Accountant at a municipal utility signs a letter shortly before Christmas, a window envelope ready beside it

Procurement, trading & market designUpdated: 10 min read

Electricity and energy tax in Germany: filing choice by 31 December, estimate by 15 January, annual return by 31 May

Since January 2026, the main customs office expects suppliers that file annually to send their own estimate of the year's tax, and a supplier that fails to report it or gets it wrong risks a fine.

For electricity tax, the declaration on the filing method for 2027 has to reach the main customs office (Hauptzollamt) by Thursday, 31 December 2026. A little over two weeks later, on Friday, 15 January 2027, the estimate of the 2027 annual tax is due, and the 2026 annual return by Monday, 31 May 2027. Electricity and natural gas follow two laws that start from opposite default rules on the filing choice.

Summary

The tax return under Section 8 StromStG and Section 39 EnergieStG is the declaration in which German electricity suppliers and natural gas suppliers calculate electricity tax or energy tax themselves and file it with the main customs office, either monthly or annually. Three deadlines apply until mid-2027: for electricity tax, the choice between monthly and annual filing has to reach the main customs office by 31 December 2026, otherwise annual filing applies; for natural gas, monthly filing is the rule, and annual filing needs a written declaration before the year begins, which then stands until revoked. Suppliers filing annually send the main customs office a traceable estimate of the 2027 annual tax by 15 January 2027 (below EUR 2,400 only on request), estimate again as of 30 June and report by 15 August if the estimate exceeds EUR 100,000 and is also more than 20 percent above the annual tax on which the main customs office based the advance payments; these duties have applied since 1 January 2026, and a notification that is intentionally or recklessly missing, wrong or late can be fined up to EUR 5,000. The 2026 annual return is due by 31 May 2027 and the balance after advance payments by 25 June 2027; the German Fiscal Code provides late filing and late payment surcharges.

31 Dec 2026
is when the 2027 filing declaration must reach the main customs office
Section 8(2) StromStG, a Thursday
15 Jan 2027
is when the estimate of the 2027 annual tax is due
Section 8(6) StromStG, Section 39(5) EnergieStG, a Friday
31 May 2027
closes the window for the 2026 annual return; payment follows by 25 June
Section 8(4) StromStG, Section 39(3) EnergieStG, a Monday
€20.50
of electricity tax applies per megawatt hour; natural gas for heating carries €5.50
Section 3 StromStG, Section 2(3) sentence 1 no. 4 EnergieStG
€2,400
of annual tax: below that, nobody sends the January estimate unprompted
Section 8(6) sentence 5 StromStG
€5,000
is the maximum fine if an estimate is missing, wrong or late
intent or recklessness, Section 14 StromStG, Section 381(2) AO

Who owes electricity tax and energy tax

Electricity tax is owed by the supplier, meaning whoever delivers electricity to final consumers: the tax arises when the customer draws the electricity from the grid (Section 5(1) and (2) StromStG), and the supplier needs a licence from the main customs office to do so (Section 4(1)). For natural gas, the supplier established in Germany owes the energy tax (Section 38(2) no. 1 EnergieStG) and registers with the main customs office before it starts supplying (Section 38(3)). At a municipal utility that is the sales company, even though the return is prepared in tax or accounting and the volumes come out of billing.

Rates have not moved in years: EUR 20.50 per megawatt hour of electricity (Section 3 StromStG) and EUR 5.50 per megawatt hour of natural gas used for heating (Section 2(3) sentence 1 no. 4 EnergieStG). What is new is the procedure around advance payments. The Third Act amending the Energy Tax Act and the Electricity Tax Act of 22 December 2025 (Federal Law Gazette 2025 I No. 340) rewrote Section 8(6) StromStG and Section 39(5) EnergieStG and attached a fine to both notifications, in force since 1 January 2026. The first January estimate was due on 15 January 2026 and the first mid-year estimate as of 30 June 2026; the estimate for 2027 follows on 15 January 2027.

Tax return (Steueranmeldung) is the declaration in which the taxpayer calculates the tax itself (Section 8(1) StromStG, Section 39(1) EnergieStG). It has the effect of a tax assessment subject to review (Section 168 AO); the main customs office issues its own assessment only if it arrives at a different amount or the return is missing (Section 167(1) AO).

