<?xml version="1.0" encoding="utf-8"?>
<feed xmlns="http://www.w3.org/2005/Atom" xml:lang="en">
  <title>innobu deadline calendar: new and changed (Company-wide, several roles)</title>
  <subtitle>Every change to the energy transition deadline calendar: deadlines added, dates moved, status changes, corrected obligations and legal consequences, with dates.</subtitle>
  <link rel="self" type="application/atom+xml" href="https://www.innobu.com/assets/feeds/fristen-aenderungen-en-unt.xml"/>
  <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-changes.html"/>
  <id>https://www.innobu.com/assets/feeds/fristen-aenderungen-en-unt.xml</id>
  <updated>2026-11-24T00:00:00Z</updated>
  <author><name>innobu GmbH</name><uri>https://www.innobu.com/</uri></author>
  <rights>A classification for typical market roles, not a review of your individual case and not legal advice. Whether an obligation applies to your company (thresholds, exemptions) is for your legal department or counsel to confirm. The calendar doesn&#x27;t replace your own deadline review.</rights>
  <entry>
    <title>Added: Set up an energy or environmental management system (EnEfG amendment)</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enefg-8-ems-novelle-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/enefg-8-ems-novelle-2027/neu/2026-11-24</id>
    <updated>2026-11-24T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 11 October 2027.

Under the government draft amending the EnEfG, companies with total final energy consumption above 23.6 GWh that reached this status by the end of 2025 set up an energy or environmental management system by 11 October 2027 (draft Section 8 EnEfG).

Source: https://dserver.bundestag.de/btd/21/080/2108027.pdf

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Waste heat: report to the Federal Office for Energy Efficiency by 31 March</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enefg-17-abwaerme-meldung-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/enefg-17-abwaerme-meldung-2027/neu/2026-11-24</id>
    <updated>2026-11-24T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 31 March 2027.

Companies whose total final energy consumption averaged more than 2.5 GWh over the last three calendar years send the Federal Office for Energy Efficiency the information on their waste heat every year by 31 March and update it without delay when it changes (Section 17(2) EnEfG).

Source: https://www.gesetze-im-internet.de/enefg/__17.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Data centres: publish annual information and send it to the federal government (31 March)</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enefg-13-rechenzentren-bericht-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/enefg-13-rechenzentren-bericht-2027/neu/2026-11-24</id>
    <updated>2026-11-24T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 31 March 2027.

Operators of data centres with a non-redundant rated connected load of 300 kW or more publish the information under Annex 3 EnEfG for the previous year every year by 31 March and send it to the federal government (Section 13(1) EnEfG).

Source: https://www.gesetze-im-internet.de/enefg/__13.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Data centres: power usage effectiveness (PUE) of 1.5 or lower</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enefg-11-rechenzentren-pue-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/enefg-11-rechenzentren-pue-2027/neu/2026-11-24</id>
    <updated>2026-11-24T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 July 2027.

Data centres of 300 kW or more that started operating before 1 July 2026 permanently reach an annual average power usage effectiveness of 1.5 or lower from 1 July 2027, and 1.3 or lower from 1 July 2030 (Section 11(1) EnEfG).

Source: https://www.gesetze-im-internet.de/enefg/__11.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Data centres: electricity demand met entirely from renewable sources</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enefg-11-5-rechenzentren-oekostrom-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/enefg-11-5-rechenzentren-oekostrom-2027/neu/2026-11-24</id>
    <updated>2026-11-24T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 January 2027.

From 1 January 2027, operators of data centres of 300 kW or more cover their electricity consumption entirely with electricity from renewable sources on a balance-sheet basis (Section 11(5) no. 2 EnEfG).

Source: https://www.gesetze-im-internet.de/enefg/__11.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Legal consequence changed: EU ETS 2 starts: emissions trading for buildings and transport replaces the national BEHG</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ets2-start-2028"/>
    <id>tag:innobu.com,2026-11-24:fristen/ets2-start-2028/folge/2026-11-01</id>
    <updated>2026-11-01T00:00:00Z</updated>
    <category term="folge" label="Legal consequence changed"/>
    <content type="text">Legal consequence changed: Fine possible → Money is lost.

