Rooftop view over a large German city with a district-heating trench under construction, two planners reviewing the route

Heat, gas & hydrogenUpdated: 8 min read

Municipal heat planning: what the 30 June 2026 deadline means for large cities

For a municipal utility, a district-heating operator or a municipality, the municipal heat plan is the document that decides where the heat business of the next two decades will be.

The heat plan decides which districts will in future be supplied through a heat network and which stay decentralised. The 30 June 2026 deadline of the Heat Planning Act, the Wärmeplanungsgesetz (WPG), brought this to a head: by that day, 84 large German cities over 100,000 inhabitants each had to have a municipal heat plan in place. The same deadline was originally meant to trigger the 65-percent-renewables rule of the Building Energy Act, the Gebäudeenergiegesetz (GEG), for millions of households; that link was deleted with effect from 29 July 2026. The plan remains the basis of every district-heating investment decision.

The article is deliberately separate from the generation technology, the large heat pumps and power-to-heat plants that follow from the plan, and from the gas distribution grids' transformation plan, which sit close by and are touched only where the heat plan connects to them.

Summary

Municipal heat planning is the first nationwide heat-planning obligation. The Heat Planning Act, the Wärmeplanungsgesetz (WPG), full name the Act on Heat Planning and the Decarbonisation of Heat Networks, has been in force since 1 January 2024, and it required all 84 large German cities over 100,000 inhabitants to deliver a municipal heat plan by 30 June 2026; all smaller municipalities have until 30 June 2028; about 10,700 municipalities are covered in total, with the goal of a climate-neutral heat supply by 2045 at the latest. The plan follows a four-step method: a suitability check (section 14 WPG) that screens out sub-areas ruled out for a heat or hydrogen network from the start, an inventory analysis of heat demand, supply structure and greenhouse-gas emissions per sub-area, a potential analysis of locally available renewable heat, unavoidable waste heat and storage and saving potential, and a target scenario plus the zoning into prospective heat supply areas with an implementation strategy. The zoning uses four area categories: district-heating area (section 3 no. 18), hydrogen network area (section 3 no. 23, the exception in practice), area for decentralised heat supply (section 3 no. 6, individual heating such as heat pumps) and area under review (section 3 no. 10, still open). The zoning is a forecast, not a connection obligation and not a building requirement; the heat plan is explicitly legally non-binding under section 3 no. 20 WPG, and even a separate area designation under section 26 WPG does not oblige owners (section 27 WPG). The link to the Building Energy Act, the Gebäudeenergiegesetz (GEG), no longer exists: under GEG section 71(8) the 65-percent-renewables rule for heating systems in existing buildings was to apply in large cities after 30 June 2026 and in smaller municipalities after 30 June 2028. In late June 2026 the legislator moved the large-city date to 31 October 2026, and with effect from 29 July 2026 it deleted sections 71 to 73 altogether (Act of 23 July 2026, BGBl. 2026 I No. 226); the act is now called the Gebäudemodernisierungsgesetz (GModG) and no longer ties any heating obligation to the heat plan. In June 2026 the Competence Centre for Municipal Heat Transition (KWW) expected the large cities to meet the deadline; six of the ten largest cities had adopted their plan or were in final public display, about 80 percent of mid-size municipalities and over half of small ones were already working on the plan or finished. Funding runs since end 2023 not via the Kommunalrichtlinie but via federal connexity funds to the Länder, EUR 500 m for 2024 to 2028. Nationwide about 14 percent of households are supplied by near- or district heating.

84
large cities over 100,000 inhabitants with the 30 June 2026 deadline
WPG section 4
30 June 2028
deadline for all smaller municipalities under 100,000 inhabitants
WPG section 4
29 July 2026
GEG sections 71 to 73 deleted, and the 65-percent rule with them
BGBl. 2026 I No. 226
EUR 500 m
federal connexity funding for heat planning 2024 to 2028
five tranches of EUR 100 m
about 14 percent
share of households on near- or district heating nationwide
Fraunhofer / ZDFheute
about 80 percent
mid-size municipalities already working on or finished with the plan
KWW, June 2026

What applies to large cities by 30 June 2026

By 30 June 2026, all 84 German cities with more than 100,000 inhabitants had to have a municipal heat plan, the kommunaler Wärmeplan, in place; smaller municipalities have until 30 June 2028. The basis is the Heat Planning Act, the Wärmeplanungsgesetz (WPG), whose full name is the Act on Heat Planning and the Decarbonisation of Heat Networks. It has been in force since 1 January 2024 and creates, for the first time, a nationwide obligation to plan the heat supply across the whole country.