None of this concerns the relief customers claim. Electricity tax relief for manufacturing companies under Section 9b StromStG is claimed by the company that drew the electricity (Section 9b(3)); the supplier files those volumes at the standard rate of Section 3. How that relief fits with other instruments is covered in our article on the industrial electricity price 2026 to 2028.

The deadlines at a glance

Three deadlines from the deadline calendar fall on suppliers over the next six months, each tied to a different part of Section 8 StromStG and Section 39 EnergieStG. For each one, the table lists who has to meet it, what is required and what the law provides if it is missed.

Electricity and energy tax deadlines for suppliers, tax years 2026 and 2027
DateWhoWhatPrimary sourceIf the date is missed
Thu, 31 Dec 2026Electricity suppliers; natural gas suppliers that want to depart from monthly filingDeclare the filing method for 2027: monthly or annualSection 8(2) StromStG; Section 39(2) EnergieStGElectricity: annual filing. Natural gas: monthly filing, or the existing annual choice stays in force
Fri, 15 Jan 2027Taxpayers filing annually with advance payments, from EUR 2,400 of annual taxReport the estimate of the 2027 annual tax; estimate again as of 30 Jun 2027 and report by 15 Aug 2027 if above EUR 100,000 and more than 20 percent above the assessmentSection 8(6) StromStG; Section 39(5) EnergieStG; Section 6(1) StromStVAdministrative offence, fine up to EUR 5,000 (Section 14 StromStG; Section 64 no. 5 EnergieStG with Section 381 AO)
Mon, 31 May 2027Taxpayers filing annually for 2026File the 2026 annual return; pay the balance after advance payments by or on Fri, 25 Jun 2027Section 8(4) StromStG; Section 39(3) EnergieStGLate filing surcharge possible (Section 152 AO); late payment surcharge of 1 percent per started month (Section 240 AO)
Timeline: filing choice by 31 Dec 2026, estimate by 15 Jan 2027, advance payments, annual returns by 31 May 2027 and 2028
A supplier filing annually works on two tax years at once in 2027: it estimates 2027 and files 2026.

Monthly filers run on a different beat: return by the 15th of the following month, payment by the 25th (Section 8(3) StromStG; for natural gas due on the 25th, Section 39(1) EnergieStG). On 15 January 2027 these suppliers file for December 2026 while annual filers send their estimate, so both groups have a deadline that Friday.

31 December 2026: monthly or annual filing

For electricity tax, the choice only ever covers one calendar year, and the declaration must have "reached the main customs office by 31 December of the previous year at the latest" (Section 8(2) StromStG, our translation). What counts is receipt, not the date it was sent. A supplier that declares nothing files annually in 2027 and pays monthly advance payments.

Natural gas works the other way round. Monthly filing is the rule (Section 39(1) EnergieStG), and a supplier that wants to file annually submits a written declaration that has to be with the main customs office before the calendar year begins. That choice applies to full calendar years and stands until the supplier revokes it in writing before the start of a year (Section 39(2) EnergieStG). A supplier whose gas tax first arises during a year has until the end of the second month after the month in which it first arose.

Filing choice for electricity tax and energy tax on natural gas
RuleElectricity tax (Section 8 StromStG)Energy tax on natural gas (Section 39 EnergieStG)
No declarationannual filingmonthly filing
Validity of the choiceone calendar year, chosen again each yearfull calendar years until revoked in writing
Deadlinereceived by the main customs office by 31 Dec of the previous yearwritten declaration on file before the calendar year begins
Monthly cyclereturn by the 15th, payment by the 25th of the following monthreturn by the 15th, due on the 25th of the following month

Either way, money goes out on the 25th of the following month. Monthly filers pay the tax they filed; annual filers pay an advance of one twelfth of the expected annual tax, set by the main customs office (Section 8(6) and (7) StromStG, Section 39(5) EnergieStG). If that comes to no more than EUR 200 a month, the main customs office waives electricity tax advance payments, provided tax interests are not affected (Section 6(3) StromStV). Since 2026 the real difference is the workload: twelve returns with monthly volumes on one side, one annual return plus two estimate dates on the other.

We advise suppliers that sell both electricity and gas to make the choice for both taxes explicitly every year and record it internally, even when nothing changes. Why: without a declaration electricity tax ends up annual and gas tax monthly, and a switch for gas only takes effect at the start of the next year.

