Two engineers walk along the gravel path through the switchyard next to a converter station hall in East Frisia

Procurement, trading & market designUpdated: 9 min read

2027 levies: figures since 26 October, open issues and fallback routes

Since 26 October the 2027 CHP levy and offshore grid levy have been fixed at 0.451 and 1.143 cents per kilowatt hour. Default suppliers have 25 days to announce new prices.

Germany's four transmission system operators published the 2027 levies under the Energy Financing Act (EnFG) on netztransparenz.de on 26 October 2026, one day after the statutory deadline, which fell on a Sunday, along with a provisional surcharge for special grid use. Suppliers need the figures for pricing and for their price change letters, distribution system operators for their 2027 price sheets. Meanwhile the subsidy towards transmission grid costs, on which the preliminary grid fees rest, still has not passed the Bundestag.

Summary

The EnFG levies are the CHP levy and the offshore grid levy; under Section 11 EnFG the transmission system operators publish them by 25 October for the following year, so by 25 October 2026 for 2027. For 2027 they are 0.451 and 1.143 cents per kilowatt hour, and with the surcharge for special grid use (2.027 cents up to 1 GWh) 3.621 cents in total, against 2.946 cents in 2026. Suppliers carry the new values into pricing and customer letters: default suppliers must publish price changes for 1 January 2027 by 20 November, and household customers on special contracts must be told at least one month ahead. Still open is the EUR 5.525 billion federal subsidy towards transmission grid costs. It does not touch the levies but it does touch grid fees: without legal certainty by 7 December 2026, the transmission system operators say their final fees will rise.

0.451 ct
per kWh is the 2027 CHP levy, barely above 2026
2026: 0.446 ct/kWh
1.143 ct
is what the TSOs charge as offshore grid levy in 2027, 21 percent more
2026: 0.941 ct/kWh
2.027 ct
comes on top in 2027 as surcharge for special grid use (up to 1 GWh), provisionally
2026: 1.559 ct/kWh
3.621 ct
is what non-privileged final customers pay for all three in 2027
2026: 2.946 ct/kWh
25 days
separate the publication on 26 October from the notice deadline in default supply
Section 5(2) StromGVV
EUR 5.525 bn
is what Berlin plans to put towards transmission grid costs in 2027, not towards the levies
Printed paper 21/8236

What was published on 26 October

The period in Section 11 EnFG ended on Sunday, 25 October 2026; the 2027 figures have been on netztransparenz.de since Monday, 26 October. The CHP levy barely moves, from 0.446 to 0.451 cents per kilowatt hour. The offshore grid levy rises 21 percent to 1.143 cents; the transmission system operators say it includes a catch-up amount from the 2025 annual settlement. The biggest jump is in the surcharge for special grid use: 2.027 cents up to 1 GWh after 1.559 cents, up 30 percent. Non-privileged final customers pay 3.621 cents per kilowatt hour for all three items in 2027, 0.675 cents more than in 2026.

Everything else that goes into the 2027 electricity price is already out. On 1 October 50Hertz, Amprion, TenneT and TransnetBW published their preliminary grid fees, on average 3.54 cents per kilowatt hour at extra-high and high voltage against 2.86 cents this year. Distribution system operators had to follow by 15 October; how that went and which items stayed open is covered in our piece on network charges 2027. With the levies out since 26 October, suppliers have every building block for their calculation, though grid fees and the surcharge remain provisional.

Which levies are due by 25 October

The EnFG knows two levies, the CHP levy (KWKG-Umlage) and the offshore grid levy. Section 10(2) has the transmission system operators calculate each one "transparently and separately" (our translation) from its funding requirement and the leviable grid withdrawal, in cents per kilowatt hour. Neither can turn negative, even if an account ran a surplus the year before.

Levies and surcharge for non-privileged final customers, in cents per kilowatt hour
ItemLegal basis202520262027
CHP levySections 10, 11 EnFG0.2770.4460.451
Offshore grid levySections 10, 11 EnFG0.8160.9411.143
Surcharge for special grid use (up to 1 GWh)Bundesnetzagentur determinations1.5581.5592.027 (provisional)

The 61 percent jump in the CHP levy for 2026 had two causes, according to an analysis by the law firm Stein from March 2026: subsidy payments for new and modernised CHP plants, and a catch-up because the previous year's figure had been set too low. The offshore grid levy rose 15 percent with the cost of connection lines and the compensation paid when a connection is disrupted or delayed. For 2027 the picture is reversed: the CHP levy stays almost flat while the offshore grid levy rises sharply.

The transmission system operators usually publish the surcharge for special grid use at the same time, though it has a different legal basis. Since 1 January 2025 it has contained the former Section 19 StromNEV levy plus a surcharge for special feed-in grid use, which spreads the extra cost of integrating renewables across the whole country. Grid operators reported the volumes for it in the pass-through procedure we describe in our article on renewables grid cost pass-through. What matters for pricing is that it comes in three customer groups: in 2026 that meant 1.559 cents up to 1 GWh, 0.050 cents for group B' and 0.025 cents for group C', and for 2027 it is 2.027, 0.050 and 0.025 cents. The transmission system operators published this surcharge on condition that the subsidy law passes; if there is no legal certainty by 7 December 2026, they say it will rise.

