Yard of a utility depot on a frosty morning: one installer loads boxes into a white van while a second checks the route sheet beside the pallet truck

Chapter 8 · Part IV: Market and practice

Rollout practice: figures, supervision and what nobody measures

The smart meter rollout in figures and on site: BNetzA statistics, 434 supervisory proceedings, the meter panel under VDE-AR-N 4100, missing data.

Updated: 24 min readDigitalising the Energy Transition
Summary

Three sets of figures are in circulation for 31 December 2025. The Federal Network Agency first reported 5.5 percent of all metering locations with a smart metering system. In September 2026 it corrected that to 4.4 percent, and for the same date it had put the share of mandatory installation cases equipped at 23.3 percent. Only the first number is wrong today. The other two measure different things.

By mid-2026 the rollout stood at 26.1 percent of the mandatory cases that count towards the quota and 5.9 percent of the total stock. 434 companies have faced supervisory proceedings since March, and by mid-September not one coercive fine had been imposed. Politically, more has been announced than decided: the coalition wants more than 90 percent by the end of 2030, and a draft regulation from the European Commission proposes targets for all final customers.

Nobody publishes how many of the devices actually deliver quarter-hour values or operate a control box.

Three figures for one reference date

On 21 September 2026 the Federal Network Agency (BNetzA) swapped two numbers on its rollout page. For 31 December 2025 it now lists 2,406,454 metering locations with an intelligent metering system (iMSys), 4.4 percent of the stock1. In spring the figures had been 3,094,346 devices and 5.5 percent23, so close to 700,000 devices have vanished on paper.

The press release of the same day says the totals were flawed and double-counted, for instance at metering locations with a PV system above 7 kW and consumption above 6,000 kWh4. A connection like that sits in two installation groups. The current survey form explicitly allows one metering location to be assigned to several groups, which is why it asks for the total number of devices in a separate question5. Add up the groups and you count twice.

The correction left the mandatory-case quota untouched: "The quotas on which the ongoing supervisory proceedings are based are not affected by this," the agency writes4. Ten days earlier the federal government had put a number on that base: 4,709,487 mandatory installation cases6.

Reference dateWhat is countediMSysBaseShare
31 Dec 2025total stock, first release3,094,34656,464,9845.5 %23
31 Dec 2025total stock, corrected2,406,454not stated4.4 %1
31 Dec 2025mandatory cases1,095,7154,709,48723.3 %6
30 Jun 2026mandatory cases1,259,2704,831,17826.1 %1
30 Jun 2026total stock3,172,57954,135,2025.9 %1
Conflicting sources

Two totals for the same day

First version, as of 27 March 2026: 5.5 percent of 56,464,984 metering locations32. The agency's version since 21 September 2026: 4.4 percent1. Older articles and slide decks don't get corrected. As late as 17 September 2026 the Bundestag's own news service wrote that households were "5.5 percent equipped with smart meters", citing a government answer that doesn't contain the figure76. Whenever you see a figure for the end of 2025, check which month the source is from and what the quota refers to.

Mandatory cases versus total stock

For 30 June 2026 the agency gives both 26.1 and 5.9 percent, on the same page1.

26.1 %
of mandatory cases had an iMSys by mid-2026
reference date 30 June 2026
5.9 %
of all metering locations were equipped on that date
a factor of 4.4 below the mandatory quota
434
companies have faced supervisory proceedings since March 2026
150 closed by 21 September 20264
0
coercive fines had been imposed by 11 September 2026
threatened: 5,000 to 500,000 euros6

The mandatory quota only counts final customers using 6,000 to 100,000 kilowatt hours a year, plus controllable consumer devices under § 14a EnWG1. The total quota takes in every metering location, the many households below that threshold included, which is why it sits lower by a factor of 4.4.

Quote only one of them and you distort the picture: at 26.1 percent the rollout looks well under way, at 5.9 percent it has barely begun, and neither impression is true.

