ENERGY & SUSTAINABILITY
Metering technician with a tablet at an open electricity meter cabinet explaining the metering service to a resident

Standardised metering contracts from 2026: what BK6-24-125 means for the basic metering operator

With BK6-24-125 the BNetzA sets three standard contracts in electricity metering, binding from 1 July 2026. Basic metering point operators must convert their entire contract portfolio by that date. What was once a set of voluntary association templates becomes mandatory law of the market.

The ruling turns the central contracts of electricity metering into fixed standard documents: the framework contract between network operator and metering point operator, plus two new contracts with connected users and with suppliers. This is a different matter from the standard balancing group contract, which is its own contract on the balancing group side, and it is not the same as the technical gateway administrator switch, which is about handing over devices rather than standardising contracts. This piece is about the contract standardisation itself: which contracts are set, who is bound, the new penalty and the changeover by 1 July 2026. Note: gMSB is the basic metering point operator, wMSB is the competitive metering point operator and MSB is the metering point operator.

Summary

With the ruling BK6-24-125, decided on 20 November 2025 and effective from 1 July 2026, the BNetzA sets three standard contracts in electricity metering: the revised framework contract MSB-RV between network operator and metering point operator (MSB), the new metering contract with connected users MSV-AN and the new metering contract with suppliers MSV-LF, plus a form under Section 54 MsbG for the data communication. The scope is electricity only, gas continues to run through the cooperation agreement. Network operators and basic metering point operators (gMSB) are bound. Every MSB must conclude the framework contract with the network operator, but the metering contracts MSV-AN and MSV-LF are mandatory only for the gMSB, while a competitive metering point operator (wMSB) may use the templates voluntarily. New is a symmetric contractual penalty of 10 cents gross per day and metering point for a culpable breach of material process or data obligations, owed by both the network operator and the MSB, only for material breaches and after a chance to remedy. New too is an automatic amendment regime: ruling-driven changes become part of the contract without a fresh explicit amendment, after information at least two months in advance and online publication, and for the first time a metering-point-specific termination of single metering points is possible. The legal basis is Section 9, Section 34(1) and Section 54 MsbG, and only standard services are in scope. Importantly, non-discrimination stays statutory under Section 8(2) MsbG, an explicit contract clause was deliberately dropped, so it is not newly created by BK6-24-125. The ruling amends Annex 3 of the WiM ruling and refers dynamically to WiM and GPKE, while the MSB change still runs under WiM. Basic metering point operators must now convert their entire portfolio by 1 July 2026, choose the changeover variant, set up acceptance channels and harden their master-data and WiM and GPKE processes against the penalty.

What BK6-24-125 sets: three standard contracts

The BNetzA decision-making chamber 6 adopted the ruling BK6-24-125 on 20 November 2025, with the contracts becoming binding from 1 July 2026. What used to be a set of non-binding association templates becomes a fixed standard: for the first time the regulator sets how the central contracts in electricity metering have to look.

BK6-24-125
BNetzA ruling
decided 20 November 2025
1 July 2026
standard contracts binding
for gMSB and network operators
3 contracts
standard in electricity metering
MSB-RV, MSV-AN, MSV-LF
10 cents
contractual penalty
per day and metering point, symmetric
Section 9, 34, 54 MsbG
legal basis
standard services only
electricity only
scope
gas via the cooperation agreement

Three contract sets are set, all for electricity. The first is the revised framework contract, the MSB-RV, between the network operator and the metering point operator (MSB). The second is the new metering contract with connected users, the MSV-AN. The third is the new metering contract with suppliers, the MSV-LF. The two metering contracts are genuinely new, while the framework contract is a reworked version of the document the market already knew.

Alongside the three contracts the ruling adds a form under Section 54 MsbG, which governs the data communication that goes with the contracts. Taken together, these documents make the previously non-binding templates of the associations into mandatory standard contracts, so the parties no longer negotiate the core text but use a set framework.

The scope is deliberately limited. BK6-24-125 covers electricity only. For gas the corresponding ground is still held by the cooperation agreement, so the standardisation set out here does not reach into the gas sector. That keeps the change focused on the electricity metering market, where the rollout volume and the contract count are highest.

Who is bound: gMSB, network operators and wMSB

The obligation is graded. This is the point that is most often misread, because not every market participant is bound in the same way.

All MSB are bound to the framework contract, the metering contracts are mandatory only for the basic MSB.
All MSB are bound to the framework contract, the metering contracts are mandatory only for the basic MSB.

Network operators and basic metering point operators (gMSB) are fully bound. They have to use the standard contracts as set, which is where the weight of the changeover falls, since the basic operator carries the bulk of the installed base and of the end-customer relationships in its area.

The framework contract and the metering contracts do not bind the same circle. Every metering point operator (MSB) must conclude the framework contract MSB-RV with the network operator, whether it is a basic or a competitive operator, because that contract governs the relationship with the network. The metering contracts MSV-AN and MSV-LF, by contrast, are mandatory only for the gMSB.

A competitive metering point operator (wMSB) is therefore in a lighter position. It is bound to the framework contract like everyone else, but it is not obliged to use the standard metering contracts with connected users and suppliers. It may adopt the templates voluntarily, which can still be useful for a clean and recognisable contract base, but it is free to shape those relationships differently.