Source: https://eur-lex.europa.eu/eli/reg/2026/667/oj

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: EU ETS 2: first surrender of allowances for 2028 emissions</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#tehg-ets2-abgabe-zertifikate-2029"/>
    <id>tag:innobu.com,2026-11-24:fristen/tehg-ets2-abgabe-zertifikate-2029/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 31 May 2029.

Regulated entities under the EU ETS 2, for example suppliers placing natural gas or heating oil on the market for buildings and transport, surrender allowances for 2028 emissions for the first time by 31 May 2029, then each year by 31 May for the previous year (Article 30k(2)(d) of Directive 2003/87/EC, applicable by virtue of Article 2 of Regulation (EU) 2026/667). The wording of Section 7(2) TEHG has not been adapted to the postponement.

Source: https://eur-lex.europa.eu/eli/reg/2026/667/oj

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: EU ETS 2: first surrender of allowances for 2028 emissions</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#tehg-ets2-abgabe-zertifikate-2029"/>
    <id>tag:innobu.com,2026-11-24:fristen/tehg-ets2-abgabe-zertifikate-2029/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Regulated entities under the EU ETS 2, for example suppliers placing natural gas or heating oil on the market for buildings and transport, surrender allowances for 2028 emissions for the first time by 31 May 2029, then each year by 31 May for the previous year (Article 30e(2) and Article 30k of the ETS Directive, transposed in Section 7(2) TEHG).

Regulated entities under the EU ETS 2, for example suppliers placing natural gas or heating oil on the market for buildings and transport, surrender allowances for 2028 emissions for the first time by 31 May 2029, then each year by 31 May for the previous year (Article 30k(2)(d) of Directive 2003/87/EC, applicable by virtue of Article 2 of Regulation (EU) 2026/667). The wording of Section 7(2) TEHG has not been adapted to the postponement.

Source: https://eur-lex.europa.eu/eli/reg/2026/667/oj

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Methane Regulation: report the methane intensity of production</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-methanintensitaet-meldung-2028"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-methanintensitaet-meldung-2028/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 5 August 2028.

By 5 August 2028 and every year thereafter, producers in the Union and importers report, for supply contracts concluded or renewed since 4 August 2024, the methane intensity of the production of the natural gas, crude oil and coal they place on the Union market (Article 29(1) Regulation (EU) 2024/1787).

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Methane Regulation: report the methane intensity of production</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-methanintensitaet-meldung-2028"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-methanintensitaet-meldung-2028/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: By 5 August 2028 and every year thereafter, importers report the methane intensity of the production of natural gas, crude oil and coal placed on the Union market under supply contracts concluded or renewed since 4 August 2024 (Article 29(1) Regulation (EU) 2024/1787).

By 5 August 2028 and every year thereafter, producers in the Union and importers report, for supply contracts concluded or renewed since 4 August 2024, the methane intensity of the production of the natural gas, crude oil and coal they place on the Union market (Article 29(1) Regulation (EU) 2024/1787).

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Methane Regulation: meet maximum methane intensity values</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-methanintensitaet-hoechstwerte-2030"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-methanintensitaet-hoechstwerte-2030/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 5 August 2030.

By 5 August 2030 and every year thereafter, producers in the Union and importers prove for supply contracts concluded or renewed after 5 August 2030 that the methane intensity of production is below the maximum values the Commission sets by delegated act (Article 29(2) Regulation (EU) 2024/1787).

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Methane Regulation: meet maximum methane intensity values</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-methanintensitaet-hoechstwerte-2030"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-methanintensitaet-hoechstwerte-2030/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: By 5 August 2030 and every year thereafter, importers prove for supply contracts concluded or renewed after 5 August 2030 that the methane intensity of production is below the maximum values the Commission sets by delegated act (Article 29(2) Regulation (EU) 2024/1787).

By 5 August 2030 and every year thereafter, producers in the Union and importers prove for supply contracts concluded or renewed after 5 August 2030 that the methane intensity of production is below the maximum values the Commission sets by delegated act (Article 29(2) Regulation (EU) 2024/1787).