Three sets of figures for 31 December 2025 and the status on 30 June 2026 Bar chart with shares in percent. Reference date 31 December 2025: total stock in the first release, as of March 2026, 5.5 percent, 3,094,346 iMSys out of 56,464,984 metering locations, superseded; total stock after the Federal Network Agency's correction 4.4 percent with 2,406,454 devices; mandatory installation cases 23.3 percent, 1,095,715 of 4,709,487. Reference date 30 June 2026: mandatory cases 26.1 percent, 1,259,270 of 4,831,178; total stock 5.9 percent, 3,172,579 of 54,135,202. On 30 June 2026 the mandatory quota is 4.4 times the total quota. A vertical line in the 31 December 2025 block marks the target of 20 percent of mandatory cases for that date under section 45 MsbG. A note below the chart gives the next target: by 31 December 2026, 90 percent of the metering points due for equipment since 25 February 2025 must be equipped. That is a period quota and cannot be compared with the bars. REFERENCE DATE 31 DECEMBER 2025 REFERENCE DATE 30 JUNE 2026 Total stock, first release 3,094,346 of 56,464,984 5.5 % superseded Total stock, corrected 2,406,454 iMSys 4.4 % Mandatory cases 1,095,715 of 4,709,487 23.3 % Mandatory cases 1,259,270 of 4,831,178 26.1 % Total stock 3,172,579 of 54,135,202 5.9 % 0 % Target, 31 Dec 2025 (§ 45): 20 % of mandatory cases Next target, 31 Dec 2026: 90 % of the metering points due for equipment since 25 Feb 2025. That is a period quota and cannot be compared with these bars. Factor 4.4

Open figure full size

Figure 1: The three sets of figures for 31 December 2025 and the status on 30 June 2026. Blue for mandatory cases, turquoise for the total stock, dashed for the superseded first release (as of March 2026). The vertical line marks the target of 20 percent of mandatory cases on 31 December 2025 under section 45 MsbG. It applies to each default metering point operator individually, not to the average and not to the total stock. The next target, due on 31 December 2026, covers 90 percent of the metering points that have fallen due for equipment since 25 February 2025. It is a period quota and cannot be compared with the bars.

Behind the average there's a gradient by size. The 19 operators with more than 500,000 metering locations reach an unweighted average of 29.7 percent; the 591 with fewer than 30,000, 19.2 percent1. That smallest class makes up almost three quarters of all 803 default metering point operators.

The total stock is fuzzy too. Competitive metering point operators report voluntarily, many have stopped sending data, and for them the agency plugs in historical values1. So the real total quota is probably higher, it says, without saying by how much.

How the period quota is measured

From the end of 2026 a different count matters. Chapter 1 covers the mechanics; this is about measurement. Under section 45(1) no. 4(b) MsbG, at least 90 percent of the metering points that have needed equipping since 25 February 2025 must be equipped by 31 December 20268. A second quota falls due on the same date, for generation plants, and it counts capacity: the equipped metering points must cover at least 90 percent of the capacity commissioned between 25 February 2025 and 30 September 2026, under no. 2(a)8. The government's draft for the EEG 2027 wants to switch the later plant quotas to metering points (chapter 1). For the end-2026 quota, the default operator would get to choose whether capacity or metering points count9.

The agency's survey form spells out what falls under the period quota: existing metering locations that become mandatory cases through higher consumption or a new § 14a device, plus metering locations in new buildings or newly commissioned connections5. For § 14a cases the form sets two hurdles: the case only counts with a control unit, and the unit only counts once it's integrated into the operator's systems and ready for operation; a box that's installed but not integrated counts as not equipped5. That's strict, but consistent, since a box that isn't connected controls nothing.

The agency isn't consistent about how often it measures: half-yearly, says the top of the page; quarterly, says the FAQ below it1. The law just says "regularly"8.

Supervision under section 76: 434 proceedings, no fine

On 27 March 2026 the agency opened 77 proceedings against companies that, by its figures, hadn't started the rollout yet, and called it a first step10. Six months later the count stood at 434 companies, and 150 proceedings had been closed, for instance because the quota had since been met or the default responsibility had been transferred4. The government's answer of 11 September gives 108 closures, but counts to 31 August, so the two don't contradict each other6.

Chapter 1 deals with the provision itself. In practice a proceeding moves in stages: a hearing with the chance to comment10, then an order to remedy the breach and the threat of a coercive fine, and finally the fine itself1. Section 94 EnWG, to which section 76(4) MsbG refers, sets the range at 1,000 euros to ten million euros1112. The amounts threatened so far lie between 5,000 and 500,000 euros. "No coercive fines have been imposed so far," the government replied6.

A coercive fine isn't a penalty. Its job is to force compliance, and it can be repeated and raised1. That's how an authority can run hundreds of proceedings without collecting a single euro, and whether the pressure works shows only in the closures. The government puts the delays down to operators' IT migrations, scarce hardware and an overstretched electrical trade6.

