<?xml version="1.0" encoding="utf-8"?>
<feed xmlns="http://www.w3.org/2005/Atom" xml:lang="en">
  <title>innobu deadline calendar: new and changed (Storage operator)</title>
  <subtitle>Every change to the energy transition deadline calendar: deadlines added, dates moved, status changes, corrected obligations and legal consequences, with dates.</subtitle>
  <link rel="self" type="application/atom+xml" href="https://www.innobu.com/assets/feeds/fristen-aenderungen-en-spb.xml"/>
  <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-changes.html"/>
  <id>https://www.innobu.com/assets/feeds/fristen-aenderungen-en-spb.xml</id>
  <updated>2026-11-24T00:00:00Z</updated>
  <author><name>innobu GmbH</name><uri>https://www.innobu.com/</uri></author>
  <rights>A classification for typical market roles, not a review of your individual case and not legal advice. Whether an obligation applies to your company (thresholds, exemptions) is for your legal department or counsel to confirm. The calendar doesn&#x27;t replace your own deadline review.</rights>
  <entry>
    <title>Added: Market master data register: register a new plant</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mastr-einheit-registrierung"/>
    <id>tag:innobu.com,2026-11-24:fristen/mastr-einheit-registrierung/neu/2026-11-24</id>
    <updated>2026-11-24T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date: within 1 month after.

Operators register units, for example for generation and storage, and EEG plants in the market master data register within one month of commissioning, and CHP plants within one month of starting or, after modernisation, resuming continuous operation (Section 5(5) MaStRV).

Source: https://www.gesetze-im-internet.de/mastrv/__5.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: MiSpeL: ruling on market integration of storage and charging points</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-festlegung"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-festlegung/pflicht/2026-11-15</id>
    <updated>2026-11-15T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: The Federal Network Agency adopted the ruling on 1 October 2026 (ref. 618-25-02). A demarcation option and a flat-rate option set how volumes at storage units and charging points in mixed use are split for EEG support and levy privileges.

The Federal Network Agency adopted the ruling on 1 October 2026 (ref. 618-25-02). A demarcation option and a flat-rate option set how volumes at storage units and charging points in mixed use are split for EEG support and levy privileges. The ruling was published in the Official Gazette on 7 October 2026 and takes effect upon notification (operative point 8).

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Legal consequence changed: AgNes: dynamic network charge for battery storage at levels 1 to 5</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#agnes-dynamisches-netzentgelt-speicher-2033"/>
    <id>tag:innobu.com,2026-11-24:fristen/agnes-dynamisches-netzentgelt-speicher-2033/folge/2026-11-15</id>
    <updated>2026-11-15T00:00:00Z</updated>
    <category term="folge" label="Legal consequence changed"/>
    <content type="text">Legal consequence changed: Regulator can enforce → Fine possible.

Source: https://www.bundesnetzagentur.de/DE/Beschlusskammern/1_GZ/GBK-GZ/2025/GBK-25-01-1x3_AgNes/Downloads/FL-Entwurf_DE_DL_BF.pdf?__blob=publicationFile&amp;v=7

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: MiSpeL: end of the transition period</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-uebergang-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-uebergang-2027/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Until the end of September 2027 the demarcation option and the flat-rate option can be used only with the consent of the grid operator and the metering operator. Both use that period to set up metering, data delivery and billing for the two options.

Until the end of September 2027 the demarcation option and the flat-rate option can be used only with the consent of the grid operator and the metering operator; the flat-rate option also only after state aid approval for Section 19(3c) EEG. Both use that period to set up metering, data delivery and billing for the two options.

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Methane Regulation: verified report with site-level measurements</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-standortmessung-bericht-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-standortmessung-bericht-2027/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 5 February 2027.

Operators and undertakings in gas transmission, gas distribution, underground storage and LNG submit by 5 February 2027 a report on source-level methane emissions with site-level measurements for operated assets, assessed by a verifier, then each year by 31 May (Article 12(3) Regulation (EU) 2024/1787). For non-operated assets the German version gives 5 February 2028, while the English and other language versions give 5 August 2028.

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Methane Regulation: verified report with site-level measurements</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-standortmessung-bericht-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-standortmessung-bericht-2027/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Operators in gas transmission, gas distribution, underground storage and LNG submit by 5 February 2027 a report on source-level methane emissions with site-level measurements for operated assets, assessed by a verifier, then each year by 31 May; for non-operated assets first by 5 February 2028 (Article 12(3) Regulation (EU) 2024/1787).