The new penalty and the amendment regime

Two changes alter contract practice the most: a flat contractual penalty and an automatic amendment regime that reaches into the running contract.

Close-up of a printed standard contract with a highlighted clause and a pen, black and white
New are a symmetric contractual penalty and an automatic amendment regime.

The new contractual penalty is a flat 10 cents gross per day and metering point. It applies for a culpable breach of material process or data obligations, and it is symmetric, so it is owed by both the network operator and the MSB. The penalty does not trigger on every slip: the claim arises only for material breaches, and only after the party at fault has been given a chance to remedy the problem first.

The second change is the amendment regime. Future ruling-driven changes become part of the contract automatically, without a fresh explicit amendment agreement between the parties. The safeguard is procedural rather than negotiated: the parties have to be informed at least two months in advance, and the changed contract is published online. This keeps the standard contracts current across the market without each pair of parties having to renegotiate every time the regulator moves.

Finally, the contracts introduce a metering-point-specific termination for the first time. Instead of having to terminate the whole contract, a party can now end the arrangement for single metering points. That gives both sides a much finer instrument and changes how disputes and migrations can be handled in practice.

The changeover by 1 July 2026

For basic metering point operators this is a mammoth task. With the end-customer contracts it can reach into potentially millions of contracts per operator, and the deadline is fixed.

Desk with a stack of printed contracts and envelopes ready to be sent
By 1 July 2026 the basic metering operators must convert their entire contract portfolio.

Existing contracts have to be converted by 1 July 2026 and the contracts have to be published online. For the gMSB this means moving the entire portfolio onto the new standard documents within a tight window, while keeping the contractual relationships intact throughout.

The form requirements are kept light to make the volume manageable. Conclusion in text form suffices, and acceptance can run by email, through a portal or via a QR code. An implied conclusion under Section 9(3) MsbG is also possible, with a confirmation in text form, so the operator does not depend on an active signature from every connected user to put the new contract in place.

  • Convert and publish by the deadline: move existing contracts onto the standard documents by 1 July 2026 and publish them online.
  • Text form is enough: conclusion in text form suffices, with acceptance by email, portal or QR code.
  • Implied conclusion is possible: an implied conclusion under Section 9(3) MsbG works, with a confirmation in text form.
  • Mind the termination variant: the amendment-and-termination route carries a risk of contract-less periods, so the deadlines have to be planned carefully.

The biggest operational risk is the changeover variant. If an operator chooses to terminate the old contract and conclude a new one, a gap can open between the two, a contract-less period that has to be avoided. Planning the deadlines so that the new contract is in force before the old one ends is therefore central to a clean changeover.

What companies should do now

Whoever sorts the contract portfolio early and hardens the processes avoids the penalty and contract-less periods. The deadline is tight, so the preparation should start with the inventory and the changeover decision.

  • Inventory the contract portfolio and choose the changeover variant. Take stock of the existing contracts and decide between a fresh conclusion and an amendment-and-termination route, so the path to the new standard documents is clear before the work starts.
  • Set up acceptance channels and prepare publication. Put the acceptance routes in place, by email, portal and QR code, and prepare the online publication of the contracts, because both are part of the conversion by 1 July 2026.
  • Harden master-data and WiM and GPKE processes against the penalty. Tighten the master-data quality and the WiM and GPKE process steps, since material process or data breaches are exactly what triggers the symmetric 10-cent penalty.
  • Prepare for the automatic amendment regime and metering-point-specific termination. Set up the internal handling so that ruling-driven changes flow into the contracts automatically and so that single metering points can be terminated cleanly when needed.

Further reading

Frequently asked questions

What does the BNetzA ruling BK6-24-125 set? +

With BK6-24-125, decided on 20 November 2025, the BNetzA sets three standard contracts in electricity metering and revises the framework contract between network operator and metering point operator. The contracts become binding from 1 July 2026. They replace the previously non-binding association templates and turn them into mandatory standard contracts for network operators and basic metering point operators.

Which contracts are standardised? +

Three contract sets for electricity are set: the revised framework contract MSB-RV between network operator and metering point operator, the new metering contract with connected users MSV-AN and the new metering contract with suppliers MSV-LF. A form under Section 54 MsbG for the data communication is added. The scope is electricity only, gas runs through the cooperation agreement.

Who is bound by the contracts? +

Network operators and basic metering point operators (gMSB) are fully bound. Every metering point operator must conclude the framework contract MSB-RV with the network operator. The metering contracts MSV-AN and MSV-LF are mandatory only for the basic metering point operator, while a competitive metering point operator (wMSB) may use the templates voluntarily.

What is the new 10-cent contractual penalty? +

The contracts introduce a flat contractual penalty of 10 cents gross per day and metering point for a culpable breach of material process or data obligations. It is symmetric, so it applies to both the network operator and the metering point operator. The claim arises only for material breaches and after a chance to remedy has been given.

By when must the contracts be converted? +

The standard contracts are binding from 1 July 2026. Basic metering point operators must convert their entire existing contract portfolio by that date and publish the contracts online. Conclusion in text form suffices, with acceptance by email, portal or QR code, and an implied conclusion under Section 9(3) MsbG is possible with confirmation in text form.