Not firmly established

The number 77: three readings, probably one group

In trade articles, 77 stands for the proceedings opened on 27 March 202610, for the companies with a quota of 0 percent among the 4344, or for default operators said not to have installed a single device by the end of 2025. The agency's table for 31 December 2025 lists exactly 77 companies at 0 percent, in both columns13. Its FAQ refers to supervisory proceedings "for the 0% companies"1. So the same group is probably meant all three times. The agency hasn't confirmed that, and "not a single device" goes further than the table, which only shows the quota for the mandatory group. By 30 June 2026, 41 companies were still at 0 percent14, not necessarily 41 of the 77. Arithmetically, 284 of the 434 proceedings were still open on 21 September; the agency itself doesn't state that difference.

Counterpoint: what a quota should count

Optional installation case is, under section 29(2) MsbG, any metering point outside the mandatory cases that the default metering point operator equips with an iMSys anyway. Under section 45(1) sentence 4, such installations reduce the number of mandatory cases the operator has to equip, as do early installations at a customer's request under section 34(2) sentence 2 no. 1158.

Until the fourth quarter of 2025 the agency published one quota per company, the one without optional installations. Only that quota showed the installation of the mandatory cases "clearly and transparently", it argued. Then the act of 18 December 2025 made clear that optional installations count towards compliance1.

Since then the table has had two columns. The supervisory proceedings use the quota with optional cases. Yet that quota "does not represent the actual state of installation in this group", the agency adds1. Some companies just get "n/a" in that column, for instance because the calculation would land above 100 percent or below zero.

Our own analysis of the table as of 18 September 2026 shows how far optional installations shift the quota14. For 743 of the 803 companies both quotas appear as numbers; the median gap is only 1.3 percentage points, and 19 companies show a gap of 20 points or more. The gap still matters for 66 companies that sit below 20 percent without optional installations and above it with them: for them, the counting method decides whether they clear the mark.

What speaks for the new count is that an iMSys in a household below the threshold is a full device: its customer can sign up for an exchange-linked tariff with it, and the law credits it to the operator. Against it: as a progress measure for the mandatory cases the quota loses precision, and the agency says as much itself. So give both values in reports, and name the column.

The barometer that never came back

"In the coming years, the progress barometer will express how the digitalisation of the energy transition has developed compared with the previous year or years." That promise was made in the edition for the reporting year 202016, and it turned out to be the last one.

It was published on 3 June 202117, with indicators frozen on 31 January 2021, overall score 44 out of 100, up from 36 the year before and 22 in the 2018 base year16. EY had rated eight key factors for what was then the Federal Ministry for Economic Affairs, from certification status to the customer view. Some sub-scores now read like a trailer for chapter 5: availability of the control unit got 25 points16.

Negative finding

No edition after reporting year 2020

No edition for 2021 or later could be found, neither at the ministry nor at the Clearingstelle EEG|KWKG. Nobody declared the series discontinued, either. For five years now there has been no annual progress measure that captures more than the installation rate.

The successor is the report under section 48 MsbG. From 30 June 2024 the ministry submits it at least every four years18; the first came out on 22 July 202419. It has no scoring system, and the next one isn't due until mid-2028: four years without an interim reading, while the next quotas fall due at the end of 2026 and the end of 2028.

Acceptance: what the evidence shows

The most recent survey commissioned by the ministry is more than five years old. For the barometer, Prolytics polled 1,000 households and 400 businesses in February and March 2021. 61 percent of households supported the rollout of modern metering devices, up from 52 percent in the survey before; among businesses, approval of smart meter installation rose from 52 to 64 percent. 43 percent of households felt poorly informed16.

Newer figures come from an industry association. Bitkom Research polled 1,002 households in April and May 2026: 69 percent said they use a smart meter or could imagine doing so, and 8 percent said they already have one. Among the households without one, 77 percent felt poorly informed20. Earlier waves polled the population rather than households, so the figures can't be compared.

Then there are the complaint statistics. In 2025 the Schlichtungsstelle Energie, the energy ombudsman, received 19,074 applications, 601 of them citing "modern metering devices", roughly 3.2 percent, with more than one reason possible per application21. iMSys aren't listed separately. For providers installing nationwide alongside the default operators, the ombudsman sees "in some cases still considerable processing and communication problems", right through to transmitting readings to the supplier21.

In the government's view, acceptance grows mainly with access to dynamic tariffs, though the same answer gives no figures to back that up6.

Negative finding

No statistics on objections or savings

There is no right to object to a mandatory installation. No central statistics are kept on complaints or objection letters received by local operators, and the agency's consumer service doesn't distinguish between enquiries and complaints6. How much households save with an iMSys is, according to the government, "not recorded statistically at a central level"6. And no survey could be found on how many customers actually use portals or apps to view their consumption.

At the meter panel

To install anything, the default metering point operator needs access, and the law covers that in four sentences. It announces the appointment at least two weeks ahead, in writing to the connection user or by a notice in the building, and offers at least one alternative date. Connection owner, connection user and plant operator then have to let it in and make sure the metering point is accessible22.