Operators and undertakings in gas transmission, gas distribution, underground storage and LNG submit by 5 February 2027 a report on source-level methane emissions with site-level measurements for operated assets, assessed by a verifier, then each year by 31 May (Article 12(3) Regulation (EU) 2024/1787). For non-operated assets the German version gives 5 February 2028, while the English and other language versions give 5 August 2028.

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Methane Regulation: emissions report for non-operated assets</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#methan-vo-quellenbericht-fremdbetrieb-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/methan-vo-quellenbericht-fremdbetrieb-2027/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 5 February 2027.

Operators and undertakings in gas transmission, gas distribution, underground storage and LNG submit by 5 February 2027 a report quantifying source-level methane emissions for non-operated assets (Article 12(2)(b) Regulation (EU) 2024/1787). For operated assets the deadline was 5 February 2026.

Source: https://eur-lex.europa.eu/legal-content/DE/TXT/?uri=CELEX:32024R1787

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Gas storage: 80 per cent fill level on 1 November, 30 per cent on 1 February</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enwg-35b-gasspeicher-fuellstand-2026"/>
    <id>tag:innobu.com,2026-11-24:fristen/enwg-35b-gasspeicher-fuellstand-2026/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 November 2026.

Gas storage operators ensure by contract that each facility is filled to 80 per cent of its working gas volume on 1 November 2026 and to 30 per cent on 1 February 2027. The Gas Storage Fill Level Ordinance sets these values in place of the 90 per cent in Section 35b(1) sentence 2 EnWG; Bad Lauchstädt, Frankenthal, Hähnlein, Rehden, Stockstadt and Uelsen need 45 per cent on 1 November, Bierwang, Breitbrunn, Inzenham-West and Wolfersberg 40 per cent on 1 February (Section 1 GasSpFüllstV). The ordinance and the fill level rules apply until the end of 31 March 2027 (Section 2 GasSpFüllstV, Section 35i EnWG).

Source: https://www.gesetze-im-internet.de/gasspf_llstv_2025/__1.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Title changed: Gas storage: 80 per cent fill level on 1 November, 30 per cent on 1 February</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enwg-35b-gasspeicher-fuellstand-2026"/>
    <id>tag:innobu.com,2026-11-24:fristen/enwg-35b-gasspeicher-fuellstand-2026/titel/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="titel" label="Title changed"/>
    <content type="text">Title changed.

Before: Gas storage: 90 percent fill level on 1 November, 30 percent on 1 February

Source: https://www.gesetze-im-internet.de/gasspf_llstv_2025/__1.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: Gas storage: 80 per cent fill level on 1 November, 30 per cent on 1 February</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enwg-35b-gasspeicher-fuellstand-2026"/>
    <id>tag:innobu.com,2026-11-24:fristen/enwg-35b-gasspeicher-fuellstand-2026/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Gas storage operators ensure by contract that each facility is filled to 90 percent of its working gas volume on 1 November 2026 and to 30 percent on 1 February 2027 (Section 35b(1) sentence 2 EnWG), unless a regulation under Section 35b(3) sets other values. The provision applies until the end of 31 March 2027 (Section 35i EnWG).

Gas storage operators ensure by contract that each facility is filled to 80 per cent of its working gas volume on 1 November 2026 and to 30 per cent on 1 February 2027. The Gas Storage Fill Level Ordinance sets these values in place of the 90 per cent in Section 35b(1) sentence 2 EnWG; Bad Lauchstädt, Frankenthal, Hähnlein, Rehden, Stockstadt and Uelsen need 45 per cent on 1 November, Bierwang, Breitbrunn, Inzenham-West and Wolfersberg 40 per cent on 1 February (Section 1 GasSpFüllstV). The ordinance and the fill level rules apply until the end of 31 March 2027 (Section 2 GasSpFüllstV, Section 35i EnWG).

Source: https://www.gesetze-im-internet.de/gasspf_llstv_2025/__1.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: EnFG: report on storage and charging points with reduced levies for 2026</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#enfg-21-7-speicher-ladepunkte-mitteilung-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/enfg-21-7-speicher-ladepunkte-mitteilung-2027/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 31 May 2027.

For grid withdrawals into storage and charging points claiming reduced levies under Section 21 EnFG, the report under Section 52(1) EnFG must be made by 31 May of the following year at the latest (Section 21(7) EnFG), i.e. by 31 May 2027 for 2026.