The plan answers a single strategic question: how the heat supply of each district is to become climate-neutral by 2045 at the latest. It is not a one-off study but a structured planning process whose result, the zoning of the city into prospective heat supply areas, is the foundation on which utilities, building owners and the municipality itself can take their next decisions. About 10,700 municipalities are covered in total, which makes this one of the largest planning exercises the heat transition demands.

The two-stage deadline reflects capacity rather than ambition. Large cities have more administrative resources and denser networks, so they went first, by 30 June 2026; the much larger number of smaller municipalities follows by 30 June 2028. The deadline was also meant to be the moment from which the Building Energy Act starts to bite in a given city; the legislator deleted that link in July 2026, as set out further below. For a utility, this is the point at which the strategic picture of where heat networks make sense, and where they do not, finally has a legal footing.

The four steps of heat planning

The heat plan is produced according to a method laid down in the WPG, so it is not a free-form report but a structured, data-driven process with defined intermediate results that the responsible planning body has to publish. Four steps build on one another: a suitability check, an inventory analysis, a potential analysis and a target scenario that leads into the zoning of the area and an implementation strategy.

The first step is the suitability check (section 14 WPG). This is a rough pre-screening of which sub-areas are ruled out for a heat or hydrogen network from the very start, for example because they are too thinly built up or too far from any feasible network. Those sub-areas are then planned as decentralised through a shortened procedure, which spares the municipality from running the full analysis where the answer is already clear. The second step, the inventory analysis, records the present heat demand, the supply structure and the greenhouse-gas emissions for each sub-area, so the plan starts from a factual picture of how the city is heated today.

The third step, the potential analysis, looks forward: it maps the locally available renewable heat and the unavoidable waste heat, together with the storage and saving potential of each sub-area. This is where the question of which renewable sources a district could realistically draw on is answered. The fourth step brings the strands together in a target scenario, which is then translated into the zoning of the city into prospective heat supply areas and into an implementation strategy with concrete measures and a timeline.

Each of these steps produces an intermediate result that has to be made transparent, which is what turns heat planning from an internal exercise into a shared planning basis. The figure below shows the three specialists at the centre of that work, reviewing the colour-coded heat map and the city plan that the inventory and potential analyses feed into.

In a planning office, three specialists review a colour-coded city heat map on a monitor and a printed city map
In a planning office, three specialists review a colour-coded city heat map on a monitor and a printed city map.

District-heating, review, decentralised: what the zoning means

The core result for utilities is the zoning of the city area into prospective heat supply areas. The WPG knows four categories, and they effectively decide the supply logic of a whole district. A district-heating area (section 3 no. 18) is one where a heat network exists or is planned and a significant share of final consumers is to be supplied through it, so this is the Fernwärme, the district heating, that carries the heaviest investment. A hydrogen network area (section 3 no. 23) provides supply through a hydrogen network and is the exception in practice.

The other two categories cover the rest of the map. An area for decentralised heat supply (section 3 no. 6) is one that is predominantly not supplied through a heat or gas network, so it relies on individual heating systems such as heat pumps. An area under review (section 3 no. 10) is still open, because the facts needed to decide are not yet sufficiently known, and it is the category that keeps a planning option alive where the analysis cannot yet settle the answer.

The single most important point about this zoning is what it does not do. The zoning is a forecast, not a connection obligation and not a building requirement. The heat plan is explicitly a legally non-binding, strategic specialist plan under section 3 no. 20 WPG, so the assignment of a district to one category or another does not by itself oblige any owner to connect to a network or to change a heating system. A separate area designation under section 26 WPG, a distinct legal act that the municipality has to take deliberately, does not oblige owners either; under section 27 WPG it feeds into land-use plans and other public planning. For a district-heating area, the climate-neutral generation that then follows, the large heat pumps and power-to-heat plants that supply the network, is a separate topic, covered in the analysis of power-to-heat and large heat pumps for district heating.

From suitability check to heat supply area, the four planning steps lead to the zoning of the city into four categories
From suitability check to heat supply area, the four planning steps lead to the zoning of the city into four categories.

The deleted link to the Building Energy Act

Until late July 2026 the heat plan was tied to heating law. Under section 71(8) of the Building Energy Act, the Gebäudeenergiegesetz (GEG), the 65-percent-renewables rule for newly installed heating systems in existing buildings was to apply in large cities over 100,000 inhabitants after 30 June 2026 and in smaller municipalities after 30 June 2028. A municipality could bring the rule forward through an advance area designation under section 26 WPG, in which case it applied one month after the decision was published. The planning deadline would have become the heating-law deadline as well.