What has to fit in the meter cabinet isn't in any law. Two application rules from VDE FNN cover it. VDE-AR-N 4100, the technical connection rules for low voltage, deals among other things with meter panels and meter cabinets, direct metering up to 63 amperes and semi-indirect metering via current transformers up to 1,000 amperes, plus control, data transmission and communication equipment. The 2026-04 edition adds a new arrangement for a further distribution field in the meter panel and adjustments to the § 14a ruling BK6-22-30023. An amendment A1 has been out as a draft since June 202623.

For generation units and storage, VDE-AR-N 4105 comes on top. Its 2026-03 edition extends monitoring of the agreed feed-in power at the grid connection point down to zero export, simplifies the requirements for units up to 800 volt-amperes and sets requirements for bidirectional charging equipment24.

Both rules apply to new connections and to extensions and changes; for an existing, unchanged part of an installation they require no adaptation, as long as supply stays safe and free of disturbance2324. For fitting modern metering devices and intelligent metering systems into existing customer installations, the 4100 refers to a separate FNN note23. Since the rollout largely upgrades existing metering points, that note is the everyday document at the meter panel.

Technical standard

What comes from the standards here

Both application rules are paid documents. This section only uses what VDE-Verlag publishes about scope, content and changes. Dimensions, field layout and transitional rules are in the text of the standards2324.

Make or buy

For the 591 smallest default operators the question comes up early: what to do in-house, what to buy1. Responsibility stays put either way, because the gateway administrator isn't a market role of its own; it's a function of the metering point operator25.

Building blockWhat the rules requireWhat sticks when you buy it in
Gateway administrationThe GWA meets BSI TR-03109-6 and proves its certification to the sub-CA26; version 2.0 of the guideline applies from 2027 with the next certification27Neither the FNN note nor TR-03109-6 describes a process for switching service provider; TR-03109-1 covers only the gateway side252728
CLS management as an active external market participantISO/IEC 27001 certification, or proof that a certified third party provides the service26A provider serving several clients must separate them technically or organisationally26
Metering at individual metering pointsThe connection user may choose a third party, but not until two years after the default operator installed an iMSys29Competitive operators have no quota and report voluntarily1
Default responsibilityTransfer or cooperation; in a cooperation the metering points of all areas count together8Transfers were one of the reasons for the 150 closed proceedings4

A more radical answer to that last row comes from outside, from an interested party. The Smart-Meter-Initiative was founded in January 2024 by three electricity suppliers that sell dynamic tariffs and need metering systems for them; a fourth joined in March 202430. It sees the fragmented structure of more than 800 metering point operators as the real obstacle and calls for consolidation2. For households outside the mandatory cases it promotes a simpler "smart meter light", meant to complement the mandatory rollout rather than replace it31.

Chapters 3 and 5 cover the gateway administrator and the control box. How announcing and installing an intelligent metering system runs through market communication is in chapter 7.

The gateway administrator change

How much hangs on a change shows in an October 2024 note from FNN, the VDE's forum for network technology and operation25. It covers the case where the metering point operator changes and the new one takes over the installed gateways. In simplified form, as in figure 2, it runs like this: the old administrator fetches the new one's certificate triple from the LDAP directory, loads its public keys into the gateway's security module and sets up the new administrator's connection profiles in a separate area called "gwapre". Only then does the gateway accept the switchGWA command3228. It connects to the new administrator, which acknowledges receipt, technically with an HTTP 200 according to the FNN note25. Under the technical guideline, though, the switch isn't complete until the new administrator has authenticated to the security module3228. The note already hands over full control with the HTTP 200, but only the guideline is binding.

