical.
Law · adopted, date open
If the deadline is missed: Fine possible Section 39 BSIG does not apply to energy networks and energy installations under Sections 5c to 5e EnWG (Section 28(5) BSIG); for them Section 95(1) nos. 3c and 3d EnWG penalise missing or late documentation. For other critical installations, failing to provide the evidence under Section 39(1) BSIG, or providing it late, is an administrative offence under Section 65(2) no. 10 BSIG, with fines of up to EUR 1 million. Legal basis ↗
Applicability: Only for operators of critical facilities under the BSIG. Section 39 BSIG does not apply to energy supply networks and energy installations subject to Sections 5c to 5e EnWG (Section 28(5) BSIG), so utilities are only affected through other critical facilities.
- Company-wide, several rolescheck applicabilityPrepares audit, inspection or certification if facilities count as critical; the BSI sets the date.Typically affected: ISMS and security operations
Linked to: German NIS2 implementation act in force
Read the article → Explained in the handbook: chapter 3 → Source ↗ Cybersecurity & resilience Information as of: 13 October 2026 Discuss the implementation →
Due by31 December 2028Smart meter rollout: 90 percent of the 2027 to 2028 installation cases
By the end of 2028 default metering point operators must have equipped at least 90 percent of the metering points that fall due for installation in 2027 and 2028.
Law · adopted
If the deadline is missed: Regulator can enforce If the default metering point operator misses the quota, the Federal Network Agency can order measures under Sections 45(2) and 76 MsbG and enforce them with coercive fines of EUR 1,000 to EUR 10 million (Section 76(4) MsbG, Section 94 EnWG). If the rollout of control units falls short by at least 25 percent and this contributes significantly to a possible threat to system security, it can withdraw the default responsibility under Section 12(2g) EnWG. Legal basis ↗
- Default metering point operatorrole obligationFits at least 90 percent of metering points due in 2027 and 2028 with smart metering systems.Typically affected: Gateway administration and CLS management, Field service and work orders
Linked to: Smart meter rollout: 90 percent of the installation cases since February 2025
Read the article → Explained in the handbook: chapter 8 → Source ↗ Smart metering, SMGW & §14a Information as of: 11 October 2026 Discuss the implementation →
Q1 2029
4 deadlinesApplies from1 January 2029§14a EnWG: end of the transition period
Preventive control is only allowed until 31 December 2028; from 2029 grid operators control solely on a grid-oriented basis using grid state assessment, which has applied to new installations since 2024. The old §14a rules end on the same date: legacy installations above 4.2 kW with a reduced network charge move into the new rules, night storage heaters keep the old arrangement, and the rest lose the reduction.
Regulatory ruling · adopted
If the deadline is missed: Regulator can enforce From 1 January 2029 ruling BK6-22-300 no longer permits preventive control (Annex 1 item 10.5), and the new rules apply to legacy installations above 4.2 kW with the old §14a reduction (item 10.2). The Federal Network Agency can order a breach to stop under Section 65 EnWG and enforce this with coercive fines under Section 94 EnWG. Legal basis ↗
Applicability: Controllable consumption devices at low voltage above 4.2 kW: non-public charging points, heat pumps, air conditioning and battery storage. Pre-2024 installations without a §14a reduction stay outside but may switch voluntarily.
- Electricity grid operatorrole obligationReplaces preventive control with grid-oriented control by 31 December 2028 at the latest, announces the switch to device operators and suppliers in advance, and moves legacy installations above 4.2 kW with the old §14a reduction into the new rules on 1 January 2029.Typically affected: Grid control system / SCADA
- Default metering point operatoraffectedProvides control units and gateway connections for legacy installations that move into grid-oriented control on 1 January 2029.Typically affected: Gateway administration and CLS management, Field service and work orders
Linked to: Smart meter rollout: 90 percent of the installation cases since February 2025
Read the article → Explained in the handbook: chapter 5 → Source ↗ Smart metering, SMGW & §14a Information as of: 13 October 2026 Discuss the implementation →
Applies from1 January 2029AgNes: new grid charge system takes effect
StromNEV expires on 31 December 2028; the BNetzA rulings replace the ordinance.