15 January 2027: estimate of the annual tax

Anyone filing annually and making advance payments sends the main customs office, by 15 January of the assessment year (the tax year in question), "an appropriate estimate of the expected annual tax liability that a third party can follow" (Section 8(6) sentence 4 StromStG; Section 39(5) EnergieStG has the same wording; our translation). If the supplier's own estimate is below EUR 2,400, it is sent only on request. It goes to the main customs office in writing on the official form (Section 6(1) StromStV), and the office sets the advance payments by notice.

Until the end of 2025, the main customs office based advance payments on the tax due for the year before last; for 2025, that meant the tax for 2023. The federal government justified the change with practice: many main customs offices had already been asking suppliers for current data at the turn of the year, and the yardstick is now the expected annual tax for the year concerned (Bundestag printed paper 21/1866 of 29 September 2025, p. 76).

The second estimate as of 30 June

As of 30 June, the taxpayer estimates the annual tax again and reports it on request. It has to report it unprompted by 15 August if two conditions are met at once: the estimate exceeds EUR 100,000, and it exceeds the annual tax on which the main customs office based the advance payments by more than 20 percent. In that case the office resets the advance payments. According to the explanatory memorandum, the figure is taken before any tax relief, and the rule follows suggestions from the Federal Court of Audit to reduce the risk of tax shortfalls (Bundestag printed paper 21/1866, p. 76).

Upward only

The 15 August duty only applies when the estimate is higher. If the annual tax falls sharply, for instance because customers have switched supplier, the taxpayer can apply for the advance payments to be set differently (Section 8(6) sentence 3 StromStG); there is no reporting duty for that case.

In our view, 30 June is the date suppliers are most likely to underestimate. It appears in no notice, it calls for a projection in the middle of the year, and this is the notification that carries a fine. A sales team that wins large business customers in spring, or takes over a default-supply customer base, can reach the 20 percent faster than the tax department hears about it. So the estimate needs the same figures as sales planning, split by tax rate and exemption, and a calculation a customs auditor can follow.

31 May 2027: 2026 annual return, payment by 25 June

With annual filing, the tax for 2026 has to be filed by Monday, 31 May 2027, and paid to the main customs office, after credit for advance payments, by Friday, 25 June 2027 (Section 8(4) StromStG). For natural gas, Section 39(3) EnergieStG says the tax is "due on 25 June" of that year. On the same 31 May, electricity suppliers report the previous year's tax-exempt volumes under Section 4(6) StromStV, to the extent they were generated in stationary installations.

The volumes come from billing, which rarely bills by calendar year. Where billing follows reading periods that span the turn of the year, as with the rolling annual bills for household customers, the law allows an appropriate, traceable estimate to split the volume between tax years. If the reading period ends later, the filed volume is corrected in the year in which it ends (Section 8(4a) StromStG, Section 39(6) EnergieStG).

Meter reader from a municipal utility holds a handheld device up to a grey diaphragm gas meter in a terraced house basement
If a reading period ends in the following year, the estimated volume is corrected in that year's return.

Since 2026 there has been a simplification: if the billed volume rests on an estimate or later turns out to be wrong, and the bill is changed as a result, the reading period also counts as ending later (Section 8(4b) StromStG, Section 39(6a) EnergieStG). Transactions that no longer make it into the annual financial statements for the tax year count as spanning several years as well (Section 8(4c), Section 39(6b)). According to the federal government, such cases had previously led to very frequent corrections of returns already filed (Bundestag printed paper 21/1866, p. 76). The correction now goes into the next return, and the financial statements and the return diverge less often.

Bookkeeping is set out in the ordinance. Suppliers keep records on the official form, separated by tax rate, exemption and final consumer; if the main customs office allows business records instead, the supplier needs one or more electricity tax accounts in the general ledger from which every transaction can be traced (Section 4(2) and (3) StromStV). Section 79 EnergieStV does the same for natural gas with energy tax accounts. If you are moving billing to SAP S/4HANA Utilities, add the tax accounts and the allocation across reading periods to the test cases; problems there tend to surface only at the first annual return.

What applies if a deadline is missed

Each of the three deadlines has a different legal consequence, and only one of them is a fine. We describe what the law provides; whether and how a main customs office acts in a given case depends on circumstances we do not assess here.