Gateway administrator change when the metering point operator changes and takes over the devices Simplified sequence in six lanes: new metering point operator (MSB), new gateway administrator (GWA), smart meter gateway, old gateway administrator, old metering point operator and the directory of the sub-CA in the smart metering PKI. Device takeover under WiM: 1 the new MSB requests a device takeover offer from the old one; 2 the old GWA supplies the technical device data to the old MSB; 3 the old MSB makes a takeover offer; 4 the new GWA supplies its configuration data including certificate details to the new MSB; 5 the new MSB orders the takeover with this configuration data; 6 the old MSB confirms with the remaining device data. Data handover and switch: 7 the new MSB passes the device data to its GWA; 8 the old MSB passes the new GWA's configuration data to its own GWA; 9 the old GWA fetches the new GWA's certificate triple from the sub-CA's LDAP directory, which it needs to configure the gateway; 10 it imports the new GWA's keys into the security module and sets up the new GWA's WAN communication profiles in the gwapre area; without this preparation the gateway rejects the switch command; 11 at the agreed time it triggers switchGWA on the gateway and then passes APN data if needed; 12 the gateway connects to the new GWA; 13 the new GWA acknowledges receipt, with an HTTP 200 according to the FNN note, and authenticates to the gateway's security module; only then is the switch complete and the fallback period to the old GWA over; 14 it reports success to its MSB. Completion under WiM: 15 the new MSB tells the old one when it took over metering point operation; 16 the old MSB informs its GWA that the change succeeded. New MSB takes over New GWA of new MSB SMGW in the field Old GWA of old MSB Old MSB hands over SM-PKI sub-CA, LDAP DEVICE TAKEOVER UNDER WIM DATA HANDOVER AND SWITCH ON THE GATEWAY COMPLETION UNDER WIM Request device takeover 1 Device data 2 Takeover offer 3 Configuration 4 Order incl. GWA configuration 5 Confirmation with remaining device data 6 Device data 7 New GWA data 8 Fetch new GWA certificate triple 9 gwapre profiles 10 switchGWA, APN 11 Connect 12 Authentication 13 Success notice 14 Takeover date 15 Success notice 16 Market process (WiM) Data MSB and GWA Command to gateway PKI and connection

Open figure full size

Figure 2: The gateway administrator change when the metering point operator changes and takes over the devices under WiM Strom, simplified from the VDE FNN note of October 2024. Related steps are sometimes merged into one arrow, and the SM-PKI lane is added. The preparation in the gwapre area (step 10) and authentication as the final step (step 13) follow TR-03109-1 and its annex VI. Like the source, the figure shows only the success case, not a change of the gateway administration service provider alone.

The preconditions are tough: every configuration of an external market participant on the gateway has to be ended first. Authorised market partners then order their readings again, this time from the new operator25. LTE450 has only one provider, and without separate framework contracts between it and both operators nothing works technically. Taking over SIM cards has no standard, and the note doesn't describe the error case at all. The gateway itself has a fallback: if the new administrator doesn't authenticate within the period set with the switch command, 24 hours by default, it aborts and carries on with the old administrator's keys32.

The APN, the access point into the mobile network, is switched by the old administrator only after the switch command, and only if one is used, according to the note25. In the guideline, a change of access network is a separate process in which old and new access data both stay on the gateway so it can fall back28. That makes two fallback levels, and if something fails, both switches have to be reversible, the note says25.

Revoking certificates isn't part of either sequence, the note's or the guideline's2528. All the smart metering PKI's certificate policy settles is who may revoke: until the new administrator has replaced the gateway's operational certificates with ones it requested itself, only the old one can revoke them26. For the exit contract, that means the old administrator stays involved until the certificates have been swapped.

As of October 2024 the change could not yet be handled fully automatically through market processes25. There is no newer version of the note as of October 2026. In February 2025 FNN renewed the tasks of its project group on gateway administrator system integration, which has existed since 2021; one of them is establishing the change process end to end and extending it to downstream components33. Whether the market processes now carry it fully automatically couldn't be verified.

The case that matters most for make or buy is missing from the note: WiM doesn't provide for an operator that merely switches its gateway administration provider, and the note expressly leaves it out25. By contrast, the guideline describes the gateway side with or without a change of metering point operator. For a change of access network it advises testing the sequence and agreeing the handover of all necessary data by contract28, and that clause belongs in the contract with the service provider.

Key point

If you buy in gateway administration or CLS management, settle the exit at the same time: handover of configuration data, certificate change, WAN contracts, time windows. The FNN note on the gateway administrator change doesn't cover a change of service provider.

What nobody measures

The agency's survey form asks about metering locations by consumption and capacity class, about optional installations and about control units5. What it leaves out tells you more about the rollout.

Negative finding

Gaps in the official statistics

The form doesn't ask which tariff use cases the gateways have switched on, and the rollout page gives no figure for it51; chapter 4 explains the consequences. Mandatory cases with a control unit are recorded on the form, but the agency doesn't publish a separate number, and the government's answer of 11 September 2026 doesn't give one either6. How many quarter-hour values actually reach their recipients isn't asked, nor which WAN technology connects the gateways. A minor interpellation in the Bundestag explicitly asked about fault reports, replacement numbers and failure rates since 2023. The answer gives none of these figures6.

The agency demands that the devices record and transmit quarter-hour values reliably4, but it doesn't publish whether they do. So the official statistics know whether a device hangs on the wall; whether it sends values, and whether it controls anything, each operator knows only for itself.

