A desk in a regulatory affairs office with an open printed document and several plain ring binders, a hand resting on the page

The GasNZV Replacement 2026: KARLA Gas, GaBi Gas, GeLi Gas 3.0 and ZuBio

A whole ordinance is being swapped out: the Gas Grid Access Ordinance (GasNZV) expires on 31 December 2025 and gives way to four BNetzA rulings. This affects the contracts, processes and IT of the entire gas sector, with a hard deadline at the turn of the year.

The Gas Grid Access Ordinance loses its legal basis. After the CJEU judgment C-718/18, rule-setting on grid access belongs to the independent regulatory authority, and the GasNZV expires on 31 December 2025. The Bundesnetzagentur transfers its content into four rulings of Ruling Chamber 7: KARLA Gas 2.0, GaBi Gas 2.1, GeLi Gas 3.0 and ZuBio. This article explains why the ordinance is expiring, what the four rulings govern, how GeLi Gas 2.0 is distinguished from 3.0, what risks the splitting and the biogas regulatory gap carry, and what gas suppliers, grid operators and municipal utilities should do now.

Summary

The GasNZV replacement is a regulatory rebuild with a hard deadline. The trigger is the CJEU judgment C-718/18 of 2 September 2021, under which rule-setting on grid access belongs to the independent regulatory authority and not the federal government. As a result, the ordinance-making power under section 24 EnWG fell away, the Bundesnetzagentur received its own ruling power under section 29 EnWG, and the Gas Grid Access Ordinance expires on 31 December 2025. Instead of one consolidated overall regulation, BNetzA Ruling Chamber 7 replaces the ordinance with four rulings that were adopted in September 2025 and mostly take effect from 1 January 2026: KARLA Gas 2.0 (BK7-24-01-007) for capacity, GaBi Gas 2.1 (BK7-24-01-008) for balancing, GeLi Gas 3.0 (BK7-24-01-009) for supplier switching and ZuBio (BK7-24-01-010) for biogas grid access. What matters is the distinction between GeLi Gas 2.0, the real process reform of 1 April 2026, and GeLi Gas 3.0, which transfers the GasNZV rules content-neutrally. Operationally, the replacement is above all a contract and reference task: where contracts once pointed to GasNZV sections, grid connection, balancing group, supplier and capacity contracts as well as the cooperation agreement must in future point to the ruling decrees. Criticised are the splitting into four separate rulings and a regulatory gap in biogas grid connection, formerly section 33 GasNZV, for which a transitional rule until 30 June 2026 is provided. Whoever maps the four rulings cleanly and adjusts the contracts avoids legal uncertainty at the turn of the year.

Why the GasNZV is expiring

The Gas Grid Access Ordinance loses its legal basis. The trigger is the CJEU judgment C-718/18 of 2 September 2021, under which rule-setting on grid access belongs to the independent regulatory authority and not the federal government. As a result, the federal government's ordinance-making power fell away, and the GasNZV expires on 31 December 2025. Read correctly, the replacement is a regulatory rebuild with a hard deadline, not a formal footnote.

2 September 2021
CJEU ruling C-718/18
trigger of the replacement
31 December 2025
GasNZV expires
loss of legal basis
4
new BNetzA rulings
KARLA, GaBi, GeLi 3.0, ZuBio
1 January 2026
start of validity
of the rulings
16
gas transmission system operators
in Germany
30 June 2026
biogas connection transition deadline
regulatory gap, former section 33

Legally, rule-setting on grid access shifts from the ordinance maker to the authority. With the Act adapting energy industry law, the ordinance-making power under section 24 EnWG fell away, and the Bundesnetzagentur received its own ruling power under section 29 EnWG. With this, Ruling Chamber 7 takes on the task of transferring the former ordinance content into rulings. Along with the GasNZV, several ordinances lose their competence basis, and open questions remain about the democratic legitimacy of this new regulatory power.

GasNZV replacement denotes the expiry of the Gas Grid Access Ordinance on 31 December 2025 and the transfer of its content into four rulings of BNetzA Ruling Chamber 7. The background is the CJEU judgment C-718/18, which assigns rule-setting on grid access to the independent regulatory authority. The four rulings KARLA Gas 2.0, GaBi Gas 2.1, GeLi Gas 3.0 and ZuBio mostly take effect from 1 January 2026.

The four rulings at a glance

The BNetzA replaces the ordinance not with an overall regulation but with four topic-specific rulings of Ruling Chamber 7. They were adopted in September 2025 and mostly take effect from 1 January 2026. Whoever knows the four building blocks can assign their contracts and processes to each decree in a targeted way.