  • Filing choice: if the electricity tax declaration is late, the tax is filed and paid annually (Section 8(2) sentence 4 StromStG). For natural gas, monthly filing or the existing annual choice continues (Section 39(1) and (2) EnergieStG).
  • Estimate: anyone who intentionally or recklessly fails to make a notification under Section 8(6) sentences 4 to 7 StromStG, or makes it incorrectly or late, commits an administrative offence; the fine is up to EUR 5,000 and the main customs office is the competent authority (Section 14 StromStG). For natural gas, Section 64 no. 5 EnergieStG refers to Section 381 AO, which also provides for up to EUR 5,000.
  • Annual return: a late filing surcharge can be imposed (Section 152(1) AO). For returns covering a calendar year it is 0.25 percent per started month of the tax less advance payments, at least EUR 25 and at most EUR 25,000 (Section 152(5) and (10) AO). If no return is filed at all, the main customs office assesses the tax itself (Section 167(1) AO).
  • Payment: if the tax is not paid by the due date, a late payment surcharge of 1 percent of the arrears, rounded down to the nearest EUR 50, accrues per started month; delays of up to three days carry no surcharge (Section 240(1) and (3) AO).

The fine for the estimate came with the act of 22 December 2025, which rewrote Section 14(1) StromStG and added no. 5 to Section 64 EnergieStG (Federal Law Gazette 2025 I No. 340, Article 1 no. 12 and Article 2 no. 24). Surcharges under the Fiscal Code applied before.

Associations and legislator on the estimate

The in-year estimate already featured in the 2024 draft of an act to modernise and cut red tape in electricity and energy tax law, which at the time provided for a check after every quarter. In its comments on the ministerial draft on 26 April 2024, the energy industry association BDEW wrote that repeated in-year calculation of the tax liability "contradicts the nature of an annual liability with credit for advance payments made". On the sanction: "Treating breaches of duty by the taxpayer separately as an administrative offence is not acceptable." The association pointed out that differences are settled fairly promptly anyway through the return on 31 May and the payment on 25 June (quotes translated by us).

VIK, which represents industrial energy users, wanted the duty limited in its statement of 8 October 2024 to companies "whose economic focus lies in section E of WZ2003 (energy supply)", in other words to suppliers. In its draft of 29 September 2025, the federal government kept the estimate and justified the mid-year check with the risk of tax shortfalls flagged by the Federal Court of Audit; the change as a whole, it said, follows the practice many main customs offices already had (Bundestag printed paper 21/1866, p. 76).

The act of 22 December 2025 sits between the two positions: one mid-year check instead of four quarterly ones, a reporting duty only above EUR 100,000 and 20 percent, but with a fine. VIK's limit to suppliers did not make it into the act; an industrial company that generates electricity for its own use and owes electricity tax on it as a self-generator and files annually also estimates by 15 January once its annual tax reaches EUR 2,400.

What suppliers should do before January

Five steps to the 2026 annual return

  1. Decide the 2027 filing method for each tax

    In November, record whether electricity tax and energy tax will be filed monthly or annually in 2027, and check which gas declaration from earlier years is still in force.

  2. Send the declaration so that it arrives before 31 December

    For electricity tax, receipt by the main customs office is what counts; for gas, the written declaration has to be on file before the year begins. 31 December is a Thursday between the holidays, so plan the dispatch to have proof of receipt beforehand.

  3. Derive the 2027 estimate from sales planning

    Take volumes per tax rate and exemption from sales planning, multiply by the rate, document the calculation and report it on the official form by Friday, 15 January 2027.

  4. Treat 30 June as a deadline in its own right

    Re-project with actual volumes to the end of May and check whether the estimate exceeds EUR 100,000 and is more than 20 percent above the assessed annual tax. If so, report by 15 August; if it is well below, consider applying for a different assessment.

  5. Prepare the 2026 annual return from January

    Pull the allocation of the 2025/26 and 2026/27 reading periods from billing, reconcile it with the electricity tax and energy tax accounts in the general ledger and file by 31 May; the payment run for 25 June belongs in the same plan.

Other dates that hit suppliers in the same weeks, such as the publication of levies, are covered in our article on the 2027 levies and in the energy transition deadline calendar.