What comes next

First, the targets themselves are moving, in Berlin and in Brussels.

Forecast

Announced, not yet law

On 2 July 2026 the coalition committee decided to tighten the targets: "By the end of 2030 the rollout is to be more than 90 percent complete for all relevant metering points." Customers outside the mandatory rollout are to get a low-cost "smart meter light"34. The government says it is examining further changes to the Metering Point Operation Act6. According to the trade press, the economics ministry has announced the amendment for the fourth quarter of 202635. No draft could be found by early November.

Brussels adds a second yardstick, so far only as a draft. Under the Commission's proposal for a regulation of 17 July 2026, at least 50 percent of all final customers are to have a smart metering system by the end of 2030 and 75 percent by the end of 2033. A member state below 30 percent when the regulation enters into force gets one more year for each target36. That would count all final customers, not the mandatory cases. Of all figures, the total quota would become the yardstick, the one that at home only serves transparency1 and stood at 5.9 percent of metering locations in mid-2026. Final customers and metering locations aren't the same thing, though. The Bundesrat's committees recommend rejecting the draft's plan to drop the cost-benefit analysis up to the 75 percent mark37.

Beyond that, three building sites reach past the mandatory electricity rollout.

Since 1 July 2026 customers can demand early equipment at gas metering points as well, to be carried out within four months38. And a connection owner may pick a different metering point operator for an entire property if that operator bundles electricity with gas, water, district heating or space heating via the gateway at no extra cost39. Chapter 2 explains how multi-utility metering is connected technically.

In submetering a deadline is running out. Heat meters and heat cost allocators that can't be read remotely must be retrofitted or replaced by 31 December 2026. Since 1 December 2022 only devices that can be connected securely to a smart meter gateway may be installed. Under the Heating Costs Ordinance, though, they only have to be connected if the owner has chosen the bundled offer for space heating40.

Charging infrastructure has a clear mandatory case: a charge point with a § 14a agreement makes the metering point a mandatory case for an iMSys with a control unit15. What's open is the separation of energy flows. How electricity from storage and bidirectional charge points is determined and proven is set out in the agency's MiSpeL determination of 1 October 2026, and until 30 September 2027 it only applies if the grid operator and the metering point operator agree41.

Much of this chapter ends up among the open questions and negative findings the book collects at the end. For your own planning, four steps will do:

  1. Pull both quotas from the agency's table

    Note your company's quota with and without optional installations, each with its reference date and table version. The agency may still change reported values after checking them14.

  2. Recalculate the period quota yourself

    Count the metering locations that have needed equipping since 25 February 2025, using the survey form's definition. § 14a cases only count with an integrated control unit that's ready for operation.

  3. Check the exit clause in your service contract

    Does your contract with your GWA or CLS provider say how configuration and certificates are handed over if you switch, and who takes on the WAN contracts?

  4. Close your own gaps

    TAF configuration, control boxes in operation, the share of quarter-hour values received: record them yourself. The official statistics deliver none of these figures.

See it in the model

The interactive model shows where in the metering chain this chapter sits.

The model: from the meter to the billing system

Open deadlines for this chapter

Live from the deadline calendar, data as of 15 November 2026. When a deadline changes, this list changes with it.

All deadlines in the deadline calendar →

Sources

Primary sources come first. Uncertain statements are marked as uncertain in the text rather than left out.