If the deadline is missed: Regulator can enforce Under the draft ruling (operative point 1.2), only grid charges under the AgNes system are permitted from 1 January 2029. A network operator that bills otherwise can be ordered by the regulator to comply under Section 65 EnWG. Legal basis ↗
- Electricity grid operatoraffectedBills network charges from 2029 under the Federal Network Agency's new framework instead of the StromNEV.Typically affected: Grid usage and customer billing, Regulatory management, controlling
- SupplieraffectedPasses the new network charge structures on in tariffs and bills from 2029.Typically affected: Grid usage and customer billing
Linked to: AgNes: follow-up rulings that fill in the detail
Read the article → Explained in the handbook: chapter 6 → Source ↗ Flexibility, storage & grid charges Information as of: 11 October 2026 Discuss the implementation →
Applies from1 January 2029NEST: fifth regulatory period, electricity
New electricity incentive regulation under the NEST rulings; the fifth period lasts five years (RAMEN Strom, operative item 3.1). From 2029 network reliability feeds into the revenue cap as a bonus or deduction, while network performance indicators are only published for now.
Regulatory ruling · adopted
If the deadline is missed: Money is lost From 2029 the regulator sets annual bonuses or deductions on the revenue cap where a network operator's reliability deviates from the reference value (quality element, ruling GBK-24-02-1#4, operative item 5.4.1). It can enforce other duties under the NEST rulings under Section 65 EnWG. Legal basis ↗
- Electricity grid operatorrole obligationEnters the fifth electricity regulatory period; from 2029 network reliability affects the revenue cap as a quality element.Typically affected: Regulatory management, controlling
Read the article → Source ↗ Grid & low voltage Information as of: 13 October 2026 Discuss the implementation →
Applies from1 January 2029Customer installations: transition period for existing installations ends
For customer installations under Section 3 nos. 65 and 66 EnWG connected by 23 December 2025, grid regulation rules only apply from 1 January 2029. Operators of such installations clarify by then whether and which regulatory requirements apply to them.
Law · adopted
If the deadline is missed: Regulator can enforce From 1 January 2029 the grid regulation rules also apply to these existing installations (Section 118(7) EnWG). If they are not met, the regulator can order measures under Section 65 EnWG; breaching the enforceable order is an administrative offence under Section 95(1) no. 3(a) EnWG (up to EUR 100,000). Legal basis ↗
Applicability: Operators of customer installations and customer installations for in-house supply connected by 23 December 2025.
- Electricity grid operatoraffectedElectricity DSOs expect requests on metering concepts, takeover or grid connection of former customer installations.Typically affected: Market communication gateway (EDIFACT, AS4, API), EDM / MDM, Grid planning, GIS, load flow
- Suppliercheck applicabilitySuppliers running tenant electricity or district models check whether the customer installations they use count as grids from 2029.Typically affected: Regulatory management, controlling, Market communication gateway (EDIFACT, AS4, API)
- Plant operator (generation)check applicabilityPlant operators with direct lines or site supply check how their installation is classified.Typically affected: Plant master data and MaStR, Regulatory management, controlling
- Company-wide, several rolescheck applicabilityCompanies with contracting or site grid business assess restructuring, handover or regulation of existing customer installations.Typically affected: Regulatory management, controlling
Source ↗ Grid & low voltage Information as of: 11 October 2026 Discuss the implementation →
Q3 2029
1 deadlineDue by4 August 2029Electricity storage: commissioning deadline for the grid fee exemption under Section 118(6) EnWG
Electricity storage commissioned within 18 years from 4 August 2011 is exempt for 20 years from grid fees on electricity drawn for storage. The exemption only applies to the extent the stored electricity is fed back into the same grid with a time delay.
Law · adopted
If the deadline is missed: Exclusion or loss of role Storage commissioned after the deadline is not exempt from grid fees under Section 118(6) sentence 1 EnWG; commissioning means the first draw of electricity for trial operation (sentence 6). Under the AgNes draft (operative point 17.5) the exemption is also to require an investment decision before the ruling is notified, to be proven by 31 March 2027. Legal basis ↗
Applicability: Electricity storage built after 31 December 2008 drawing from the grid and commissioned by the deadline.