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Methane Regulation: importers prove equivalent monitoring at producer level</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-importeure-gleichwertigkeit-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-importeure-gleichwertigkeit-2027/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 January 2027.

From 1 January 2027 importers prove that supply contracts for natural gas, crude oil or coal from third countries concluded or renewed since 4 August 2024 only cover volumes whose production is subject to equivalent monitoring, reporting and verification (Article 28(1) Regulation (EU) 2024/1787).

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Methane Regulation: annual importer report under Annex IX</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-importeure-anhang-ix-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-importeure-anhang-ix-2027/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 31 May 2027.

Importers of natural gas, crude oil or coal from third countries submit the information listed in Annex IX to the competent authority each year by 31 May (Article 27(1) Regulation (EU) 2024/1787).

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: KRITIS umbrella act in force</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#kritis-dach-in-kraft"/>
    <id>tag:innobu.com,2026-11-24:fristen/kritis-dach-in-kraft/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Physical resilience of critical facilities: registration with BBK and BSI, resilience plans. The original registration deadline was dropped; the ordinance will set the new one.

Physical resilience of critical facilities: registration with the BBK via the joint BSI/BBK registration facility no later than three months after a facility counts as critical (Section 8(1) KRITISDachG), plus resilience plans. When a facility counts as critical only follows from the ordinance setting the thresholds.

Source: https://www.gesetze-im-internet.de/kritisdachg/BJNR0420B0026.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Heating costs ordinance: retrofit remote reading</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#heizkostenv-fernablesung"/>
    <id>tag:innobu.com,2026-11-24:fristen/heizkostenv-fernablesung/pflicht/2026-10-25</id>
    <updated>2026-10-25T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Building owners retrofit or replace heat and hot water meters and heat cost allocators installed up to 1 December 2021 that cannot be read remotely by the end of 2026 (Section 5(3) HeizkostenV). The same duty applies to a heat supplier that bills occupants directly by their share of total consumption (Section 1(3) HeizkostenV).

Building owners retrofit or replace heat and hot water meters and heat cost allocators that cannot be read remotely and were installed up to 1 December 2021, or later as a replacement or addition within a system that is not remotely readable (Section 5(2) sentence 4 HeizkostenV), by the end of 2026 (Section 5(3) HeizkostenV). The same duty applies to a heat supplier that bills occupants directly by their share of total consumption (Section 1(3) HeizkostenV).

Source: https://www.gesetze-im-internet.de/heizkostenv/__5.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: German NIS2 implementation act in force</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#nis2-in-kraft"/>
    <id>tag:innobu.com,2026-11-24:fristen/nis2-in-kraft/pflicht/2026-10-23</id>
    <updated>2026-10-23T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Applies without a transition period: registration, risk management, reporting within 24 and 72 hours, management liability.

In force since 6 December 2025 with no general implementation period: registration within three months (Section 33 BSIG; network operators outside NIS2 by 6 March 2026 under Section 5d(4) EnWG), risk management, reporting within 24 and 72 hours, management liability.

Source: https://www.recht.bund.de/bgbl/1/2025/301/VO.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: SAP ECC and IS-U: end of mainstream maintenance</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#is-u-wartungsende"/>
    <id>tag:innobu.com,2026-11-24:fristen/is-u-wartungsende/pflicht/2026-10-23</id>
    <updated>2026-10-23T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Extended maintenance until 2030 at a surcharge. Migrations to S/4HANA Utilities take 18 to 36 months.

After that, extended maintenance until the end of 2030 at a premium of two percentage points on the maintenance basis, followed by customer-specific maintenance.

Source: https://support.sap.com/en/release-upgrade-maintenance/maintenance-information/maintenance-strategy/s4hana-business-suite7.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Heating costs ordinance: retrofit remote reading</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#heizkostenv-fernablesung"/>
    <id>tag:innobu.com,2026-11-24:fristen/heizkostenv-fernablesung/pflicht/2026-10-23</id>
    <updated>2026-10-23T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Heat suppliers retrofit or replace meters installed before 5 October 2021 that cannot be read remotely (FFVAV). Building owners do the same for heat and hot water meters and heat cost allocators (Heating Costs Ordinance).