  1. Federal Network Agency: iMSys rollout, results of the first half-yearly survey 2026 with FAQ, page as of 21 September 2026 (German). bundesnetzagentur.de, retrieved 14 October 2026.
  2. energiezukunft: Current figures on the smart meter rollout, 7 April 2026, with the Federal Network Agency's figures for 31 December 2025 as published at the time and the position of the Smart-Meter-Initiative (German). energiezukunft.eu, retrieved 14 October 2026. Trade press.
  3. German Bundestag, Research Services: Rechtliche Grenzen der Leerstandsermittlung durch Stromzählerdaten (legal limits of detecting vacancies from electricity meter data), WD 5 - 3000 - 090/26, completed 15 September 2026, section 5.2 with the Federal Network Agency's figures as of 27 March 2026 (German). bundestag.de, retrieved 15 October 2026.
  4. Federal Network Agency: press release "Bundesnetzagentur veröffentlicht halbjährliche Erhebung im Messwesen" (half-yearly metering survey published), 21 September 2026 (German). bundesnetzagentur.de, retrieved 14 October 2026.
  5. Federal Network Agency: metering survey form for the first half of 2026, sheets for default operators and notes (German). bundesnetzagentur.de, retrieved 14 October 2026.
  6. German Bundestag: answer of the federal government to the minor interpellation "Verhältnismäßigkeit und Zwangsmaßnahmen im Rahmen des Smart-Meter-Rollouts" (proportionality and coercive measures in the smart meter rollout, printed paper 21/7751), printed paper 21/7996 of 11 September 2026, answers to questions 1 to 7, 14, 15 to 21 and 30 to 41 (German). dserver.bundestag.de, retrieved 14 October 2026.
  7. German Bundestag: Smart-Meter-Ausbau geht langsam voran (smart meter rollout progressing slowly), heute im bundestag (hib) 718/2026 of 17 September 2026 (German). bundestag.de, retrieved 15 October 2026.
  8. Section 45 Metering Point Operation Act (MsbG), equipment obligations, paragraph 1 sentence 1 nos. 2 and 4, sentences 3 and 4, and paragraph 4 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  9. German Bundestag: government bill for a plannable, cost-efficient, grid-compatible and market-oriented expansion of renewable energy in the electricity sector, printed paper 21/7867 of 7 September 2026, article 3 no. 3 (p. 77) and explanatory memorandum (p. 256) (German). dserver.bundestag.de, retrieved 15 October 2026. Draft, not law.
  10. Federal Network Agency: Federal Network Agency opens proceedings over failures in the smart meter rollout, press release of 27 March 2026 (German). bundesnetzagentur.de, retrieved 14 October 2026.
  11. Section 76 MsbG, supervisory measures of the Federal Network Agency, paragraphs 1, 2 and 4 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  12. Section 94 Energy Industry Act (EnWG), coercive fine, sentence 3 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  13. Federal Network Agency: rollout quotas iMSys Q4 2025, table per default metering point operator, reference date 31 December 2025 (German). bundesnetzagentur.de, retrieved 14 October 2026. The file is no longer linked from the rollout page; the count of zero quotas is our own analysis.
  14. Federal Network Agency: rollout quotas iMSys H1 2026, table per default metering point operator, as of 18 September 2026 (German). bundesnetzagentur.de, retrieved 14 October 2026. The median, the threshold counts and the count of zero quotas are our own analysis of the reported values.
  15. Section 29 MsbG, equipment of metering points, paragraph 1 no. 2 and paragraph 2 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  16. EY for the Federal Ministry for Economic Affairs and Energy: Barometer Digitalisierung der Energiewende, reporting year 2020, pp. 5, 9, 16 to 18 and 79 (German). bundeswirtschaftsministerium.de, retrieved 14 October 2026.
  17. Clearingstelle EEG|KWKG: record of the study Barometer Digitalisierung der Energiewende 2020, dated 3 June 2021 (German). clearingstelle-eeg-kwkg.de, retrieved 14 October 2026.
  18. Section 48 MsbG, reports of the Federal Ministry for Economic Affairs and Energy, paragraph 1 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  19. Federal Ministry for Economic Affairs and Climate Action: analyses and reports under section 48 MsbG in 2024 (digitalisation report), introduction ("first digitalisation report") (German). bundeswirtschaftsministerium.de, retrieved 15 October 2026. Dated 22 July 2024 according to the record of the Clearingstelle EEG|KWKG (German). clearingstelle-eeg-kwkg.de, retrieved 14 October 2026.
  20. Bitkom: Die Digitalisierung der Energiewende (digitalising the energy transition), presentation of 30 June 2026, slides 9, 10 and 15 (Bitkom Research, telephone survey of 1,002 households, calendar weeks 16 to 20 of 2026) (German). bitkom.org, retrieved 14 October 2026. Association survey.
  21. Schlichtungsstelle Energie: activity report 2025, p. 6 and pp. 11 f. (German). schlichtungsstelle-energie.de, retrieved 14 October 2026.
  22. Section 38 of the Metering Point Operation Act, right of access (German). gesetze-im-internet.de, retrieved 18 October 2026.