That did not happen. In late June 2026 the legislator moved the large-city date to 31 October 2026 (Article 8 of the Act of 22 June 2026, BGBl. 2026 I No. 191). Four weeks later it deleted sections 71 to 73 altogether: Article 1 no. 32 of the Act of 23 July 2026, BGBl. 2026 I No. 226, has applied since 29 July 2026. Since then the act has been called the Gebäudemodernisierungsgesetz (GModG). So the 30 June 2026 deadline never triggered the 65-percent rule in the large cities.

What applies now? Section 42 GModG lists ten options for replacing a heating system, among them a heat pump, a connection to a heat network and a gas boiler; sections 43 to 46 set conditions for some of them. Owners who install a gas, oil or LPG heating system in an existing building after 29 July 2026 must ensure that at least 10 percent of its heat comes from biomethane, bio-oil, biogenic LPG or hydrogen from 2029, 15 percent from 2030, 30 percent from 2035 and 60 percent from 2040 (section 43 GModG). Nowhere does the act refer to the heat plan any more.

References to the GEG were removed from the Heat Planning Act as well (Article 8(10) of the same Act). An area designation under section 26 WPG therefore no longer triggers any heating obligation; under section 27(2) WPG it only has to be taken into account in land-use plans and other public planning. For owners the heat plan remains a guide to whether a heat network is likely in their district. Utilities now have to win connections to the heat network on price and offer rather than through heating law.

Status in June 2026 and funding

Shortly before the deadline, the large cities were on track to meet it. According to the Competence Centre for Municipal Heat Transition (KWW), whose head is Robert Brückmann, the large cities would deliver: six of the ten largest cities had adopted their plan or were in final public display, about 80 percent of mid-size municipalities and over half of small ones were already working on the plan or finished. Concrete adoptions illustrate the pace: Munich adopted its plan on 26 November 2025, Stuttgart as early as 2023, Essen on 25 March 2026 and Düsseldorf on 7 May 2026, while Hamburg, Frankfurt and Dortmund were in the final stretch in June 2026.

Baden-Württemberg was the front-runner, ahead of the federal law. Under its state climate act, the KlimaG BW, urban districts and large district towns there already had to plan by 31 December 2023, with 103 municipalities under obligation, so the south-west had completed a first round of municipal heat plans before the WPG deadline applied elsewhere. That head start is one reason several of the most advanced examples sit in that region.

The funding model changed with the WPG. Since the end of 2023, heat planning is no longer funded via the Kommunalrichtlinie, whose earlier 90-percent grant ended in mid-December 2023 when the WPG came into force. Instead, the federal government provides the Länder with EUR 500 m as a connexity settlement for the years 2024 to 2028, in five tranches of EUR 100 m each through a fixed value-added-tax amount, and the Länder pass the money on to the municipalities. The stakes behind all of this are large: nationwide about 14 percent of households are supplied by near- or district heating today, and the heat plans will decide how far that share grows.

What utilities should do now

For a utility, the heat plan is the entry ticket to any robust network-investment decision. The zoning into a district-heating area or a decentralised area defines the future business field and the order in which the build-out should happen, so the plan is not a compliance task for the municipality to handle alone but a shared data basis that will run through the heat planning data space, one that utilities should help shape and whose data quality they should secure. Treating it as someone else's paperwork is the most expensive mistake on offer.

The practical work starts with the data base. A utility should bring its heat-consumption figures, its network inventory and its load profiles into the process as a reliable foundation for the inventory and potential analyses, because the quality of the zoning is only as good as the data behind it. The second step is to prioritise build-out areas: from the zoning, derive a concrete sequence of districts and realistic connection-rate targets, so that the billions in network investment go first where the heat plan shows the strongest case.

The third step is to factor in the legal effect of an area designation. Since 29 July 2026 a designation under section 26 WPG no longer triggers any heating obligation for owners, but land-use and other public planning has to take it into account (section 27(2) WPG). It is worth checking where such a designation would secure a network build-out in planning terms, and where an area under review should deliberately stay open until the facts are clearer. The fourth step is citizen communication: making transparent early on which districts will be a heat network, an area under review or decentralised gives owners the planning certainty they need and reduces the friction that derails build-out later.

Construction of a district-heating pipeline in a residential street, a worker at the pipe joint in an open trench
Construction of a district-heating pipeline in a residential street, a worker at the pipe joint in an open trench.

Beyond the plan itself, two adjacent processes deserve a place in the utility's roadmap. The day-to-day operation of a district-heating network, once built, is increasingly run with a digital twin and AI for utilities, and the heat plan also has to mesh with the gas distribution grids' transformation plan, which decides the parallel question of where the gas network is wound down. Both sit alongside the wider regulatory framework of the energy transition that shapes the economics of the build-out.