Building owners retrofit or replace heat and hot water meters and heat cost allocators that cannot be read remotely and were installed up to 1 December 2021, or later as a replacement or addition within a system that is not remotely readable (Section 5(2) sentence 4 HeizkostenV), by the end of 2026 (Section 5(3) HeizkostenV). The same duty applies to a heat supplier that bills occupants directly by their share of total consumption (Section 1(3) HeizkostenV).

Source: https://www.gesetze-im-internet.de/heizkostenv/__5.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: BSIG § 39: first evidence for critical installations</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#bsig-39-nachweis"/>
    <id>tag:innobu.com,2026-11-24:fristen/bsig-39-nachweis/pflicht/2026-10-23</id>
    <updated>2026-10-23T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Operators of critical installations must prove their security measures through an audit, review or certification, then every three years. The BSI sets the date, at the earliest three years after the installation counts as critical.

Operators of critical installations must prove their security measures through an audit, review or certification, then every three years. The BSI sets the date, at the earliest three years after the installation counts as critical; for existing KRITIS operators at the earliest three years after their last audit under the former Section 8a(3) BSIG (Section 39(3) BSIG).

Source: https://www.gesetze-im-internet.de/bsig_2025/__39.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Title changed: EU AI Act: transparency duties under Art. 50</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ai-act-klassifizierung"/>
    <id>tag:innobu.com,2026-11-24:fristen/ai-act-klassifizierung/titel/2026-10-17</id>
    <updated>2026-10-17T00:00:00Z</updated>
    <category term="titel" label="Title changed"/>
    <content type="text">Title changed.

Before: EU AI Act: classification and transparency obligations

Source: https://eur-lex.europa.eu/eli/reg/2024/1689/oj/deu

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: EU AI Act: transparency duties under Art. 50</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ai-act-klassifizierung"/>
    <id>tag:innobu.com,2026-11-24:fristen/ai-act-klassifizierung/pflicht/2026-10-17</id>
    <updated>2026-10-17T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: AI systems must be classified, transparency obligations apply. High-risk requirements follow in stages.

Since 2 August 2026 the Art. 50 transparency duties apply: a chatbot or voicebot must be recognisable as AI, and generated content must be marked in a machine-readable way. For systems placed on the market before that date, the Art. 50(2) marking applies from 2 December 2026.

Source: https://eur-lex.europa.eu/eli/reg/2024/1689/oj/deu

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: EU AI Act: high-risk requirements, Annex III</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ai-act-annex-iii"/>
    <id>tag:innobu.com,2026-11-24:fristen/ai-act-annex-iii/pflicht/2026-10-17</id>
    <updated>2026-10-17T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: AI in critical infrastructure and grid operations falls under Annex III; the BNetzA becomes market surveillance authority.

From 2 December 2027 the high-risk duties apply to Annex III systems, such as credit checks and applicant screening. Under the Commission&#x27;s draft guidelines of 19 May 2026, grid AI is only covered where, as a safety component, it directly protects the asset and the operator is designated a critical entity. The Bundesnetzagentur has been the supervisory authority since 29 July 2026.

Source: https://eur-lex.europa.eu/eli/reg/2026/1744/oj

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Capacity market (StromVKG): first technology-open capacity auction</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#stromvkg-kapazitaeten-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/stromvkg-kapazitaeten-2027/neu/2026-09-28</id>
    <updated>2026-09-28T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 December 2027.

The first capacity auction takes place on 1 December 2027, open to generation plants, electricity storage, controllable loads and plant pools. Prequalification with the responsible transmission system operator is required first; applications are only possible from the seventh to the fifth month before the bid date.

Source: https://www.gesetze-im-internet.de/stromvkg/BJNR0D2AB0026.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Customer installations: transition period for existing installations ends</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#kundenanlagen-regulierung-2029"/>
    <id>tag:innobu.com,2026-11-24:fristen/kundenanlagen-regulierung-2029/neu/2026-09-28</id>
    <updated>2026-09-28T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 January 2029.