  23. VDE-Verlag: VDE-AR-N 4100 application rule:2026-04, technical connection rules for low voltage (TAR NS), product description with scope, list of changes and replacement note (German). vde-verlag.de, retrieved 18 October 2026. Publisher source, text of the standard is paid.
  24. VDE-Verlag: VDE-AR-N 4105 application rule:2026-03, generation units and storage on the low-voltage grid (TAR EZA NS), product description with list of changes (German). vde-verlag.de, retrieved 18 October 2026. Publisher source, text of the standard is paid.
  25. VDE FNN: process description of a gateway administrator change when the metering point operator changes with device takeover under WiM Strom, note version 1.0, October 2024, chapters 1 to 4 (German). vde.com, retrieved 14 October 2026.
  26. Federal Office for Information Security (BSI): certificate policy of the smart metering PKI, version 1.1.2 of 25 January 2023, sections 1.3.3.4, 3.5.1.1, 5.1.1 and 5.1.2 (German). bsi.bund.de, retrieved 14 October 2026.
  27. BSI: TR-03109-6 smart meter gateway administration, version 2.0 of 28 November 2025, section 1.2 (to be applied from 1 January 2027 with the next new certification or recertification of the GWA system); it describes no process for changing the GWA or its service provider (German). bsi.bund.de, retrieved 15 October 2026.
  28. BSI: TR-03109-1, annex VI: operating processes involving the smart meter gateway, version 2.0 of 13 December 2024, section 3.11.2 (gateway administrator change with or without a change of metering point operator, preconditions and table 3.43) and section 3.11.3 (change of WAN access network) (German). bsi.bund.de, retrieved 14 October 2026.
  29. Section 5 MsbG, right of choice of the connection user, paragraph 1 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  30. Ostrom: Ostrom becomes a partner of the Smart-Meter-Initiative, statement of 7 March 2024 (German). ostrom.de, retrieved 14 October 2026. Company statement by a member.
  31. Smart-Meter-Initiative: concept paper Smart Meter Light, technical and regulatory options for a low-cost and cyber-secure rollout path outside the mandatory installation cases, July 2026, summary p. 3 (German). a.storyblok.com, retrieved 14 October 2026. Position of an interested party.
  32. BSI: TR-03109-1, version 2.0 of 13 December 2024, section 3.18 (gateway administrator change, FA.DoSwitchGwa with REQ.FA.DoSwitchGwa.10, and FA.AcceptSwitchGwa) and section 3.22.19 (switch parameters, default 86,400 seconds) (German). bsi.bund.de, retrieved 14 October 2026.
  33. VDE FNN: call for experts, project group on GWA system integration, 25 February 2025; the list of FNN notes still shows the process description of the GWA change as version 1.0 of October 2024 (German). vde.com, retrieved 14 October 2026.
  34. CDU, CSU and SPD: Ein Programm für Aufschwung und Beschäftigung (a programme for recovery and employment), result of the coalition committee of 2 July 2026, p. 7 (German). bundesregierung.de, retrieved 14 October 2026. Political declaration of intent.
  35. Zeitung für kommunale Wirtschaft: Verteilnetzpaket und Smart Meter: Worauf es jetzt ankommt (distribution grid package and smart meters, what matters now), column of 3 August 2026 (German). zfk.de, retrieved 14 October 2026. Trade press.
  36. European Commission: proposal for a regulation amending Regulation (EU) 2019/943 on future-proof electricity bills in the Union (lower system costs, more electrification and digitalisation), COM(2026) 600 final of 17 July 2026, Article 18b; Bundesrat printed paper 501/26 of 1 September 2026, p. 40 (German version). dserver.bundestag.de, retrieved 14 October 2026. Draft in procedure 2026/0203(COD), not law.
  37. Bundesrat: recommendations of the committees on COM(2026) 600, printed paper 501/1/26 of 5 October 2026, p. 3, for the plenary session of 16 October 2026 (German). dserver.bundestag.de, retrieved 14 October 2026.
  38. Section 34 MsbG, paragraph 2 sentence 2 no. 1, early equipment as an additional service (German). gesetze-im-internet.de, retrieved 14 October 2026.
  39. Section 6 MsbG, right of choice of the connection owner, paragraph 1 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  40. Section 5 Heating Costs Ordinance (HeizkostenV), equipment for recording consumption, paragraphs 2, 3 and 6 (German). gesetze-im-internet.de, retrieved 14 October 2026.
  41. Federal Network Agency: determination on the market integration of storage and charge points (MiSpeL), ref. 618-25-02 of 1 October 2026, operative provision 9 a) (German). bundesnetzagentur.de, retrieved 14 October 2026.

Further reading on innobu.com

Related tools

Contents of the handbook

  1. 1The legal framework: from the GDEW to today's MsbG
  2. 2Devices and architecture: what an intelligent metering system is
  3. 3BSI standards, certification and the smart metering PKI
  4. 4Tariff use cases: TAF 1 to 16 and version 2.0
  5. 5Grid-oriented control under § 14a EnWG
  6. 6Dynamic tariffs and grid charges in transition
  7. 7Market communication: how meter readings become processes
  8. 8Rollout practice: figures, supervision and what nobody measures
  9. +Digitalising the energy transition, explained
  10. +The model: from the meter to the billing system
  11. +Reading paths through ten topic fields and AI
  12. +Open questions and negative findings