Deadline, market roles, systems

31 December 2026Electricity and energy tax: choose monthly or annual filing for 2027Law · adopted

If the deadline is missed: No direct legal consequence Without a timely declaration the default applies: electricity tax is filed annually (Section 8(2) StromStG), energy tax on natural gas monthly (Section 39(1) EnergieStG). Legal basis ↗

  • Suppliercheck applicabilityDecides on monthly or annual tax filing for 2027 and submits the declaration to the main customs office by 31 December 2026.Typically affected: SAP IS-U / S/4HANA Utilities, Grid usage and customer billing

15 January 2027Electricity and energy tax: estimate of 2027 annual tax by 15 JanuaryLaw · adopted

If the deadline is missed: Fine possible Failing, intentionally or recklessly, to make a notice under Section 8(6) sentences 4 to 7 StromStG, or making it incorrectly or late, is an administrative offence with a fine of up to 5,000 euros (Section 14(1) no. 1 and (2) StromStG). The same applies to natural gas via Section 64 EnergieStG with Section 381 AO. Legal basis ↗

  • Supplierrole obligationEstimates 2027 electricity and gas tax from sales planning and reports it by 15 January 2027; checks the deviation as of 30 June.Typically affected: SAP IS-U / S/4HANA Utilities, Grid usage and customer billing

31 May 2027Electricity and energy tax 2026: annual return by 31 May, payment by 25 JuneLaw · adopted

If the deadline is missed: Money is lost Filing late risks a late filing surcharge (Section 152 AO); paying late incurs late payment surcharges (Section 240 AO). Legal basis ↗

  • Supplierrole obligationPrepares the 2026 annual tax return from billing and volume allocation, files it by 31 May 2027 and pays by 25 June 2027.Typically affected: SAP IS-U / S/4HANA Utilities, Grid usage and customer billing

A classification for typical market roles, not a review of your individual case and not legal advice. Whether an obligation applies to your company (thresholds, exemptions) is for your legal department or counsel to confirm. The calendar doesn't replace your own deadline review. Information as of: 27 October 2026.

Discuss the implementation →In the deadline calendar →

Further reading

Frequently asked questions

It is the declaration in which the taxpayer calculates the tax itself and files it with the main customs office (Hauptzollamt). For electricity tax that is the supplier that delivers electricity to final consumers (Sections 5 and 8 StromStG); for energy tax on natural gas it is the supplier established in Germany (Sections 38 and 39 EnergieStG). The return has the effect of a tax assessment subject to review (Section 168 AO).

For electricity tax, the declaration must reach the main customs office by Thursday, 31 December 2026 at the latest; without it, annual filing applies for 2027 (Section 8(2) StromStG). For energy tax on natural gas, monthly filing is the rule. A supplier that wants to file annually in 2027 needs a written declaration that is with the main customs office before the year begins; an earlier choice stays in force until it is revoked (Section 39(2) EnergieStG).

No. The duty applies to taxpayers who file annually and make advance payments (Section 8(6) StromStG, Section 39(5) EnergieStG). If their own estimate of the annual tax is below EUR 2,400, they send it only when the main customs office asks for it. The estimate is submitted in writing on the official form (Section 6(1) StromStV).

Every taxpayer filing annually makes a second estimate as of 30 June and reports it on request. It must be reported unprompted by 15 August if it exceeds EUR 100,000 and also exceeds the annual tax on which the main customs office based the advance payments by more than 20 percent. A lower estimate triggers no reporting duty; the taxpayer can instead apply for the advance payments to be set differently.

For a late return, the main customs office can impose a late filing surcharge (Section 152(1) AO); for returns covering a calendar year it is 0.25 percent per started month of the tax less advance payments, at least EUR 25 and at most EUR 25,000 (Section 152(5) and (10) AO). If the tax is not paid by the due date, a late payment surcharge of 1 percent of the rounded-down arrears applies per started month (Section 240(1) AO), except for delays of up to three days (Section 240(3) AO).

Yes. Anyone who intentionally or recklessly fails to make a notification under Section 8(6) sentences 4 to 7 StromStG, makes it incorrectly or late commits an administrative offence; the fine is up to EUR 5,000 (Section 14 StromStG). The same applies to natural gas through Section 64 no. 5 EnergieStG in conjunction with Section 381 AO. Both fine provisions have applied since 1 January 2026.

Let's collaborate

One contact, a team behind it

Thirty minutes on what you're working on, whether grid, metering, market processes, IT architecture or AI. Afterwards you'll know how we'd approach it and who would sit at the table.

Energy and measurement technology since 2010 · innobu GmbH since 2014 · Based in Schleswig-Holstein, Germany

Whoever pitches also delivers: whoever leads the first call stays your contact right through to the steering committee, with established partners in the project. Direct: info@innobu.com