For customer installations under Section 3 nos. 65 and 66 EnWG connected by 23 December 2025, grid regulation rules only apply from 1 January 2029. Operators of such installations clarify by then whether and which regulatory requirements apply to them.

Source: https://www.gesetze-im-internet.de/enwg_2005/__118.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: EU ETS 2 starts: emissions trading for buildings and transport replaces the national BEHG</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ets2-start-2028"/>
    <id>tag:innobu.com,2026-11-24:fristen/ets2-start-2028/neu/2026-09-28</id>
    <updated>2026-09-28T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 January 2028.

The regular phase of EU ETS 2 starts on 1 January 2028; the first surrender of allowances for 2028 emissions is due by 31 May 2029. Reporting and surrender duties under the national BEHG continue through 2027.

Source: https://eur-lex.europa.eu/eli/reg/2026/667/oj

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Heating costs ordinance: retrofit remote reading</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#heizkostenv-fernablesung"/>
    <id>tag:innobu.com,2026-11-24:fristen/heizkostenv-fernablesung/pflicht/2026-09-23</id>
    <updated>2026-09-23T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: All heat and hot water meters must be remotely readable; FFVAV requires the same for suppliers.

Building owners retrofit or replace heat and hot water meters and heat cost allocators that cannot be read remotely and were installed up to 1 December 2021, or later as a replacement or addition within a system that is not remotely readable (Section 5(2) sentence 4 HeizkostenV), by the end of 2026 (Section 5(3) HeizkostenV). The same duty applies to a heat supplier that bills occupants directly by their share of total consumption (Section 1(3) HeizkostenV).

Source: https://www.gesetze-im-internet.de/heizkostenv/__5.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: KI-MIG: the Bundesnetzagentur becomes market surveillance authority</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ki-mig-in-kraft"/>
    <id>tag:innobu.com,2026-11-24:fristen/ki-mig-in-kraft/neu/2026-09-11</id>
    <updated>2026-09-11T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 29 July 2026.

For AI systems in critical infrastructure and in HR, the Bundesnetzagentur is the supervisor, contact point and complaints body. Anyone using AI in grid operations or customer service now has a German counterpart for evidence and complaints.

Source: https://www.bundesnetzagentur.de/SharedDocs/Pressemitteilungen/DE/2026/20260729_KI_VO.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: BSIG § 39: first evidence for critical installations</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#bsig-39-nachweis"/>
    <id>tag:innobu.com,2026-11-24:fristen/bsig-39-nachweis/neu/2026-09-11</id>
    <updated>2026-09-11T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 6 December 2028.

Operators of critical installations must prove their security measures through an audit, review or certification, then every three years. The BSI sets the date, at the earliest three years after the installation counts as critical; for existing KRITIS operators at the earliest three years after their last audit under the former Section 8a(3) BSIG (Section 39(3) BSIG).

Source: https://www.gesetze-im-internet.de/bsig_2025/__39.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: EU AI Act: labelling duty extends to AI already in use</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ai-act-kennzeichnung-bestand"/>
    <id>tag:innobu.com,2026-11-24:fristen/ai-act-kennzeichnung-bestand/pflicht/2026-09-11</id>
    <updated>2026-09-11T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: The four month transition period ends. Generative AI systems placed on the market before 2 August 2026 must mark their output in machine readable form, which covers chatbots and text generators in utility customer service.

The four-month transition period ends. Generative AI systems placed on the market before 2 August 2026 must mark their output in machine-readable form.

Source: https://eur-lex.europa.eu/eli/reg/2026/1744/oj/deu

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: EU AI Act: labelling duty extends to AI already in use</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#ai-act-kennzeichnung-bestand"/>
    <id>tag:innobu.com,2026-11-24:fristen/ai-act-kennzeichnung-bestand/neu/2026-09-10</id>
    <updated>2026-09-10T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 2 December 2026.

The four-month transition period ends. Generative AI systems placed on the market before 2 August 2026 must mark their output in machine-readable form.

Source: https://eur-lex.europa.eu/eli/reg/2026/1744/oj/deu