Source: https://www.gesetze-im-internet.de/enfg/__21.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: EEG innovation tender: bid date 1 May 2027, bids by 3 May 2027</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#eeg-innovationsausschreibung-2027-05"/>
    <id>tag:innobu.com,2026-11-24:fristen/eeg-innovationsausschreibung-2027-05/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 May 2027.

Bids must reach the Federal Network Agency by the bid date; the dates are set by law (Section 28e(1) EEG): 1 May and 1 September, until 2028. 1 May 2027 is a Saturday and a public holiday, so the submission period ends on Monday, 3 May 2027 (Sections 188 and 193 BGB).

Source: https://www.gesetze-im-internet.de/eeg_2014/__28e.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Date moved: EEG innovation tender: bid date 1 May 2027, bids by 3 May 2027</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#eeg-innovationsausschreibung-2027-05"/>
    <id>tag:innobu.com,2026-11-24:fristen/eeg-innovationsausschreibung-2027-05/termin/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="termin" label="Date moved"/>
    <content type="text">Date moved: 1 May 2027 → 3 May 2027.

Source: https://www.gesetze-im-internet.de/eeg_2014/__28e.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Title changed: EEG innovation tender: bid date 1 May 2027, bids by 3 May 2027</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#eeg-innovationsausschreibung-2027-05"/>
    <id>tag:innobu.com,2026-11-24:fristen/eeg-innovationsausschreibung-2027-05/titel/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="titel" label="Title changed"/>
    <content type="text">Title changed.

Before: EEG innovation tender: bid date 1 May 2027

Source: https://www.gesetze-im-internet.de/eeg_2014/__28e.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: EEG innovation tender: bid date 1 May 2027, bids by 3 May 2027</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#eeg-innovationsausschreibung-2027-05"/>
    <id>tag:innobu.com,2026-11-24:fristen/eeg-innovationsausschreibung-2027-05/pflicht/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Bids must reach the Federal Network Agency by the bid date; the dates are set by law (Section 28e(1) EEG): 1 May and 1 September, until 2028.

Bids must reach the Federal Network Agency by the bid date; the dates are set by law (Section 28e(1) EEG): 1 May and 1 September, until 2028. 1 May 2027 is a Saturday and a public holiday, so the submission period ends on Monday, 3 May 2027 (Sections 188 and 193 BGB).

Source: https://www.gesetze-im-internet.de/eeg_2014/__28e.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: AgNes: proof of the final investment decision for grandfathering</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#agnes-investitionsentscheidung-nachweis-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/agnes-investitionsentscheidung-nachweis-2027/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 31 March 2027.

Operators of generation plants, battery storage, pumped storage and electrolysers that rely on a final investment decision taken before publication for the charging rules prove it to the responsible network operator by 31 March 2027 (AgNes draft ruling, operative points 17.4 to 17.7).

Source: https://www.bundesnetzagentur.de/DE/Beschlusskammern/1_GZ/GBK-GZ/2025/GBK-25-01-1x3_AgNes/Downloads/FL-Entwurf_DE_DL_BF.pdf?__blob=publicationFile&amp;v=7

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: AgNes: dynamic network charge for battery storage at levels 1 to 5</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#agnes-dynamisches-netzentgelt-speicher-2033"/>
    <id>tag:innobu.com,2026-11-24:fristen/agnes-dynamisches-netzentgelt-speicher-2033/neu/2026-10-27</id>
    <updated>2026-10-27T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 January 2033.

Network operators set up a dynamic network charge and bill it to battery storage operators at grid and transformer levels 1 to 5 from 1 January 2033 at the latest, not before 1 January 2030 (AgNes draft ruling, operative point 12.2 sentence 1, subject to the condition in operative point 12.3).

Source: https://www.bundesnetzagentur.de/DE/Beschlusskammern/1_GZ/GBK-GZ/2025/GBK-25-01-1x3_AgNes/Downloads/FL-Entwurf_DE_DL_BF.pdf?__blob=publicationFile&amp;v=7

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: MiSpeL: end of the transition period</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-uebergang-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-uebergang-2027/neu/2026-10-04</id>
    <updated>2026-10-04T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 30 September 2027.

Until the end of September 2027 the demarcation option and the flat-rate option can be used only with the consent of the grid operator and the metering operator; the flat-rate option also only after state aid approval for Section 19(3c) EEG. Both use that period to set up metering, data delivery and billing for the two options.