Deadline, market roles, systems

30 June 2028WPG: heat plans for all municipalities with 100,000 inhabitants or fewerLaw · adopted

Applicability: The federal states must ensure heat plans are drawn up and usually delegate the duty to municipalities by ordinance (Section 4(1), Section 33(1) WPG); the population on 1 January 2024 is decisive. Network operators contribute data.

If the deadline is missed: No direct legal consequence The deadline binds the planning bodies, usually municipalities, not the network operators. If grid or heat network operators withhold the information owed under Section 11(1) no. 2 WPG, the planning body can order it with a deadline under Section 11(6) WPG. Legal basis ↗

  • Gas grid operatoraffectedAligns gas network areas and conversion paths with municipal heat planning.Typically affected: Grid planning, GIS, load flow
  • Heat network operatoraffectedProvides the municipality with data on network, generation and expansion plans for heat planning.Typically affected: Grid planning, GIS, load flow

A classification for typical market roles, not a review of your individual case and not legal advice. Whether an obligation applies to your company (thresholds, exemptions) is for your legal department or counsel to confirm. The calendar doesn't replace your own deadline review. Information as of: 1 November 2026.

Discuss the implementation →In the deadline calendar →

Further reading

Frequently asked questions

By 30 June 2026, all 84 German cities with more than 100,000 inhabitants had to have a municipal heat plan in place; all smaller municipalities have until 30 June 2028. The basis is the Heat Planning Act, the Wärmeplanungsgesetz (WPG), in force since 1 January 2024, which for the first time creates a nationwide obligation to plan the heat supply. About 10,700 municipalities are covered in total. The plan answers a single strategic question: how the heat supply of every sub-area is to become climate-neutral by 2045 at the latest. It does not oblige any individual building owner to do anything; it sets the strategic direction.

The core result of the heat plan is the zoning of the city into prospective heat supply areas. The WPG knows four categories: a district-heating area (section 3 no. 18), where a heat network exists or is planned and a significant share of consumers is to be supplied through it; a hydrogen network area (section 3 no. 23), the exception in practice; an area for decentralised heat supply (section 3 no. 6), with individual heating such as heat pumps; and an area under review (section 3 no. 10), still open because the necessary facts are not yet sufficiently known. The zoning is a forecast, not a connection obligation and not a building requirement.

No. The heat plan is explicitly a legally non-binding, strategic specialist plan under section 3 no. 20 WPG, and the mere zoning of an area creates no obligation for property owners. A separate area designation under section 26 WPG does not oblige owners either (section 27(1) WPG). Since 29 July 2026 it no longer triggers a heating obligation under the Building Energy Act, because sections 71 to 73 of that act were deleted on that date.

Since 29 July 2026 it no longer does. Until then, GEG section 71(8) set the date from which the 65-percent-renewables rule applied to new heating systems in existing buildings: after 30 June 2026 in large cities over 100,000 inhabitants, after 30 June 2028 in smaller municipalities, and one month after publication where a municipality had made an advance area designation under section 26 WPG. In late June 2026 the legislator moved the large-city date to 31 October 2026 (BGBl. 2026 I No. 191). The Act of 23 July 2026 (BGBl. 2026 I No. 226) then deleted sections 71 to 73 with effect from 29 July 2026 and renamed the GEG the Gebäudemodernisierungsgesetz (GModG). The GModG no longer ties requirements for new heating systems to the heat plan. Owners who install a gas or oil heating system in an existing building after 29 July 2026 must ensure a rising share of biomethane, bio-oil or hydrogen from 2029 (section 43 GModG).

Since the end of 2023, heat planning is no longer funded via the Kommunalrichtlinie, whose earlier 90-percent grant ended in mid-December 2023 with the WPG coming into force. Instead, the federal government provides the Länder with EUR 500 m as a connexity settlement for 2024 to 2028, in five tranches of EUR 100 m each through a fixed value-added-tax amount. The Länder pass the funds on to the municipalities. Baden-Württemberg was the front-runner: there, urban districts and large district towns already had to plan by 31 December 2023 under the state climate act KlimaG BW, with 103 municipalities under obligation.

Let's collaborate

One contact, a team behind it

Thirty minutes on what you're working on, whether grid, metering, market processes, IT architecture or AI. Afterwards you'll know how we'd approach it and who would sit at the table.

Energy and measurement technology since 2010 · innobu GmbH since 2014 · Based in Schleswig-Holstein, Germany

Whoever pitches also delivers: whoever leads the first call stays your contact right through to the steering committee, with established partners in the project. Direct: info@innobu.com