From the GasNZV to four BNetzA rulings
The expiring GasNZV is transferred into four topic-specific BNetzA rulings: KARLA Gas 2.0 for capacity, GaBi Gas 2.1 for balancing, GeLi Gas 3.0 for supplier switching and ZuBio for biogas grid access.
Ruling File number Content
KARLA Gas 2.0 BK7-24-01-007 Capacity: capacity rules and the handling of grid access including auction procedures
GaBi Gas 2.1 BK7-24-01-008 Balancing: balancing in gas, including the extended balancing settlement
GeLi Gas 3.0 BK7-24-01-009 Supplier switch: content-neutral transfer of the GasNZV rules, no new formats
ZuBio BK7-24-01-010 Biogas grid access: grid access for biogas including quality requirements

The split follows the major topic areas of the former ordinance. KARLA Gas 2.0 bundles capacity and grid access handling with the auction procedures, GaBi Gas 2.1 the balancing including the extended balancing settlement. GeLi Gas 3.0 transfers supplier switching content-neutrally, and ZuBio governs biogas grid access with the quality requirements. For practice this means every former GasNZV reference must in future be assigned to the matching ruling decree.

GeLi Gas 2.0 or 3.0? The distinction

The similar names cause confusion, but they mean different things. GeLi Gas 2.0 is the real process reform of supplier switching from 1 April 2026. GeLi Gas 3.0 is the purely legal transfer of the GasNZV rules into a ruling, without new processes or formats.

GeLi Gas 2.0: process reform
Substantive process and format reform
Own deadline of 1 April 2026
New identification logic and new data formats
GeLi Gas 3.0: GasNZV transfer
Part of the GasNZV replacement, one of four rulings
Content-neutral transfer of the former rules
No new processes, no new data formats

For planning this means: GeLi Gas 2.0 is the real project with new processes, formats and its own deadline, on which IT, processes and tests depend. GeLi Gas 3.0, by contrast, is a content-neutral transfer of the former GasNZV supplier-switching rules and only one of four pillars of the replacement. Whoever confuses the two plans duplicate IT projects without reason. The details of the process reform are in the innobu article on GeLi Gas 2.0 , which covers the operational reform of supplier switching on its own.

What changes for market participants

Operationally, the replacement is above all a contract and reference task. Where contracts once pointed to GasNZV sections, they must in future point to the ruling decrees. Whoever knows the affected contracts can steer the switch in a targeted way, rather than touching everything at once.

A fenced gas transmission station at the edge of farmland with painted steel pipework, valves and a small control kiosk under a grey sky
Behind the rulings stands the real grid operation: grid connection, capacity and balancing group contracts will in future point to the ruling decrees instead of GasNZV sections.

In concrete terms the switch affects grid connection, balancing group, supplier and capacity contracts as well as the gas cooperation agreement. All references from GasNZV sections to the matching ruling decrees must be switched over, as must the relevant terms and conditions. A gap analysis per process makes sense, recording which former section was transferred into which decree. The de facto deadline is 1 January 2026, from which the rulings take effect. Whoever maps this cleanly keeps contracts and processes legally sound at the turn of the year.

Challenges and risks

The rebuild brings new uncertainties. The splitting into four rulings makes the overview harder, and in biogas a real regulatory gap remains. An honest view has to name this, rather than painting the replacement only as an orderly transfer.

Instead of one consolidated overall regulation, four separate ruling decrees emerge, which creates interface and overview risks: whoever wants to check a process may have to look it up in several texts. In biogas grid connection, formerly section 33 GasNZV, a real regulatory gap remains, for which a transitional rule until 30 June 2026 is provided. On top of this comes the tight time window, because the decisions were only adopted in September 2025 but already take effect from 1 January 2026. In addition, parallel gas releases such as GeLi Gas 2.0 and the AS4 migration burden the already scarce resources.

Watch the splitting and the biogas case: Four separate rulings instead of one overall regulation raise the risk of overlooking references or assigning decrees wrongly. In biogas grid connection, formerly section 33 GasNZV, a regulatory gap opens up that is only bridged by a transitional rule until 30 June 2026. Whoever does not actively track this special case risks uncertainty precisely with connection requests.

Key point

The GasNZV replacement is not a mere change of form but brings three real risks: the splitting instead of consolidation, the biogas regulatory gap with a transition until 30 June 2026, and the deadline pressure from the decision in September 2025 and validity from January 2026. Whoever maps the four decrees cleanly, tracks the biogas special case and coordinates the parallel gas releases keeps the transition manageable.