- Electricity grid operatoraffectedElectricity DSOs check the exemption conditions and bill storage withdrawal accordingly.Typically affected: Grid usage and customer billing, EDM / MDM
- Transmission system operatoraffectedTransmission system operators reimburse downstream DSOs for lost revenue.Typically affected: Grid usage and customer billing, Regulatory management, controlling
- Storage operatoraffectedStorage operators factor the commissioning date into project planning and business cases.Typically affected: Plant master data and MaStR, Regulatory management, controlling
Explained in the handbook: chapter 6 → Source ↗ Flexibility, storage & grid charges Information as of: 28 September 2026 Discuss the implementation →
Q4 2029
1 deadlineApplies from1 October 2029MaBiS hub: go-live (BDEW scenario)
Under the BDEW introduction scenario, parallel operation ends on 1 October 2029 and only the new process landscape with the MaBiS hub applies from then on. Block 1 of the ruling (BK6-24-210-1) was open for comment until 17 November 2025; block 2 on balance group settlement follows.
If the deadline is missed: No direct legal consequence The go-live date so far only appears in the industry's introduction scenario; there is no decision yet in proceeding BK6-24-210. Only a ruling would make the date binding and enforceable under Section 65 EnWG. Legal basis ↗
Applicability: The date is a BDEW proposal that the Federal Network Agency has put out for consultation in procedure BK6-24-210-1 but not adopted. Notice no. 58 of 1 October 2026 lists the MaBiS hub ruling as pending.
- Electricity grid operatoraffectedWorks with central balancing settlement in the MaBiS hub from go-live.Typically affected: EDM / MDM, Market communication gateway (EDIFACT, AS4, API)
- SupplieraffectedReceives balancing settlement and data reconciliation from the MaBiS hub from go-live.Typically affected: EDM / MDM
Linked to: MaBiS hub: test systems of all market partners ready (BDEW scenario)
Read the article → Explained in the handbook: chapter 7 → Source ↗ Market communication & market processes Information as of: 14 October 2026 Discuss the implementation →
Q4 2030
1 deadlineDue by31 December 2030Smart meter rollout: 90 percent of the 2029 to 2030 installation cases
Third period quota of the statutory rollout: at least 90 percent of the metering points that fall due in 2029 and 2030. The target year for the full stock is 2032.
Law · adopted
If the deadline is missed: Regulator can enforce If the default metering point operator misses the quota, the Federal Network Agency can order measures under Sections 45(2) and 76 MsbG and enforce them with coercive fines of EUR 1,000 to EUR 10 million (Section 76(4) MsbG, Section 94 EnWG). If the rollout of control units falls short by at least 25 percent and this contributes significantly to a possible threat to system security, it can withdraw the default responsibility under Section 12(2g) EnWG. Legal basis ↗
- Default metering point operatorrole obligationFits at least 90 percent of metering points due in 2029 and 2030 with smart metering systems.Typically affected: Gateway administration and CLS management, Field service and work orders
Linked to: Smart meter rollout: 90 percent of the 2027 to 2028 installation cases
Read the article → Source ↗ Smart metering, SMGW & §14a Information as of: 14 October 2026 Discuss the implementation →
Q4 2032
1 deadlineDue by31 December 2032Smart meter rollout: 90 percent of all mandatory cases
Final mark of the statutory rollout: by the end of 2032, 90 percent of all metering points to be equipped need an intelligent metering system. Optional installation cases count towards the quota since the EnWRÄndG of 18 December 2025.
Law · adopted
If the deadline is missed: Regulator can enforce If the default metering point operator misses the quota, the Federal Network Agency can order measures under Sections 45(2) and 76 MsbG and enforce them with coercive fines of EUR 1,000 to EUR 10 million (Section 76(4) MsbG, Section 94 EnWG). If the rollout of control units falls short by at least 25 percent and this contributes significantly to a possible threat to system security, it can withdraw the default responsibility under Section 12(2g) EnWG. Legal basis ↗
- Default metering point operatorrole obligationHas fitted at least 90 percent of all metering points due with smart metering systems by the end of 2032.Typically affected: Gateway administration and CLS management, Field service and work orders
Linked to: Smart meter rollout: 90 percent of the 2029 to 2030 installation cases
Read the article → Source ↗ Smart metering, SMGW & §14a Information as of: 11 October 2026 Discuss the implementation →
Where it gets tight
Three bundles where several deadlines need the same system and the same team. Each dot is one deadline.