What depends on the subsidy and what does not

The subsidy lowers transmission grid fees and nothing else. On 2 September 2026 the federal cabinet adopted the draft that would add Section 24d to the Energy Industry Act (EnWG) with EUR 5.525 billion a year from the Climate and Transformation Fund for 2027 to 2029; it sits in the Bundestag as printed paper 21/8236 of 28 September. The EnFG levies do not appear in it.

For suppliers that means two uncertainties on two different dates. The levies have been fixed since 26 October and won't change, while grid fees remain provisional, and the Federal Network Agency decides on the use of the transmission system operators' congestion income only by 31 December. Without the subsidy, 2027 transmission grid fees would be 6.52 rather than 3.54 cents, and the transmission system operators have said their final fees will rise if there is no legal certainty by 7 December 2026. How much of that reaches distribution grid fees depends on how much upstream cost sits in each operator's calculation.

Subsidise grid fees or the levies?

The industry associations don't agree on where the money should go. VKU, the association of municipal utilities, and the Federation of German Consumer Organisations (vzbv) want part of the subsidy spent on the levies, because they are the same everywhere and so relieve every household equally; a subsidy for transmission grids alone works out differently from region to region. BDEW backs the government's approach, according to an overview by the trade paper ZfK on 13 August 2026. The government draft followed the second line. Whether the parliamentary process changes that is open, and any change would come too late for this autumn's pricing anyway.

From netztransparenz.de to the customer letter

A published levy has to land in three places: the distribution system operator's price sheet, the billing conditions and the supplier's calculation. Section 12(1) EnFG lets grid operators charge the levies "as a separate surcharge on grid withdrawal" (our translation), which is why they appear as their own lines next to the grid fee.

Timeline with five dates from the publication of the levies on 26 October to the new prices on 1 January 2027
Five dates between the publication of the levies and the new prices taking effect, with the role that acts at each step.

It gets tight on the supplier side, because default suppliers have to publish changed general prices at least six weeks before they take effect under Section 5(2) StromGVV (default supply price change), and send every customer a letter at the same time setting out the scope, reason and conditions of the change. For 1 January 2027 that deadline is 20 November. For household customers on special contracts, Section 41(5) EnWG requires notice at least one month ahead; for all other final customers, two weeks.

Two people from a municipal utility's pricing team go through a printed price sheet at a desk
Between the levy figure and the customer letter sit the calculation, the sign-off and the update in the billing system.

One detail helps. If a levy falls, Section 41(6) EnWG lets the supplier pass on the reduction unchanged without prior notice. If it rises, the full notice period applies, and a supplier that shows the levies as separate price components can't simply pass higher figures through the moment they appear: the notice, including the reference to the customer's right to terminate, has to reach the customer in time.

Four open issues

None of these is new, but in 2026 they all land in the same four weeks.

Where dates and responsibilities collide in 2026

1

Values at the weekend

The figures were only on netztransparenz.de on Monday, 26 October, one day after the deadline. Data entry and sign-off therefore start that day at the earliest, leaving 25 days until 20 November.

2

Grid fees still provisional

Prices announced by 20 November rest on preliminary grid fees. If the subsidy law turns out differently after 7 December, the calculation is out of date.

3

Capped consumption points

For consumption points capped under Sections 30 to 36 EnFG, or with an application filed for 2027, only the transmission system operators collect the levies (Section 12(2)). They must not show up a second time on the distribution operator's price sheet.

4

Surcharge groups

The surcharge for special grid use distinguishes between consumption above and below 1 GWh. The assignment has to be in the system before the first 2027 instalment invoice.

Fallback routes if values come late or differ

Section 11 EnFG has no fallback like Section 20(1) sentence 2 EnWG, which allows expected values for grid fees. The transmission system operators publish the final figure, and it applies for the whole year. For suppliers, the fallback therefore moves into their own planning: anyone who only starts calculating when the figures appear on 26 October has nothing to fall back on if sign-off or printing slips.

We recommend preparing the calculation in variants, say with the 2026 values and a range above them, so that on publication day only the figures need entering. The price change letters then sit ready in the approval workflow with placeholders. They go out once levies and grid fees fit together, because the letter has to state the reason for the change.

A clerk in a regional utility's mailroom lifts a tray of franked letters off the franking machine
Letters to default supply customers have to go out together with the public notice, for 1 January no later than 20 November.

The second case is harder: grid fees rise after 7 December because the subsidy does not arrive in time. A second price change for 1 January would no longer be possible for default supply customers, since the six-week period has run out. Suppliers would then have to decide whether to absorb the extra cost until a later date or adjust on 1 February or 1 March. That decision belongs with management now, not in December.