What companies should do now

The GasNZV replacement is a compliance and contract task with a hard deadline. Whoever maps the four rulings cleanly and adjusts the contracts avoids legal uncertainty at the turn of the year. A regulatory mandatory deadline then becomes an orderly step.

Two colleagues at a meeting table comparing several printed ruling documents, one running a finger down a list
A clean mapping of the four rulings against the old GasNZV sections is the basis for switching contracts and the cooperation agreement over in good time.
  1. Obtain the four ruling texts and map them

    Obtain the four ruling texts on KARLA Gas 2.0, GaBi Gas 2.1, GeLi Gas 3.0 and ZuBio, and map each process against the old GasNZV sections. Only with this assignment can you trace which former section was transferred into which decree.

  2. Switch contracts, terms and cooperation agreement over

    Switch contracts, terms and conditions and the gas cooperation agreement over to the new rulings. Grid connection, balancing group, supplier and capacity contracts should point to the decrees by the start of validity on 1 January 2026, no longer to the expired GasNZV sections.

  3. Bundle the gas releases and separate GeLi 2.0 from 3.0

    Bundle the gas releases in a shared plan and separate GeLi Gas 3.0 cleanly from GeLi Gas 2.0. That keeps the resources where genuinely new processes arise, namely with the reform GeLi Gas 2.0, while the transfer GeLi Gas 3.0 stays content-neutral.

  4. Track the biogas special case and the transitional rule

    Actively track the biogas special case and the transitional rule until 30 June 2026. With the regulatory gap in biogas grid connection, formerly section 33 GasNZV, it is important to keep connection requests and deadlines in view until the gap is closed.

Key point

At heart the GasNZV replacement is a compliance and contract task with a regulatory clock. Whoever maps the four rulings, switches the contracts over and separates GeLi Gas 3.0 from GeLi Gas 2.0 avoids legal uncertainty at the turn of the year. Whoever wants to go deeper into supplier switching in gas sets it alongside the GeLi Gas 2.0 supplier switch from 1 April 2026 and recognises the deliberate differences.

Further reading

Frequently asked questions

Why is the GasNZV expiring? +

The Gas Grid Access Ordinance (GasNZV) loses its legal basis. The trigger is the CJEU judgment C-718/18 of 2 September 2021, under which rule-setting on grid access belongs to the independent regulatory authority and not the federal government. As a result, the ordinance-making power under section 24 EnWG fell away, and the Bundesnetzagentur received its own ruling power under section 29 EnWG. The GasNZV therefore expires on 31 December 2025.

What replaces the GasNZV from 2026? +

The Bundesnetzagentur replaces the ordinance not with a single overall regulation but with four topic-specific rulings of Ruling Chamber 7. They were adopted in September 2025 and mostly take effect from 1 January 2026: KARLA Gas 2.0, GaBi Gas 2.1, GeLi Gas 3.0 and ZuBio. With this, the former GasNZV content moves into four separate ruling decrees.

What are KARLA Gas, GaBi Gas, GeLi Gas 3.0 and ZuBio? +

The four rulings each cover one topic area of the former GasNZV. KARLA Gas 2.0 (BK7-24-01-007) governs capacity rules and the handling of grid access including auction procedures. GaBi Gas 2.1 (BK7-24-01-008) concerns balancing in gas. GeLi Gas 3.0 (BK7-24-01-009) transfers supplier switching content-neutrally. ZuBio (BK7-24-01-010) governs biogas grid access including quality requirements.

What is the difference between GeLi Gas 2.0 and GeLi Gas 3.0? +

GeLi Gas 2.0 is the substantive process and format reform of supplier switching with its own deadline of 1 April 2026 and new data formats. GeLi Gas 3.0 is part of the GasNZV replacement and transfers the former GasNZV supplier-switching rules content-neutrally into a BNetzA ruling, without new processes or formats. Whoever confuses the two plans duplicate IT projects without reason.

What must gas companies do now? +

The GasNZV replacement is above all a compliance and contract task with a hard deadline. Companies should first obtain the four ruling texts and, process by process, map them against the old GasNZV sections. After that the task is to switch contracts, terms and conditions and the gas cooperation agreement over to the rulings, to bundle the gas releases and to separate GeLi Gas 3.0 cleanly from GeLi Gas 2.0. The biogas special case with the transitional rule until 30 June 2026 belongs on the active watch list.