October 2026 to October 2027
Market communication and EDM wave
- 1 October 20263 deadlines, passed
- 1 April 20272 deadlines
- 2027, date open1 deadline
- End of September 20271 deadline
The deadlines and why it gets tight
- 1 October 2026 MaKo format release, notice no. 56
- 1 October 2026 MiSpeL: ruling on market integration of storage and charging points
- 1 October 2026 WiM Gas 2.0 applies
- 1 April 2027 MaKo format release, notice no. 58
- 1 April 2027 Schedule nomination process description v4.7 becomes binding
- 2027, date open Energy sharing: practical start with the BNetzA platform
- End of September 2027 MiSpeL: end of the transition period
Mitteilung 56, WiM Gas 2.0 and the MiSpeL ruling all landed on 1 October 2026. Mitteilung 58 brings the new redispatch format and transport rules 1.11 on 1 April 2027, and the MiSpeL transition ends at the end of September 2027. Going live on one version and starting the project for the next fall into the same weeks.
December 2026 to January 2027
Metering at year end
- 31 December 20263 deadlines
- 1 January 20273 deadlines
The deadlines and why it gets tight
- 31 December 2026 Heating costs ordinance: retrofit remote reading
- 31 December 2026 Smart meter rollout: 90 percent of the installation cases since February 2025
- 31 December 2026 Smart meter rollout: 90 percent of new generation capacity up to 100 kilowatts
- 1 January 2027 BSI TR-03109-6 v2.0 for gateway administrators
- 1 January 2027 BSI TR-03109-1 v2.0: gateway certificates only with MUSS+
- 1 January 2027 Fallback metering operator: publication for 2027
Both 90 percent rollout quotas and remote reading of heat meters fall due at year end. In January, TR-03109-6 version 2.0 follows with the next recertification of the gateway administration system, along with the MUSS+ requirements for new gateway certificates. Every one of them pulls on the same installers, the same gateway administration system and the same deliveries of gateways and control boxes.
October 2026 to January 2027
Grid regulation and planning
- 14 October 20261 deadline, passed
- 15 October 20261 deadline, passed
- 26 October 20261 deadline
- 31 October 20261 deadline
- 31 December 20261 deadline
- End of 20262 deadlines
- 1 January 20271 deadline
The deadlines and why it gets tight
- 14 October 2026 Renewables grid cost pass-through: binding notification to the TSO
- 15 October 2026 2027 network charges: publication by 15 October
- 26 October 2026 Electricity efficiency benchmarking: data collection consultation closes
- 31 October 2026 Grid expansion plan under section 14d EnWG: first filing
- 31 December 2026 Regulatory account: application for 2025
- End of 2026 AgNes: framework ruling on electricity grid charges
- End of 2026 Gas WACC: the rate of return decision is issued
- 1 January 2027 Grid package: system-serving connection capacity instead of maximum output
Grid charges on 15 October, the §14d grid expansion plan on 31 October, the AgNes framework and gas WACC at year end, the grid package from January 2027. The same revenue cap model, the same GIS and usually the same few people in regulation and grid planning.
Already in force (14)
Past dates (8)
Passed due dates, closed consultations and decisions taken. Whatever continues as an obligation is listed under "Already in force" or as a deadline of its own.
Let's collaborate
Which of these deadlines hits your programme?
Thirty minutes on your market role and your next deadline: which processes, systems and data hang off it, and in what order it can be solved. If you want, a one-page implementation map afterwards. Whether an obligation applies to your company is for your legal counsel to settle, not this call.
Energy and measurement technology since 2010 · innobu GmbH since 2014 · Based in Schleswig-Holstein, Germany
Whoever pitches also delivers: whoever leads the first call stays your contact right through to the steering committee, with established partners in the project. Direct: info@innobu.com