What the law provides if the deadline is missed

The duty under Section 11 EnFG lies with the transmission system operators, and the Bundesnetzagentur monitors under Section 62(1) no. 1(a) EnFG that they calculate and publish the levies properly; it can order publication using its EnWG powers. Breaching an enforceable order is an administrative offence under Section 63(1) no. 2 EnFG, with fines of up to EUR 200,000. Suppliers are bound by the deadlines in Section 41 EnWG and the StromGVV. This describes the legal framework, not an assessment of any individual case. We track the date and roles in our energy transition deadline calendar.

What suppliers and grid operators should settle this week

The levies have been fixed since 26 October. What decides the 20 November notice deadline now is the sign-off process, not waiting for figures.

Five steps before the end of October

  1. Carry the 2027 figures into pricing and billing

    CHP levy 0.451 cents, offshore grid levy 1.143 cents and the surcharge of 2.027, 0.050 and 0.025 cents for groups A', B' and C' go to both teams on Monday, 26 October.

  2. Finish the calculation with the 2027 figures

    Add a second line for grid fees and surcharge without the subsidy, so management knows the order of magnitude if the law fails.

  3. Check price sheet against billing system

    At the distribution operator: CHP levy, offshore grid levy and surcharge as separate items, groups A', B' and C' assigned correctly, capped consumption points excluded. At the supplier: the same values in the billing conditions.

  4. Put the letters with placeholders into sign-off

    Still in October, so that printing and dispatch for default supply are done by 20 November.

  5. Decide the December question now

    What does the company do if grid fees rise after 7 December and the deadline for 1 January has passed: carry the extra cost until the next date, or adjust during the year? A decision in October saves a crisis meeting in December.

How dates like these from regulation and law turn into a working plan at a utility is described on our page on regulatory implementation for grid operators. More articles are collected in the topic field procurement, trading and market design.

Deadline, market roles, systems

25 October 20262027 levies: publication by the transmission system operatorsLaw · date passed

Applicability: Transmission system operators; indirectly all electricity suppliers and electricity DSOs.

If the deadline is missed: Regulator can enforce The Federal Network Agency monitors publication under Section 62(1) no. 1(a) EnFG and can order it using its EnWG powers. Breaching an enforceable order is an administrative offence under Section 63(1) no. 2 EnFG, with fines of up to EUR 200,000. Legal basis ↗

  • Electricity grid operatoraffectedElectricity DSOs apply the levies as a surcharge on grid withdrawal in their 2027 price sheets.Typically affected: Grid usage and customer billing, Regulatory management, controlling
  • Transmission system operatorrole obligationTransmission system operators publish the 2027 levies on time on their joint website.Typically affected: Regulatory management, controlling, Customer and grid connection portal
  • SupplieraffectedSuppliers carry the levies into 2027 pricing and price change letters.Typically affected: Grid usage and customer billing, SAP IS-U / S/4HANA Utilities

A classification for typical market roles, not a review of your individual case and not legal advice. Whether an obligation applies to your company (thresholds, exemptions) is for your legal department or counsel to confirm. The calendar doesn't replace your own deadline review. Information as of: 1 November 2026.

Discuss the implementation →In the deadline calendar →

Further reading

Frequently asked questions

Under Section 11 EnFG the transmission system operators had to publish the 2027 levies by Sunday, 25 October 2026, on their joint website, netztransparenz.de. They published the figures on Monday, 26 October 2026: 0.451 cents per kilowatt hour for the CHP levy and 1.143 cents for the offshore grid levy.

The CHP levy and the offshore grid levy. Each is calculated separately from its funding requirement and the leviable grid withdrawal, in cents per kilowatt hour, and under Section 10 EnFG neither can be negative. The surcharge for special grid use does not rest on the EnFG.

The CHP levy was 0.446 cents per kilowatt hour in 2026, the offshore grid levy 0.941 cents and the surcharge for special grid use 1.559 cents for final customers up to 1 GWh. Together that is 2.946 cents, up from 2.651 cents in 2025.

No. The draft law (Bundestag printed paper 21/8236 of 28 September 2026) provides EUR 5.525 billion a year towards transmission grid costs for 2027 to 2029. The EnFG levies are not covered. The draft has not been passed yet.

Default suppliers publish changed general prices at least six weeks in advance (Section 5(2) StromGVV), so by 20 November 2026 for 1 January 2027. Household customers on special contracts must be notified at least one month in advance under Section 41(5) EnWG, other final customers at least two weeks in advance.

The Bundesnetzagentur monitors publication under Section 62(1) no. 1(a) EnFG and can order it using its EnWG powers. Breaching an enforceable order is an administrative offence under Section 63(1) no. 2 EnFG, with fines of up to EUR 200,000.

Let's collaborate

One contact, a team behind it

Thirty minutes on what you're working on, whether grid, metering, market processes, IT architecture or AI. Afterwards you'll know how we'd approach it and who would sit at the table.

Energy and measurement technology since 2010 · innobu GmbH since 2014 · Based in Schleswig-Holstein, Germany

Whoever pitches also delivers: whoever leads the first call stays your contact right through to the steering committee, with established partners in the project. Direct: info@innobu.com