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Status changed: MiSpeL: ruling on market integration of storage and charging points</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-festlegung"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-festlegung/status/2026-10-04</id>
    <updated>2026-10-04T00:00:00Z</updated>
    <category term="status" label="Status changed"/>
    <content type="text">Status changed: planned → fixed.

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: MiSpeL: ruling on market integration of storage and charging points</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-festlegung"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-festlegung/pflicht/2026-10-04</id>
    <updated>2026-10-04T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: The Federal Network Agency plans to publish the ruling with a demarcation option and a flat-rate option for storage and charging points in mixed use. It sets how volumes are separated for EEG support and levy privileges.

The Federal Network Agency adopted the ruling on 1 October 2026 (ref. 618-25-02). A demarcation option and a flat-rate option set how volumes at storage units and charging points in mixed use are split for EEG support and levy privileges. The ruling was published in the Official Gazette on 7 October 2026 and takes effect upon notification (operative point 8).

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Capacity market (StromVKG): first technology-open capacity auction</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#stromvkg-kapazitaeten-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/stromvkg-kapazitaeten-2027/neu/2026-09-28</id>
    <updated>2026-09-28T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 1 December 2027.

The first capacity auction takes place on 1 December 2027, open to generation plants, electricity storage, controllable loads and plant pools. Prequalification with the responsible transmission system operator is required first; applications are only possible from the seventh to the fifth month before the bid date.

Source: https://www.gesetze-im-internet.de/stromvkg/BJNR0D2AB0026.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: Electricity storage: commissioning deadline for the grid fee exemption under Section 118(6) EnWG</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#speicher-netzentgeltbefreiung-2029"/>
    <id>tag:innobu.com,2026-11-24:fristen/speicher-netzentgeltbefreiung-2029/neu/2026-09-28</id>
    <updated>2026-09-28T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 4 August 2029.

Electricity storage commissioned within 18 years from 4 August 2011 is exempt for 20 years from grid fees on electricity drawn for storage. The exemption only applies to the extent the stored electricity is fed back into the same grid with a time delay.

Source: https://www.gesetze-im-internet.de/enwg_2005/__118.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Added: REMIT II: new reporting formats and first exposure report</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#remit-meldungen-2027"/>
    <id>tag:innobu.com,2026-11-24:fristen/remit-meldungen-2027/neu/2026-09-28</id>
    <updated>2026-09-28T00:00:00Z</updated>
    <category term="neu" label="Added"/>
    <content type="text">Added: Date 29 October 2027.

From 29 October 2027 the new data fields apply to continuous transaction reporting to ACER. Market participants with positions of 600 GWh per year or more report exposures quarterly, first in October 2027; balancing service transactions must be reported monthly from 29 April 2028.

Source: https://eur-lex.europa.eu/eli/reg_impl/2026/256/oj

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Status changed: MiSpeL: ruling on market integration of storage and charging points</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-festlegung"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-festlegung/status/2026-09-23</id>
    <updated>2026-09-23T00:00:00Z</updated>
    <category term="status" label="Status changed"/>
    <content type="text">Status changed: fixed → planned.

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>
  </entry>
  <entry>
    <title>Obligation text changed: MiSpeL: ruling on market integration of storage and charging points</title>
    <link rel="alternate" type="text/html" href="https://www.innobu.com/en/deadline-calendar-energy-transition.html#mispel-festlegung"/>
    <id>tag:innobu.com,2026-11-24:fristen/mispel-festlegung/pflicht/2026-09-23</id>
    <updated>2026-09-23T00:00:00Z</updated>
    <category term="pflicht" label="Obligation text changed"/>
    <content type="text">Obligation text changed.

Before: Balancing and grid charges for storage and bidirectional charging points; MaKo automation only from 2027.

The Federal Network Agency adopted the ruling on 1 October 2026 (ref. 618-25-02). A demarcation option and a flat-rate option set how volumes at storage units and charging points in mixed use are split for EEG support and levy privileges. The ruling was published in the Official Gazette on 7 October 2026 and takes effect upon notification (operative point 8).

Source: https://www.bundesnetzagentur.de/DE/Fachthemen/ElektrizitaetundGas/ErneuerbareEnergien/EEG_Aufsicht/MiSpeL/start.html

Note: A classification for typical market roles, not a review of your individual case and not legal advice. The calendar doesn&#x27;t replace your own deadline review.</content>